Home > Lucent Technologies > Communications System > Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual

Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual

    Download as PDF Print this page Share this page

    Have a look at the manual Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 413 Lucent Technologies manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    Page
    of 502
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-13 Task Tables 
    5
    Table 5-5. Tasks to Upgrade to Release 8r — Critical Reliability
    áTask Description Page
    Upgrade Cabinets
    5-75
    Follow Routine Preventive Maintenance5-76
    Label Cables5-76
    Check Link Status5-77
    Disable TTI5-77
    Power Down G2 System5-77
    Install Power-Failure Transfer Ground Wire5-77
    Disconnect Cables5-78
    Remove Circuit Packs from Module Control Carriers A and B5-78
    Remove CURL from Module Control Carrier A5-78
    Remove Module Control Carriers A and B5-79
    Prepare the New A and B Position Carriers5-83
    Install the New A and B Position Carriers5-84
    Test the CURL5-90
    Install Circuit Packs5-90
    Interconnect Port Networks — Critical Reliability5-91
    Verify Usable Circuit Pack Vintages5-105
    Remove Power-Failure Ground Strap5-106
    Boot the Release 8 System5-106
    Set Daylight Savings Rules5-107
    Set Date and Time5-108
    Set Additional Administration5-110
    Close Upgraded EPN Cabinet and Reconnect Cables5-110
    Power Up the EPN Cabinets5-111
    Retranslate Port Circuits5-111
    Enable TTI5-111
    Check Link Status5-111
    Enable Scheduled Maintenance5-111
    Continued on next page 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-14 Task Tables 
    5
    Resolve Alarms5-112
    Enable Customer Options and Alarm Origination5-112
    Save Translations5-113
    Back Up Disk5-113
    Return Replaced Equipment5-113
    Table 5-5. Tasks to Upgrade to Release 8r — Critical Reliability
     — Continued
    áTask Description Page
    Continued on next page 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-15 Standard Reliability 
    5
    Standard Reliability 
    Required Hardware
    The equipment in Table 5-6 must be on-site b efore the up g rad e beg ins. To p lac e 
    a c laim for missing  eq uip ment, as p art of the Streamlined  Imp lementation 
    p roc ess, c all 1-800-772-5409, or the numb er p rovid ed  b y your Luc ent 
    Tec hnolog ies rep resentative.
    Table 5-6. Required Hardware
    Equipment Description Quantity
    PEC 6300-05X Proc essor Port Network 1
    J58890AF-1 Expansion Control Carrier 1
    106647985 TN775B Maintenanc e  1
    103557294
    or
    103281788TN776 Exp ansion Interfac e
    TN570 Exp ansion Interfac e2 or 6 
    1
    2 or 6 1,2
    1.Depend ing  on the numb er of Release 8 EPNs. Two are req uired for a stand ard  
    reliab ility system with 2 p ort networks; 6 with 3 p ort networks. Either 1 or 4 Exp ansion 
    Interfac es (EIs) are ship p ed loose with the EPN equipment. The fac tory has installed  
    either 1 or 2 EIs in the new PPN.
    2. Required  p ort network interfac es in a Release 8 system with the optional p acket b us.
    407439975 20-Foot Multi-mod e Fib er Op tic  Cab le 1 or 3 3
    3. Depend ing  on the numb er of DEFINITY ECS Release 8 EPNs. Two or 6 are req uired  
    if the PPN and  EPN(s) are remotely loc ated . Assuming  ac cep tab le leng ths, the fiber 
    that previously connec ted  an up g raded  G2 universal mod ule (not a trad itional 
    mod ule) to the G2 TMS has the correc t transc eiver c onnec tors and c an b e reused.
    106455348
    or
    1064553639823A Lig htwave Transc eiver
    9823B Lig htwave Transc eiver2 or 6 4
    2 or 6 5
    4. One p air for each fib er c onnection. For eac h c onnec tion, either 1 lig htwave 
    transc eiver is installed  in an EPN and  1 in the PPN. A transc eiver c an b e reused from 
    eac h up g rad ed G2 universal mod ule. Add itional transc eivers, ord ered  sep arately, 
    are also ship ped  loose with the EPN equipment. 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-16 Standard Reliability 
    5
    Required Tools
    The following tools and  items may b e req uired  d uring  the up g rad e:
    nHig h-intensity flashlig ht or AC d rop  lig ht
    n3/8-inc h flat-b lad e sc rewd river with a 10-inc h shank (minimum)
    n5/16-inc h and  1/4-inc h soc kets with a ratc het and  10-inc h extension
    nLong -nose p liers to d isc onnec t ground  straps and  straig hten b ac kplane 
    pins
    nStatic -p roof or orig inal c irc uit p ac k p ac kag ing  for transp orting  c irc uit 
    packs
    nLab els for id entifying  the p ort c irc uit p ac ks and  c ab les attac hed  to the 
    rear of c ab inets
    nTwelve sp are #12 and  #10 self-tap p ing  sc rews
    nFour sp are c arrier g round  strap s
    nWrist ground strap
    nRep air kit for b ac kp lane p ins (KS-22876 L2 or eq uivalent)
    nOne c op y of eac h of the following  manuals:
    — DEFINITY Enterp rise Communic ations Server Release 8 
    Maintenanc e for R8si or DEFINITY Enterp rise Communic ations 
    Server Release 8 Maintenance for R8r
    — DEFINITY Enterp rise Communic ations Server Release 8 
    Ad ministrator’s Guid e
    Follow Routine Preventive Maintenance
    During  the up g rad e, follow routine p reventive maintenanc e p roc ed ures on the 
    system to b e up g rad ed . For information ab out the p roc ed ures and  nec essary 
    eq uip ment, refer to the “ Preventive Maintenanc e”  sec tion in 
    DEFINITY Enterp rise 
    Communic ations Server Release 8 Maintenanc e for R8r
    .
    Label Cables
    To make rec onnec ting  the c ab les simp ler and  more reliable, lab el b oth end s of 
    the c onnec tor c ables assoc iated with the c arrier to b e removed . 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-17 Standard Reliability 
    5
    Check Link Status
    1. Type display communication-interface links
     and p ress En te r. Write d own 
    all enab led  links.
    2. Type status link
     
