    Have a look at the manual Lucent Technologies DEFINITY Enterprise Communication Server Release 8.2 Installation And Test For Multi-Carrier Cabinets Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 413 Lucent Technologies manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    Page
    of 467
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-11 Connect AC Power and Ground 
    1
    Figure 1-2. Typical Cabinet Grounding Wiring Diagram Figure Notes
    1. PPN Cab inet
    2. EPN Cab inet (if Installed )
    3. 6 AWG (#40) (16 mm
    2) CABINET 
    GROUND Wire
    4. Sing le-Point Ground Bloc k5. 6 AWG (#40) (16 mm
    2) Ground Wire
    6. AC Load Center Sing le-Point Ground
    7. Over 50 ft (15.2 m)
    8. Cab inet Ground Terminal Bloc k
    6
    122
    333
    5
    widf spgb KLC 100297
    74
    888 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-12 Connect AC Power and Ground 
    1
    Connect Battery Leads (J58890CH-1)
    Fi g u re  1 - 3 shows a typ ic al op tional small b attery hold over assemb ly. These 
    assemb lies may ship  with the b attery lead s d isc onnec ted  to p revent the b atteries 
    from discharging.
    1. Plug  the b attery c onnec tor into the -48 VDC Batteries c onnec tor on the 
    rear of the J58890CH-1 Power Distrib ution Unit.
    Figure 1-3. Typical Small Battery Assembly
    !CAUTION:
    Power is present in the c ab inet even if the AC p ower c ab le is unp lug g ed . 
    When p roc ed ures require ALL Power to b e removed  from the c ab inet and  
    to p revent unnec essary d isc harg ing  of the b attery, always p ower d own the 
    c ab inet using  the main c irc uit breaker loc ated on the front of the p ower 
    d istrib ution unit.
    psdfbat b RPY 061797
    Battery
    connector 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-13 Connect AC Power and Ground 
    1
    Figure 1-4. Power Distribution Unit (J58890CH)
    2. Be sure the main p ower to the p ower d istrib ution unit is OFF.
    3. At the power d istribution unit, set all c arrier c irc uit b reakers OFF.
    Small Battery Holdover 
    1. Connec t the small b attery hold over c ab le to J20. See Fi g u re  1 -4. Figure Notes
    1. Connec t small battery holdover 
    c ab le (or temperature sensor c ab le 
    from larg e b attery c ab inet) to J20
    2. Carrier Circ uit Breakers
    3. Ground  Terminal Bloc k
    4. Connec t -48 VDC Return - 1 AWG 
    (50 mm
    2) red  cable here.
    5. Connec t -48 VDC - 1 AWG 
    (50 mm
    2) black cable6. 1 AWG (50 mm
    2) 50 ft (15.2 
    m) c ab le to larg e b attery 
    c ab inet. For c ab les greater 
    than 50 ft 
    (15.2 m), c ontac t your 
    Luc ent Tec hnolog ies 
    rep resentative.
    7. Ground  Terminal Bloc k
    8. To AC load  c enter or 
    ap p roved  sing le-p oint 
    g round  b loc k
    External Alarms
    -4
    8
    V
    D
    C
    R
    e
    tu
    rn
    Carr
    ierB A
    C
    DEF/G
    R
    e
    m
    o
    te
    Powe
    r-48VDC Batter
    ies
    pcdf010 KLC 020599
    1
    2
    3
    4
    5
    6
    7
    8 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-14 Connect AC Power and Ground 
    1
    Large Battery Holdover
    When using  larg e b attery hold over, 1 b attery c ab inet is req uired  for every system 
    c ab inet req uiring  hold over. The 24-c ell b attery c ab inet must have a float voltag e 
    of 54.2 VDC. 
    1. Connec t the -48 VDC c able to the larg e b attery c onnec tor. See Fi g u re  1 -4
    .
