    Have a look at the manual Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 413 Lucent Technologies manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    Page
    of 502
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-19 Release 5/6si to Release 8r 
    3
    Figure 3-3. TDM/LAN Connections for Release 5/6si EPN Figure Notes
    1. AHF110 TDM LAN/Bus Terminator
    2. Slot 17
    3. TDM/LAN Cab le (WP91716 L3)
    4. Slot 00
    5. Slot 036. Slot 18
    7.J58890H Port Cab inet (“ D”  
    Po si t io n )
    8. J58890H Port Cab inet (“ C”  
    Po si t io n )  
    9. J58890H Port Cab inet (“ B”  Position)
    10. J58890NExp ansion Control Cab inet 
    (“ A”  Position) 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-20 Release 5/6si to Release 8r 
    3
    Connect TDM/LAN Cables and ICC Cables
    1. Route and  c onnec t the TDM/LAN c ab les. If any of the Release 5/6si p ort 
    c ab inets (b eing  up g rad ed  to Release 8r c ab inets) were orig inally R1V3 
    p ort c ab inets, use the following  step s to route a c ab le b etween an R1V3 
    up p er c ab inet and  c ab inet b eneath it. Do not run a new c ab le throug h the 
    existing  slot in the rear shelf of the up p er c ab inet.
    a. Loosen the 2 left c onnec tor p anel sc rews, then remove the other 2 
    c onnec tor p anel sc rews.
    b . Attac h the TDM/LAN c ab le to the b ac kp lane and  slid e the c ab le 
    b etween the c onnec tor panel and the rear shelf (not throug h the 
    existing  slot in the shelf). Route the c ab le along  the b ottom of the 
    c ab inet.
    c . Rep lac e and  tig hten the c onnec tor p anel sc rews.
    2. For a c ritic al reliab ility system, c onnec t the ICC c ab les as shown in Table 
    3-4, Figure 3-4, and  Figure 3-5.
    NOTE:
    For a d up lic ated  c ab inet, d o not use the ICC c ab les (H600-259 G1) 
    removed  from the dup lic ated  Release 5/6si PPN. Use the new ICC 
    c ab les (H600-248 G1) sup p lied  with the up g rad e.
    3.On the “ A”  c arrier, verify the CFY1 c urrent limiter (CURL) c onnec ts to 
    p infield  b loc k “ 00”  (see Figure 3-4
    ).
    Table 3-4. Intercabinet Cable Connections
    Connect ICC Cables
    From To
    Carrier Pin-Field Block Carrier Pin-Field Block
    EPN J58890N ICCA J58890H ICCA
    ICCB ICCB 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-21 Release 5/6si to Release 8r 
    3
    Figure 3-4. ICC Pinfield Blocks on J58890N Expansion Control Cabinet
    Figure 3-5. ICC Pinfield Blocks on J58890H Port Cabinet
    114 25 12
    24
    00  00
    20 19  20 19
    0  3 2 1
    2 1  2 1 ICCB ICCA  TERM
    CURL
    Pinfield
    5.00 4.006.00
    0  3 2 100
    3.00
    24
    2.001.00 0.00
    ICCB
    ICCA 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-22 Release 5/6si to Release 8r 
    3
    Interconnect Port Networks with Fiber Optic
    Cabling — Standard Reliability Release 8r 
    After all fib er op tic  eq uip ment is installed , refer to Chapter A, ‘‘Fiber Link 
    Administration’’.
    1. Keep  trac k of whic h fib er attac hes to whic h c onnec tor on eac h lig htwave 
    transc eiver. Lab el every c ab le installed . This sec tion p rovid es fig ures 
    showing  typ ic al examp les of these c onnec tions.
    The c onnec tors on the lightwave transc eivers are lab eled  “ TX”  (transmit) or “ RX”  
    (rec eive), while the fib ers attac hing  to eac h c onnec tor are numb ered  either “ 1”  or 
    “2.” See Figure 3-7
    .
    Collocated Port Networks
    For a stand ard reliab ility system with 1 c olloc ated  EPN, use 1 fib er op tic  c ab le 
    and  2 lig htwave transc eivers to d irec tly c onnec t the networks.
