    							CHAPTER 2 INSTALLATION
    Procedure
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 45
    PROCEDURE
    This flowchart explains the procedures for installing the PBX system. Follow the procedures in
    Figure 2-2.
    Figure 2-2  Procedure Flowchart (1 of 2)
    START
    UNPACKING
    INSTALLATION
    OF
    MAIN EQUIPMENT
    BATTERY
    CONNECTION
    TERMINATION OF
    CABLES ON MDF SUPPLY VOLTAGE CHECK
    AND
    HEAT RUN TEST
    CABLE RUNNING
    TO MDF
    INSTALLATION
    OF
    PERIPHERAL EQUIPMENT
    A POWER CABLE
    CONNECTION
    SWITCH SETTINGS
    OF
    CIRCUIT CARDSREFER TO CHAPTER 3.
     Page 49
     Page 54
     Page 83
     Page 90
     Page 94
     Page 102
     Page 109
    Page 128
    WIRING AC CABLE
    TO
    TERMINALS Page 50 
    						
    							CHAPTER 2 INSTALLATION
    Procedure
    NEAX2000 IVS2 Installation Procedure ManualPage 46ND-70928 (E), Issue 1.0
    Figure 2-2  Procedure Flowchart (2 of 2)
    For Floor Standing Installation, there are three methods to install the equipment. It depends on
    the country according to the UL/cUL/ACA.
    NOTE:
    UL = Underwriters Laboratories (U.S.A.)
    cUL = Canadian Underwriters Laboratories (Canada)
    ACA = Australian Communication Authority (Australia)
    “Stationary Equipment (For North America/ Australia)”
    “Fixed Equipment (For Nor th America/ Australia)”
    “Fixed Equipment (For Other Countries)”
    A
    END MOUNTING
    MOUNTING FRONT COVERCIRCUIT CARDS
    SYSTEM
    SYSTEM DATA ENTRY
    CLEANING
    AND
    VISUAL CHECK INITIALIZATION
    OPERATION TEST
    SYSTEM DATA SAVE
     Page 199
    Page 201
     Page 202
    Page 204
    Page 205
    Page 205
      
    						
    							CHAPTER 2 INSTALLATION
    Stationary Equipment (For North America/Australia)
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 47
    Stationary Equipment (For North America/Australia)
    The equipment is placed on the BASE TRAY which is fixed on the floor, and is connected to 120V/
    240V AC Power Source using AC CORD-D cable.
    For installation of Stationary Equipment, see the following pages.
    WIRING AC CABLE TO TERMINALS - Using AC CORD-D  Page 50
    INSTALLATION OF MAIN EQUIPMENT - Floor Marking for BASE TRAY  Page 58
    - Installation of PIM, For Stationary Equipment  
    Page 55
    Fixed Equipment (For North America/Australia)
    The equipment is fixed on the floor by BASE PLATE and anchor bolts, and is connected to AC
    Power Distribution Board using installation cable.
    For installation of this equipment, see the following pages.
    WIRING AC CABLE TO TERMINALS - Using installation Cable  Page 52
    INSTALLATION OF MAIN EQUIPMENT - Floor Marking for BASE PLATE  Page 58
    - Installation of PIM, For Fixed Equipment
     Page 55
    Fixed Equipment (For Other Countries)
    The equipment is fixed on the floor by BASE PLATE and anchor bolts, and is connected to 120V/
    240V AC Power Source using AC CORD-D cable.
    For installation of this equipment, see the following pages.
    WIRING AC CABLE TO TERMINALS - Using AC CORD-D  Page 50
    INSTALLATION OF MAIN EQUIPMENT - Floor Marking for BASE PLATE  Page 58
    - Installation of PIM, For Fixed Equipment
     Page 55 
    						
    							CHAPTER 2 INSTALLATION
    Fixed Equipment (For Other Countries)
    NEAX2000 IVS2 Installation Procedure ManualPage 48ND-70928 (E), Issue 1.0
    The mark shown below is attached to each procedure in which circuit cards are handled. When
    doing such a procedure, the installer must perform the procedure with caution, to prevent dam-
    age caused by static electricity (See “Static Electricity Guard”on Page 39
    ).
    ATTENTION
    Contents
    Static Sensitive
    Handling
    Precautions Required 
    						
    							CHAPTER 2 INSTALLATION
    Unpacking
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 49
    UNPACKING
    (1) Check the received quantity of packages containing the PBX system with the description on 
    the shipping document.
    (2) Check the packaging for external damage done by transportation and record it as 
    necessary.
    (3) Unpack the packaging.
    For unpacking the packages containing circuit cards, a grounded wrist strap should be 
    worn.
    (4) Check the quantity of equipment and materials unpacked with the shipping document.
    (5) Perform visual inspection, checking for the following items.
    PIMs Overall distor tion.
    Scratches and dents on the surface.
    Scratches and cracks on the PIM Backplane.
    Broken or bent pins on the PIM Backplane.
    Covers Scratches and dents.
    Circuit Cards Overall distor tion
    Scratches and cracks
    Loss, or damage of par ts on the circuit cards.
    Attendant Console Scratches and cracks on the keyboard
    Overall distor tion
    Damage to Keys and lamps.
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required 
    						