    2. Connec t the -48 VDC RETURN c ab le to the g round  terminal b loc k.
    3. Connec t the temperature sensor c ab le, from the b attery c ab inet, to J20.
    NOTE:
    An ad apter c ab le may b e req uired  when c onnec ting  the temp erature 
    sensor c ab le to the J58890CH unit. See Ta b l e  1 - 4
    . 
    Connect Shorting Cable to J58890CE-2
    !CAUTION:
    For a c ab inet with a b attery c harg er, read the c aution lab el on the 397C 
    b attery c harg er b efore d isc onnec ting  b atteries.
    Some c ab inets c ontain a J58890CE-2 AC Power Distrib ution Unit without an 
    op tional b attery c harger. Install the shorting c ab le only when a b attery c harg er is 
    not installed . If you d o not install the shorting  c ab le or a b attery c harg er, then an 
    alarm ap p ears.
    Table 1-4. Temperature Sensor Cable Adapter Cables
    H600-476 Adapter Cable Usage
    Group  1 (G1) 24-c ell c ustomer-p rovided  b attery
    Group 3 (G3) (included 
    with b attery c ab inet)24-c ell Luc ent Tec hnolog ies battery 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-15 Connect AC Power and Ground 
    1
    Figure 1-5. Shorting Cable Installation
    1. Set the c irc uit breakers on the p ower d istrib ution unit OFF. See Fi g u re  1 -5
    .
    2. At the rear of the c ab inet, insert the shorting  c ab le (H600-442-G1) into 
    J11. The c ab le is keyed  so it c an fit only 1 way.
    Connect AC Power
    1. Set the main c irc uit b reakers on the p ower d istrib ution unit OFF.
    2. Connec t c ab inet AC line c ord s to the AC p ower rec ep tac les.
    3. Do not p ower up  the system at this time. Figure Notes
    1. Shorting  Cab le (H600-442-G1) (If 
    Battery Charg er is Not Installed )2. J11 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-16 Connect DC Power and Ground 
    1
    Connect DC Power and Ground
    Power Distribution Unit (J58890CH-1 Only)
    Rectifier Modules and Battery Interface Unit 
    Eac h rec tifier mod ule op erates as an integ ral p art of a c omp lete p ower system 
    with b attery b ac kup . The mod ules op erate in a red und ant, hig h reliab ility mod e to 
    p rovid e -48 VDC at 850 Watts to a c ommon p ower b us.
    The Battery Interfac e Unit (BIU) c ontrols the rec tifier mod ules, manag es the 
    b atteries, and  rep orts the status of system power. The BIU p rovid es the Remote 
    Power Off (RPO) op tion and  b attery alarm interfac es for internal and  external 
    alarms.
    Figure 1-6. Rectifier Module Installation Figure Notes
    1. Install Battery Interfac e Unit into Slot 1
    2. Install Rectifier Mod ules into Slots 2-5
    3. Rec tifier Mod ule 3 (in Slot 4)4. Test Points
    5. Main Circ uit Breakers 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-17 Connect DC Power and Ground 
    1
    1. Install the BU3200A Battery Interfac e Unit (c omc ode 107781502) in the 
    first slot of the p ower d istrib ution unit. See Fig ure  1-6
    . 
    NOTE:
    The BIU and  the rec tifier mod ules are keyed and  c an only install 1 
    way.
    2. Install the first 2 RM0850HA100 Rec tifier Modules (c omc od e 107793796) 
    into the sec ond  and  third  slots of the p ower d istrib ution unit. 
    3. If 2 to 3 c arriers are installed  in the system, install a third  rec tifier mod ule 
    (N+ 1).
    4. If 4 to 5 c arriers are installed  in the system, install a fourth rec tifier mod ule. 
    5. The fifth rec tifier mod ule slot is reserved  for future system g rowth.
    Connect Power 
    1. Have a q ualified  elec tric ian c onnec t and  route wires from the AC load  
    c enter to the d ed ic ated  elec tric al outlet for the power d istribution unit.
    Connect PPN Cabinet Ground
    1. Connec t 1 end  of a 6 AWG (#40) (16 mm2) wire to the ground  terminal 
    b loc k on the rear of the c ab inet. See Fig ure 1-4
    .
    2. Route the CABINET GROUND wire to the AC load  c enter sing le-p oint 
    g round  b loc k and  c onnec t.
    Connect EPN Cabinet Ground(s)
    1. Connec t 1 end  of a 6 AWG (#40) (16 mm2) CABINET GROUND wire to the 
    g round  terminal b loc k at the b ottom rear of the EPN c ab inet. See Fi g u re  
    1-2.
    2. Route the CABINET GROUND wire to the AC load  c enter sing le-p oint 
    g round  and c onnec t.
    3. Connec t eac h remaining  EPN c ab inet to the AC load c enter sing le-p oint 
    g round . 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-18 Connect DC Power and Ground 
    1
    DC Power and Ground (J58890CF Only)
    Fi g u re  1 - 7 shows a typ ic al p ower and  g round  layout for a DC-powered  c ab inet. 
    The size of the wire required  for the -48 volt DC and  -48 volt return must ensure 
    the voltage sup p lied  b y the b attery plant is maintained  b etween -42.5 and  -54.2 
    volts DC at all times for p roper op eration and  to p revent hard ware d amag e. The 
    wire must b e sized  for a maximum voltag e d rop  of 0.5 VDC in eac h leg  of the DC 
    distribution. This procedure applies to both PPN and EPN cabinets.
    Figure 1-7. Typical Power and Ground for a DC-Powered Cabinet
    Ground
    connection
    terminal
    DC battery
    cabinet
    Battery
    +
    +
    --
    Frame ground
    1 AWG
    -48 V-48 V RTN
    EPN cabinet 17
    -48 V-48 V RTN
    EPN cabinet n
    Ground
    discharge
    barTo
    CBC ground terminal
    bar at the MDF
    1 AWG
    ground wire
    Approved
    ground
    System
    single point
    ground
    Single point
    ground
    block
    6 AWG
    6 AWG 6 AWG
    6 AWG 10 AWG
    DC power
    from rectifiers
    cydf_dc  KLC 032999
    3
    1
    Main AC
    supply
    (AC mains)
    4
    DC output
    distribution bus
    1 AWG
    5
    5
    51 AWG
    7
    1 AWG
    -48 V
    -48 V RTN
    PPN cabinet7
    1 AWG 1 AWG RTN
    75A
    DC power cabinet
    75A
    circuit
    breaker
    75A
    75A
    5
    5
    To  n e x t
    cabinet
    Rectifiers
    -48V
    DC
    -48V DC
    8LV D
    2 
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-19 Connect DC Power and Ground 
    1
    Connect DC Power and Ground
    The g round ing  method s for the DC-p owered  system are more c omp lex than that 
    of an AC-powered  system. The following  installation p roc ed ures refer to Fig ure 
    1-7. The numbers 1-8 in Fi g u re  1 -7 matc h the following  sub sec tions 1-8. Other 
    fig ures may b e referenc ed  as req uired .
    !CAUTION:
    Ground ing  of the system shall c omp ly with the g eneral rules for g round ing  
    c ontained  in Artic le 250 of the National Elec tric al Code, NFPA 70. For more 
    information, refer to ‘‘
    Ap p roved  Ground s’’ on p age 1-22.
    1. Install Coupled Bonding Conductor Wires
    This is a c ond uc tor that c onnec ts to the sing le-point g round  b loc k and  run 
    ad jac ent to p airs in an assoc iated  c ab le. The mutual c oup ling  b etween the CBC 
    and  the p airs red uc es p otential d ifferenc es in terminating  equip ment. The 
    c ond uc tor c onsists of a 10 AWG (#25) (6 mm
    2) wire terminated  at the CBC 
    g round  terminal b ar at the Main Distrib ution Frame (MDF).
    1. At the DC Power Cab inet, c onnec t a 10 AWG (#25) (6 mm
    2) ground wire to 
    the Ground  Disc harg e Bar. See Fi g u re  1 -7
    .
    2. Route the 10 AWG (#25) (6 mm
    2) ground  wire to the CBC g round  terminal 
    b ar at the MDF. Be sure a minimum of 12 in. (30.5 c m) sp ac ing  is 
    maintained  b etween the CBC and  other p ower and  g round  lead s.
    3. Tie wrap  the g round  wire to the insid e wiring  c ab le.
    NOTE:
    The g round  wires are c onnec ted to the CBC as instruc ted  in Chap ter 2, 
    ‘‘Install Telec ommunic ations Cab ling’’.
    2. Connect DC Battery and Power Cabinet 
    Grounds
    NOTE:
    The wire in the next step  must b e sized  for a maximum voltag e d rop  of 0.5 
    VDC in eac h leg of the DC distrib ution. In this examp le 1 AWG is used .
    1. Measure and cut a minimum of a 1 AWG (#70) (44 mm
    2) wire long  enough 
    to reac h b etween the ground connection t
    erminal in the DC Battery 
    Cab inet and  the Ground  Disc harg e Bar in the DC Power Cab inet. See 
    Fi g u re  1 - 7
    .
    2. Crimp terminal lug s on eac h end  of the wire. Terminal lug s are furnished  
    as p art of D-181895, Kit of Parts (c omc od e 105434559).  
    						
    							DEFINITY ECS Release 8.2 Installation and Test
    for Multi-Carrier Cabinets  555-233-114  Issue 1
    April 2000
    Install and Connect Cabinets 
    1-20 Connect DC Power and Ground 
    1
    3. At the DC Power Cab inet, c onnec t the wire to the Ground  Disc harg e Bar.
    4. Route the wire throug h 1 of the holes in the sid e of the c ab inets and  
    terminate it on the Ground  Connec tion Terminal in the DC Battery Cabinet.
    3. DC Power Cabinet Approved Ground
    NOTE:
    The wire must b e at least as larg e as the larg est d istrib ution wire in the 
    system (req uired b y UL). In this examp le 1 AWG is used .
    1. At the DC Power Cab inet, c onnec t a 1 AWG (#70) (44 mm
    2) ground wire to 
    the Ground  Disc harg e Bar. See Fi g u re  1 -7
    .
    2. Route the g round  wire out of the c ab inet and  terminate it on the ap p roved  
    g round . The ap p roved  g round  must be id entified  with a g round ing  tag  
    (FORM 15657NR or eq uivalent). See ‘‘
    Approved Grounds’’ on pag e 1-22.
    4. Connect Main AC Supply to DC Power Cabinet
    1. Ensure the assoc iated  c irc uit breakers at the AC p ower p anel are OFF
    .
    2. Have a q ualified elec tric ian c onnec t AC power lead s to the rec tifiers in the 
    DC Power Cab inet. Eac h rec tifier should  have its own b ranc h c irc uit. 
    Terminate the leads on the AC INPUT terminal b loc k of eac h rec tifier.
    5. Connect Ground Wires for DC-Powered 
    Systems
    !CAUTION:
    Do not c onnec t any g round  wires from an EPN c ab inet to another EPN 
    c ab inet or to a PPN c ab inet. All g round  wires must be terminated  at the 
    sing le-p oint g round bloc k at the main AC sup p ly (AC mains).
    1. Connec t a 6 AWG (#40) (16 mm
    2) wire to the PPN c ab inet ground terminal 
    block. 
    2. Route the wire to the AC mains sing le-p oint g round  b loc k and  c onnec t. 
    3. Connect a 6 AWG (#40) (16 mm
    2) wire to eac h EPN’s c ab inet g round  
    terminal b loc k.
    4. Route the wire(s) to the AC mains sing le-p oint g round  bloc k and  c onnec t. 
    5. Connec t a 6 AWG (#40) wire to the DC b attery c abinet and  DC p ower 
    c ab inet.
    6. Route wires to the AC mains sing le point g round  b loc k and  c onnec t them. 
    						