    For a stand ard  reliab ility system with 2 c olloc ated  EPNs, use 3 fiber optic  c ab les 
    and  6 lig htwave transc eivers to d irec tly c onnec t the networks.
    NOTE:
    Based  on floor p lan c onsid erations, the leng th of these c ab les may vary. 
    20-foot (6.1 m) c ab les are normally ad eq uate for a Release 8r with 2 PNs.
    For c olloc ated  c ab inets, route the fib er op tic  c ab les d irec tly from the PPN to eac h 
    EPN c ab inet. Sinc e a Release 8r PPN c ab inet is c olloc ated  with a Sing le-Carrier 
    Cab inet stac k, the p referred  routing  is to run the c ab les 
    down the c ab le tray and  
    out the b ottom of the PPN c ab inet. The c ab les are then run to the EPN c ab inet 
    and  up  the outsid e of the rear p anels to the d esired  c arrier level.
    Fiber Remoted Port Networks
    For a stand ard reliab ility system with 1 fib er-remoted  EPN, use 2 fib er op tic  
    cables,2 lightwave transceivers, and 2 lightguide interface units (provided by the 
    PSC ).
    For a stand ard reliab ility system with 2 fib er-remoted  EPNs, use 6 fib er op tic  
    c ab les, 6 lig htwave transc eivers, and  6 lig htg uid e interfac e units (p rovid ed  b y 
    the PSC). 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-23 Release 5/6si to Release 8r 
    3
    DS1 CONV-Remoted Port Networks
    For a stand ard reliab ility system with 1 DS1 CONV-remoted  EPN, use 2 DS1 
    CONV c irc uit p ac ks (TN1654), 2 DS1 Conv-to-EI c ab les (846448637 and /or 
    846448645), two H-600-348 c ables, from 1 to 4 p airs of Channel Servic e Units 
    (CSUs), and  from 1 to 4 p airs of MDF c ab les (p rovid ed  with the CSUs).
    NOTE:
    The TN1654 requires the use of a TN573B Switc hed  Nod e Interfac e c irc uit 
    pack
    For a stand ard reliab ility system with 2 DS1 CONV-remoted  EPNs, this 
    arrang ement req uires:
    n6 DS1 CONV c irc uit p ac ks (TN1654)
    n6 DS1 CONV-to-EI c ab les (846448637 and /or 846448645)
    n6 H-600-348 c ab les
    n3, 6, 9, or 12 p airs of CSUs
    n3, 6, 9, or 12 p airs of wall-field  c ab les (p rovided  with CSUs)
    n5, 10, or 15 d B attenuators (sing le-mod e fib er only)
    For 1 or 2 Collocated Expansion Port Networks
    1. Behind  p ort c arrier B of the multic arrier PPN. See Figure 3-6 and  Figure 
    3-7:
    a. Install a lig htwave transc eiver on the c onnec tor at slot 1B02.
    NOTE:
    Attenuators may be required for single mode fiber using a 
    300A Lightwave Transc eiver
    b . Connec t 1 end  of the ap p rop riate fib er op tic  c ab le to the lig htwave 
    transc eiver at slot 1B02.
    c . Route the fib er optic  c ab le from the lig htwave transc eiver to the 
    c ab inet’s c ab le tray and  d own out of the c ab inet to the EPN stac k.
    d . Carefully attac h the fib er op tic  c ab le (with c ab le ties) to the wall of 
    the c ab le tray at the b uilt-in c ab le tie p ositions. 5d B Attenuator 106060718
    10d B Attenuator 106060734
    15d B Attenuator  106061021 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-24 Release 5/6si to Release 8r 
    3
    2. Behind control cabinet A of EPN stack 2:
    a. Install a lig htwave transc eiver on the c onnec tor at slot 2A01.
    b . Connec t the other end  of the fiber op tic  c able from the PPN to the 
    lig htwave transc eiver at slot 2A01.
    c . Carefully attac h the fib er op tic  c ab le (with c ab le ties) to the rear 
    c overs of the EPN stac k.
    d . Coil up  the surp lus leng th of fib er op tic  c ab le, and  p lac e the c oil 
    either in the c ab le manag er or on the b ottom shelf (hold ing  the 
    p ower sup p ly) of the PPN c ab inet.
    Figure 3-6. Standard Reliability Release 8r with 2 or 3 Port NetworksFigure Notes
    1. Cabinet 1 PPN
    2. Cabinet Stac k 2 EPN 1
    3. Cabinet Stac k 3 EPN 24. From Cab inet 3 A1 to Cab inet 1 C2
    5. From Cab inet 2 A2 to Cab inet 3 A2
    6. From Cab inet 1 B2 to Cab inet 2 A1  
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-25 Release 5/6si to Release 8r 
    3
    Figure 3-7. Typical Fiber Optic Connections
    For 1 or 2 Fiber-Remoted Expansion Port 
    Networks
    1. Behind  p ort c arrier B of the multic arrier PPN. See Figure 3-6 and  Figure 
    3-8:
    a. Install a lig htwave transc eiver on the c onnec tor at slot 1B02.
    NOTE:
    Attenuators may be required for single mode fiber using a 
    300A Lightwave Transc eiver
    b . Connec t a fib er op tic  c ab le to the transc eiver just installed .
    c . Route the c ab le to the c ab inet c ab le tray and out of the c ab inet 
    throug h the c ab le manag er to the PDS c ross-c onnec t fac ility.
    d . Connec t the fib er c ab le to the lig htg uid e interfac e unit p rovided .
    e. Carefully attac h the fib er op tic  c ab le (with c ab le ties) to the wall of 
    the c ab le tray at the b uilt-in c ab le tie p ositions. Figure Notes
    1. Lightwave Transc eiver
    2. To PPN Carrier B Slot 1B02
    3. To EPN 1 Carrier A Slot 2A01 
    (Cab inet Stac k 2)4. Fiber Optic Cable
    5. TX Connec tor
    6. RX Connec tor
    cydff05 CJL 103196
    RX TX
    2211 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-26 Release 5/6si to Release 8r 
    3
    2. Behind control cabinet A of EPN stack 2:
    a. Install a lig htwave transc eiver on the c onnec tor at slot 2A01.
    b . Connec t a fib er op tic  c ab le to the transc eiver just installed .
    c . Route the c ab le d own the outsid e of the rear c overs and  throug h 
    the c ab le manag er to the PDS c ross-c onnec t fac ility.
    d . Connec t the fib er op tic  c ab le to the lig htg uid e interfac e unit.
    e. Carefully attac h the fib er op tic  c ab le (with c ab le ties) to the rear 
    c overs of the EPN stac k.
    f. Coil up  the surp lus fib er op tic  c able and  p lac e the c oil in the c ab le 
    manag er.
    Figure 3-8. Fiber Optic Connections PPN to EPN1 Figure Notes
    1. Lightwave Transc eiver
    2. PPN Carrier B Slot 1B02
    3. EPN 1 Carrier A Slot 2A01 (Cabinet 
    Stac k 2)
    4. Fiber Optic Cable5. Fib er Op tic  Cross-Connec t Fac ility
    6. Lig htg uid e Interfac e Unit (LIU)
    7. TX Connec tor
    8. RX Connec tor
    cydf013 CJL102396
    RX TX
    2
    22 1
    11
    22
    11 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-27 Release 5/6si to Release 8r 
    3
    Interconnect Port Networks with Fiber Optic
    Cabling — High Reliability Release 8r 
    1. Keep  trac k of whic h fib er attac hes to whic h c onnec tor on eac h lig htwave 
    transc eiver. 
    This sec tion p rovid es fig ures showing  typ ic al ways of making  these c onnec tions. 
    The c onnec tors on the lightwave transc eivers are lab eled  “ TX”  (transmit) or “ RX”  
    (rec eive), while the fib ers attac hing  to eac h c onnec tor are numb ered  “ 1”  or “ 2.”  
    See Figure 3-10
    .
    Collocated Port Networks
    For a high reliab ility system with 1 c olloc ated  EPN, use 1 fiber op tic  c able and  2 
    lig htwave transc eivers, or 1 sing le-mod e fib er op tic  c ab le and  2 sing le-mod e 
    lig htwave transc eivers to d irec tly c onnec t the networks.
    For a hig h reliab ility system with 2 c olloc ated  EPN, use 3 fib er op tic  c ab les and  6 
    lig htwave transc eivers, or 3 sing le-mod e fib er op tic  c ab les and  6 sing le-mod e 
    lig htwave transc eivers to d irec tly c onnec t the networks.
    NOTE:
    Based  on floor p lan c onsid erations, the leng th of these c ab les may vary. 
    20-foot (6.1 m) c ab les are normally ad eq uate for a Release 8r with 2 p ort 
    networks.
    For c olloc ated  c ab inets, route the fib er op tic  c ab les d irec tly from the PPN to eac h 
    EPN c ab inet. Sinc e a Release 8r PPN c ab inet is c olloc ated  with a Sing le-Carrier 
    Cab inet stac k, the p referred  routing  is to run the c ab les 
    down the c ab le tray and  
    out the b ottom of the PPN c ab inet. The c ab les are then run to the EPN c ab inet 
    and  up  the outsid e of the rear p anels to the d esired  c arrier.
    Fiber-Remoted Port Networks
    For a hig h reliability system with 1 fib er-remoted  EPN, use 2 fib er op tic  c ab les, 2 
    lig htwave transc eivers, and  2 lig htg uid e interfac e units (p rovid ed  b y the PSC).
    For a hig h reliab ility system with 2 fiber-remoted  EPNs, use 6 fib er op tic  c ab les, 6 
    lig htwave transc eivers, and  6 lig htwave-interfac e units (p rovid ed  by the PSC).
    DS1 CONV-Remoted Port Networks
    For a high reliab ility system with 1 DS1 CONV-remoted expansion p ort network, 
    use 2 DS1 CONV c irc uit p ac ks (TN1654), 2 DS1 CONV-to-EI c ab les (846448637 
    and /or 846448645), 2 H-600-348 c ab les, from 1 to 4 pairs of c hannel servic e 
    units (CSUs), and  from 1 to 4 p airs of wall-field  c ab les (p rovid ed  with the CSUs).
    NOTE:
    The TN1654 requires a TN573B Switc h Nod e Interfac e c irc uit p ac k 
    						
    							DEFINITY Enterprise Communications Server Release 8.2
    Upgrades and Additions for R8r  555-233-115  Issue 1
    April 2000
    Upgrading R5si/R6si to R8r EPN and Adding Memory 
    3-28 Release 5/6si to Release 8r 
    3
    For a high reliab ility system with 2 DS1 Conv-remoted  exp ansion p ort networks, 
    this arrang ement req uires:
    n6 DS1 Converter c irc uit p ac ks (TN1654)
    n6 DS1 Converter-to-EI c ab les (846448637 and /or 846448645)
    n6 H-600-348 c ab les
    n3, 6, 9, or 12 p airs of CSUs
    n3, 6, 9, or 12 p airs of wall-field  c ab les (p rovided  with CSUs)
    For 1 or 2 Collocated Expansion Port Networks
    1. Behind  p ort c arrier C of the multic arrier PPN. See Figure 3-9 and Figure 
    3-10:
    a. Install a lig htwave transc eiver on the c onnec tor at slot 1C02.
    NOTE:
    Attenuators may be required for single mode fiber using a 
    300A Lightwave Transc eiver
    b . Connec t 1 end  of the ap p rop riate fib er op tic  c ab le to the lig htwave 
    transc eiver at slot 1C02.
    c . Route the fib er optic  c ab le from the lig htwave transc eiver to the 
    c ab inet’s c ab le tray and  d own, out of the c ab inet, to the EPN stac k.
    d . Carefully attac h the fib er op tic  c ab le (with c ab le ties) to the wall of 
    the c ab le tray at the b uilt-in c ab le tie p ositions.
    2. Behind  c ontrol c ab inet A EPN stac k 2:
    a. Install a lig htwave transc eiver on the c onnec tor at slot 2A01.
    NOTE:
    Attenuators may be required for single mode fiber using a 
    300A Lightwave Transc eiver
    b . Connec t the other end  of the fiber op tic  c able from the PPN to the 
    lig htwave transc eiver at slot 2A01.
    c . Carefully attac h the fib er op tic  c ab le (with c ab le ties) to the rear 
    c overs of the EPN stac k.
    d . Coil up  the surp lus fib er op tic  c ab le, and  p lac e the c oil either in the 
    c ab le manager or on the b ottom shelf (holding  the p ower supp ly) of 
    the PPN c ab inet. 
    						