    number and  p ress En t e r. Rep eat this step  for all links.
    3. Write d own whic h links are in servic e.
    Disable TTI
    !CAUTION:
    If you d o not d isab le the TTI, the translations c an b e c orrup ted .
    1. Make sure the ISDN is in servic e. If not, attempt to b usy out and release 
    the ISDN D-c hannel/link. This will b ring  the ISDN trunks b ac k into servic e.
    2. Type change system-parameters features
     and  p ress 
    En te r . Use sc reen 2 
    to d isab le Terminal Translation Initialization (TTI) b y c hang ing  the value to 
    n
    .
    Power Down G2 System
    1.At the c ommon c ontrol’s p ower d istrib ution unit, set the main c irc uit 
    b re a k e r  t o  O FF.
    2. At the universal mod ule’s p ower d istrib ution unit, set the main c irc uit 
    b re a k e r  t o  O FF.
    Install Power-Failure Transfer Ground Wire
    !CAUTION:
    To avoid  c ontaminating  sing le-p oint g round , d o not c onnec t the g round  wire 
    while the system is p owered  up .
    1. Connec t a 10 AWG (#25) (2.6 mm2) wire to p in 49 of the c onnec ting  b loc k 
    or to pin 49 of the CAP (c ab le ac c ess p anel) on the p ower-failure transfer 
    p anel.
    2. Route the op p osite end  of the wire to an ap p roved  g round  and  c onnec t. 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-18 Standard Reliability 
    5
    Disconnect Cables
    1. With the c ab le retainer in front of you and  the p art numb er visib le (4B or 
    4C), loc ate the slot that is almost vertic al. This slot is ad jac ent to the p art 
    numb er. Insert a #2 flat b lad e sc rewd river into the slot and  twist. The 
    retainer will snap  op en easily. Remove the c able.
    2. Disc onnec t the c ab les assoc iated  with the c arrier to b e removed .
    3. Remove the rear d oors from the c ab inet.
    4. Behind  a p reviously up graded  c ab inet, remove all of the rear p anels. Two 
    d ifferent types of sc rews hold the b ac k p anels to the c ab inet. Remove the 
    #10 sc rews with a sc rewd river or a 1/4-inc h soc ket. Remove the #12 
    sc rews with a sc rewdriver or a 5/16-inc h soc ket.
    Remove Circuit Packs from Module Control 
    Carrier A
    1.To ensure that p ower units in the “ A”  c arrier are p rop erly rep lac ed , lab el 
    eac h p ower unit with its slot number.
    2. Disc onnec t the p ower c ords from the p ower units in the “ A”  c arrier.
    3. Remove all c irc uit p ac ks and  p ower units from c arrier “ A.”  Store the c irc uit 
    p ac ks in the static -p roof p ac kag ing .
    4. Remove all circuit pack blanks.
    5. Remove the front trim p late from the “ A”  c arrier b y p ulling  it straig ht off.
    Remove CURL from Module Control Carrier A
    1. Remove the CFY1 c urrent limiter (CURL) from the p in-field  b loc k marked  
    “ CURL”  on the “ A”  c arrier. The CURL is reused in the Release 8 EPN.
    NOTE:
    Verify the CURL meets the minimum usab le vintag e req uirements. 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-19 Standard Reliability 
    5
    Remove Module Control Carrier A
    Disconnect TDM/LAN Cables
    NOTE:
    Note the p osition of the TDM/LAN c ab les b efore d isc onnec ting .
    1.Disc onnec t 1 end  of the TDM/LAN c ab le (b etween the “ A”  and  “ C”  
    c arriers) from the “ A”  c arrier. See Figure 5-1
    .
    2. Disc onnec t 1 end  of the TDM/LAN c ab le (b etween the “ A”  and  “ D”  
    c arriers) from the “ A”  c arrier.
    !WARNING:
    When removing the TDM/LAN c ab les from a previously up g rad ed  
    c arrier, b e c areful that none of the short p iec es of shrink tub ing c ome 
    off the 4 c orner p ins of the p in-field  b loc k. Otherwise, when the new 
    eq uip ment is c onnec ted, -48 volts c ould  short to g round .
    3. On p ort c arrier J58890BB-1, c onnec t the TDM c ab le or TDM terminator to 
    Slot 02. On p ort c arriers J58890BB-2 and  J58890BB-3, c onnec t the TDM 
    c ab les to Slot 01. 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-20 Standard Reliability 
    5
    Figure 5-1. TDM/LAN Connections for Standard Reliability Module Figure Notes
    1.Port Carrier (“ C” Position)
    2. ZAHF4 TDM/LAN Terminator
    3. TDM/LAN Cab le (WP91716 L6)
    4. Mod ule Control Carrier (“ A”  Position)
    5. Port Carrier (“ D” Position)6. Port Carrier (“ E”  Position)
    7. Slot 21
    8. Slot 01
    9. TDM/LAN Cab le (WP91716 L7) 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-21 Standard Reliability 
    5
    Remove Carrier Ground Straps
    1.Disc onnec t the top  and  b ottom g round  strap s from the “ A”  c arrier. See 
    Figure 5-2
    . These straps will rec onnec t to the new “ A”  c arrier.
    Figure 5-2. Location of Ground Jumpers Figure Notes
    1. Rear of Cab inet
    2. Port Carrier (“ C” Position)
    3. Ground  Jump ers4. Mod ule Control Carrier (“ A”  
    Po si t io n )
    5. Port Carrier (“ D”  Position) 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Multicarrier G2 Universal Module to R8r EPN 
    5-22 Standard Reliability 
    5
    2.Disc onnec t the “ P1”  and  “ P2”  c ab les from the “ A”  c arrier. See Figure 5-3. 
    3. Remove the fan trim p late by p ulling  it straig ht off.
    4. Clean or rep lac e the air filter (403326820) if nec essary.
    5. In front of the c arrier, remove the 4 sc rews (top 2 first) hold ing  the “ A”  
    c arrier to the c ab inet frame. Use a long -hand le sc rewd river or 5/16-inc h 
    soc ket with a 10-inc h extension.
    6. Behind  the c arrier, remove the 2 sc rews hold ing  the “ A”  c arrier’s rear 
    c onnec tor p anel to the c ab inet frame.
    7. Slid e the c arrier forward 1 to 2 inc hes. Be sure that no c ab les or wiring  
    harnesses are c aught on the c ab inet/c arrier framework.
    !CAUTION:
    Cab les and  wiring harnesses c an be d amag ed  if they c atc h on the 
    framework and  if too muc h pressure is ap p lied  in removing  the 
    carrier.
    8. Remove the c arrier b y slid ing  it out the front of the c ab inet.
    Figure 5-3. Location of P1 and P2 ConnectorsFigure Notes
    1. Rear of Control Carrier
    2. P2 Connec tor3. P1 Connec tor 
    						
    All Lucent Technologies manuals Comments (0)

    Related Manuals for Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual