    Section 8-2 - DISASSEMBLY/RE-ASSEMBLY 8 - 75
    8-2-30 P3RLY / P2RLY Assy & P2RLY with Dummy 
    8-2-30-1 Tools • Common pilIips screwdrivers
    8-2-30-2 Preparations • Shut down the system and switch off the main breaker.
    8-2-30-3 Removal procedure 1.) Remove the side right cover. Refer to the  8-2-16 Side Right Cover on page 8-52.
    2.) Remove the side left cover. Refer to the  8-2-15 Side Left Cover on page 8-51.
    3.) Remove the Front Cover. Refer to the 8-2-17 Front Cover on page 8-53 .
    4.) Remove the ASIG Board. Refer to the 8-2-35 ASIG Assy on page 8-86 .
    5.) Unscrew 8 screws (1-8) and remove the metal cover.
    6.) Unscrew 6 screws (1-6) and remove the PCB. Figure 8-111   RLY Cover
    Figure 8-112   Screws of the RLY board
    (8) (7)
    (6)
    (5)
    (4)
    (3)
    (2)
    (1)
    (1)
    (2)
    (3)
    (4) (5)(6) 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1 LOGIQ™ P5 SERVICE MANUAL  
    8 - 76 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
    8-2-30-3              Removal procedure  (cont’d)
    7.) Perform the following functional tests. If all are successful, include the debrief script provided below.
    8-2-30-4 Mounting Procedure Install the new parts in the reverse order of removal.
    Table 8-31    Functional Tests
    Service Manual
    Section
    Functional Test / Diagnostic TestDebrief Script
    Section 4-3-1 Power On/Boot Up
    “Service Manual, Direction
    5394141, Rev 1+, Section 8-2-30. Equipment 
    passed all required tests and is ready for use. “
    Section 4-3-2
    Power Off / Shutdown
    Section 4-9-6 P3RLY,P2RLY and P2RLY with Dummy Assy 
    function check procedure
    Section 4-3-4 System B/M-Mode Checks
    Section 4-3-5 System CFM and PWD Checks
    Section 10-5-2 Functional Checks (See Also Chapter 4)
    Section 10-5-7 Probe Maintenance 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1LOGIQ™ P5 SERVICE MANUAL 
    Section 8-2 - DISASSEMBLY/RE-ASSEMBLY 8 - 77
    8-2-31 Backplane Assy 
    8-2-31-1 Tools • Common pilIips screwdrivers
    8-2-31-2 Preparations • Shut down the system and switch off the main breaker.
    8-2-31-3 Removal procedure 1.) To detached the backplane, all pwas in the cardcage should be removed from cardcage.
    2.) Open the Side Left Cover and Side Right Cover. Refer to the  8-2-15 Side Left Cover on page 8-
    51  and  8-2-16 Side Right Cover on page 8-52 .
    3.) Open the EMI Cover L and EMI Cover R. Refer to the  8-2-26 EMI Cover L on page 8-68 and 8-2-
    27 EMI Cover R on page 8-69 .
    4.) Remove all pwas from the nest box.
    5.) Open the front cover. Refer to the  8-2-17 Front Cover on page 8-53.
    6.) Remove the P3RLY / P2RLY Board. Re fer to the 8-2-30 P3RLY / P2RLY Assy & P2RLY with 
    Dummy on page 8-75 .
    7.) Remove the DVD, HDD. Refer to the  8-2-44 DVD R/W Drive on page 8-98 and 8-2-47 SATA HDD 
    Assy on page 8-104.
    8.) Unplug all the cable connectors all in Backplane Assy. Figure 8-113   PWAs in the nest box 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1 LOGIQ™ P5 SERVICE MANUAL  
    8 - 78 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
    8-2-31-3              Removal procedure  (cont’d)
    9.) Unscrew 16 screws from the Backplane Assy.
    10.) Perform the following functional tests. If all ar e successful, include the debrief script provided below.
    8-2-31-4 Mounting Procedure Install the new parts in the reverse order of removal. Figure 8-114   Backplane
    Table 8-32    Functional Tests
    Service Manual Section
    Functional Test / Diagnostic TestDebrief Script
    Section 4-3-1 Power On/Boot Up
    “Service Manual, Direction
    5394141, Rev 1+, Section 8-2-31. Equipment 
    passed all required tests and is ready for use. “
    Section 4-3-2
    Power Off / Shutdown
    Section 4-9-9 BackPlane Assy Function Validation 
    Procedure
    Section 4-3-4 System B/M-Mode Checks
    Section 4-3-5 System CFM and PWD Checks
    Section 10-5-2 Functional Checks (See Also Chapter 4) 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1LOGIQ™ P5 SERVICE MANUAL 
    Section 8-2 - DISASSEMBLY/RE-ASSEMBLY 8 - 79
    8-2-32 ACWD Assy 
    8-2-32-1 Tools • Common pilIips screwdrivers
    8-2-32-2 Preparations • Shut down the system and switch off the main breaker.
    8-2-32-3 Removal procedure 1.) Remove the Side Right Cover. Refer to the  8-2-16 Side Right Cover on page 8-52.
    2.) Remove the EMI Cover R. Refer to the  8-2-27 EMI Cover R on page 8-69.
    3.) Remove the ASIG Board. Refer to the 8-2-35 ASIG Assy on page 8-86 .
    4.) Pull the ACWD assy out from Nest box.  The ACWD assy is located in slot #2.
    Figure 8-115   PWAs in Nest Box 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1 LOGIQ™ P5 SERVICE MANUAL  
    8 - 80 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
    8-2-32-3              Removal procedure  (cont’d)
    5.) Perform the following functional tests. If all are successful, include the debrief script provided below.
    8-2-32-4 Mounting Procedure Install the new parts in the reverse order of removal. Table 8-33    Functional Tests
    Service ManualSection
    Functional Test / Diagnostic TestDebrief Script
    Section 4-3-1 Power On/Boot Up
    “Service Manual, Direction
    5394141, Rev 1+, Section 8-2-32. Equipment 
    passed all required tests and is ready for use. “
    Section 4-3-2
    Power Off / Shutdown
    Section 4-9-9 ACWD Assy Function Validation Procedure
    Section 4-3-5 System CFM and PWD Checks
    Section 10-5-2 Functional Checks (See Also Chapter 4)
    Section 10-5-5 Physical Inspection 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1LOGIQ™ P5 SERVICE MANUAL 
    Section 8-2 - DISASSEMBLY/RE-ASSEMBLY 8 - 81
    8-2-33 SYSCON PM As sy/SYSCON CM Assy
    8-2-33-1 Tools
    • Common pilIips screwdrivers
    8-2-33-2 Preparations • Shut down the system and switch off the main breaker.
    8-2-33-3 Removal procedure 1.) Remove the Side Right Cover. Refer to the  8-2-16 Side Right Cover on page 8-52.
    2.) Remove the EMI Cover R. Refer to the  8-2-27 EMI Cover R on page 8-69.
    3.) Remove the SYSCONPM(SYSCONCM) assy  in slot #3 in the nest box.
    4.) Eject one ASIR ROM from old SYSC ONML with regular screw driver.
    Separate ASIR ROM form new  SYSCONML as same procedure.
    Figure 8-116   PWAs in Nest Box
    Figure 8-117   ASIR location 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1 LOGIQ™ P5 SERVICE MANUAL  
    8 - 82 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
    8-2-33-3              Removal procedure  (cont’d)
    5.) Mount ASIR ROM to new SYSCONML  Assy. Refer to the Figure 8-119.
    6.) Confirm mounting direction and pin number.
    NOTE: It is important to swap ASIR  ROM(U23). Because it contains the serial Number and option the 
    system. Figure 8-118   Separation of ASIR ROM
    Figure 8-119   ASIR ROM mounting direction 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1LOGIQ™ P5 SERVICE MANUAL 
    Section 8-2 - DISASSEMBLY/RE-ASSEMBLY 8 - 83
    8-2-33-3              Removal procedure  (cont’d)
    7.) Perform the following functional tests. If all ar e successful, include the debrief script provided below.
    8-2-33-4 Mounting Procedure Install the new parts in the reverse order of removal. Table 8-34    Functional Tests
    Service ManualSection
    Functional Test / Diagnostic TestDebrief Script
    Section 4-3-1 Power On/Boot Up
    “Service Manual, Direction
    5394141, Rev 1+, Section 8-2-33. Equipment 
    passed all required tests and is ready for use. “
    Section 4-3-2
    Power Off / Shutdown
    Section 4-9-4 SYSCONML Assy Function Validation 
    Procedure
    Section 4-3-4 System B/M-Mode Checks
    Section 4-3-5 System CFM and PWD Checks
    Section 4-5 Peripheral Checks
    Section 10-5-2 Functional Checks (See Also Chapter 4)
    Section 10-5-2-2 Peripheral/Option Checks
    Section 10-5-5 Physical Inspection 
    						
    							GE HEALTHCARE
    DIRECTION 5394141, REVISION  1 LOGIQ™ P5 SERVICE MANUAL  
    8 - 84 Section 8-2 - DISASSEMBLY/RE-ASSEMBLY
    8-2-34 PM SOM Assy with  1G/ CM SOM Assy with 512M
    8-2-34-1 Tools
    • Common pilIips screwdrivers
    8-2-34-2 Preparations • Shut down the system and switch off the main breaker.
    8-2-34-3 Removal procedure 1.) Remove the Side Right Cover. Refer to the  8-2-16 Side Right Cover on page 8-52.
    2.) Remove the EMI Cover R. Refer to the  8-2-27 EMI Cover R on page 8-69.
    3.) Remove the SYSCOM PM  / CM Assy. Refer to the 8-2-33 SYSCON PM Assy/SYSCON CM Assy 
    on page 8-81 .
    4.) Unscrews 4 screws.
    5.) Remove the SOM Assy. Figure 8-120   4 screws for SOM on SYSCON
    Figure 8-121   Detached the SOM from SYSCON PWA 
    						