    							CHAPTER 2 INSTALLATION
    Wiring AC Cable to Terminals
    NEAX2000 IVS2 Installation Procedure ManualPage 50ND-70928 (E), Issue 1.0
    WIRING AC CABLE TO TERMINALS
    There are two kinds of AC cable : AC CORD-D For Stationary Equipment/Fixed Equipment (For
    Other Countries)
    : Installation Cable For Fixed Equipment (For North America/
    Australia)
    Using AC CORD-D
    (1) Take the AC CORD-D out of the hole on the left side of the BASE, then secure the code to 
    the BASE with the cord bush.
    NOTE:
    Cord bush is attached to the AC CORD-D.
    (2) Wire the AC CORD-D and the FG cable to the FG, NEUTRAL, LINE and Ground terminals 
    on the BASE.
    (3) Wire the  AC CORD-B to the FG, NEUTRAL and LINE terminals on the BASE.
    Figure 2-3  Wiring AC CORD to Terminals
    NOTE:
    Cable colors in the parentheses are for Australia.
    FG CABLE 
    (GREEN)
    HOW TO SECURE CABLES TO TERMINAL BLOCK
    INSERT A SCREW DRIVER INTO THE INSIDE HOLE OF TERMINAL BLOCK.
    PULL DOWN THE SCREW DRIVER TOWARD INSIDE AND OPEN THE METAL PLATE.
    INSERT A POWER CABLE INTO THE OUTSIDE HOLE OF TERMINAL BLOCK.
    REMOVE THE SCREW DRIVER. 1 12
    2 33
    4 4
    AC CORD-B
    AC CORD-D TO
    120V/240V
    AC POWER
    SOURCETO CN1 on
    PZ-PW121 in PIM
    FG
    NEUTRALLINETERMINAL
    BLOCKS GREEN
    (GREEN/YELLOW)BLACK (BROWN)
    BLACK (BROWN)
    WHITE (BLUE)
    GREEN
    (GREEN/YELLOW)WHITE (BLUE)
    BASE
    FRONT 
    						
    							CHAPTER 2 INSTALLATION
    Using AC CORD-D
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 51
    (4) When the system is two-frame configuration, the AC CORD-D of the right side frame can 
    go through the BASE of the left side frame.
    Figure 2-4  AC CORD Wiring for Two-Frame Configuration
    BASE
    FGLINENEUTRALFGLINENEUTRAL
    TERMINAL
    BLOCKS TO
    120V/240V AC
    POWER SOURCE
    AC CORD-D
    CORD BUSH 
    						
    							CHAPTER 2 INSTALLATION
    Using Installation Cable
    NEAX2000 IVS2 Installation Procedure ManualPage 52ND-70928 (E), Issue 1.0
    Using Installation Cable
    (1) Take the Installation cable out of the hole on the left side of the BASE, then secure the cable 
    to the BASE with the cord bush.
    NOTE:The installer is to use minimum 16 AWG (1.3
    φ) size wire, maximum 9 mm size
    cable.
    (2) Wire the Installation cable and the FG cable to the FG, NEUTRAL, LINE and Ground 
    terminals on the BASE.
    (3) Wire the  AC CORD-B to the FG, NEUTRAL and LINE terminals on the BASE.
    Figure 2-5  Wiring Installation Cable to Terminals
    NOTE:Cable colors in the parentheses are for Australia.
    FG CABLE 
    (GREEN)
    HOW TO SECURE CABLES TO TERMINAL BLOCK
    INSERT A SCREW DRIVER INTO THE INSIDE HOLE OF TERMINAL BLOCK.
    PULL DOWN THE SCREW DRIVER TOWARD INSIDE AND OPEN THE METAL PLATE.
    INSERT A POWER CABLE INTO THE OUTSIDE HOLE OF TERMINAL BLOCK.
    REMOVE THE SCREW DRIVER. 112
    23
    3
    4
    4
    AC CORD-B
    INSTALLATION CABLE TO AC
    POWER
    DISTRIBUTION
    BOARDTO CN1 on
    PZ-PW121 in PIM
    FG NEUTRAL LINETERMINAL
    BLOCKS GREEN
    (GREEN/YELLOW)BLACK (BROWN)
    BLACK (BROWN)
    WHITE (BLUE)
    GREEN
    (GREEN/YELLOW)WHITE (BLUE)
    BASE
    FRONT 
    						
    							CHAPTER 2 INSTALLATION
    Using Installation Cable
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 53
    (4) When the system is two-frame configuration, the Installation cable of the right side frame 
    can go through the BASE of the left side frame.
    Figure 2-6  Installation Cable Wiring for Two-Frame Configuration
    BASE
    FGLINENEUTRALFGLINENEUTRAL
    TERMINAL
    BLOCKS TO
    AC POWER
    DISTRIBUTION
    BOARD
    INSTALLATION CABLE
    CORD BUSH 
    						
    							CHAPTER 2 INSTALLATION
    Installation of Main Equipment
    NEAX2000 IVS2 Installation Procedure ManualPage 54ND-70928 (E), Issue 1.0
    INSTALLATION OF MAIN EQUIPMENT
    Floor Standing Installation
    
    Check the site for installing the PBX with the work drawing to verify that 
    the required floor space is ensured and that service entrances and 
    ducts for trunk/extension cables, power cables and bus cables have 
    been properly worked at correct positions. See Figure 2-7 and Figure 
    2-8.
    
    Mark positions for installation of the PBX main equipment.
    For Fixed Equipment, detach the BASE PLATE from the BASE. See  
    Figure 2-9.
    For Stationary Equipment, see Figure 2-10.
    NOTE:
    Measure the level of the floor surface before installing the PBX
    main equipment.
    
    Check the level of the floor. If necessary, adjust the level by inserting 
    spacers beneath the equipment.
    
    First open necessary number of preliminary prepared holes using the 
    drill bit for small-diameter holes, then use the finishing drill bit for fin-
    ishing drill holes. See “Drilling” on Page 59.
    
    Detach the front cover of each PIM. See “Detaching FRONT COVER” 
    on Page 60
    .
    Start 
    Checkup
    before installation
    Marking
    Leveling
    Detaching Front Cover
    Drilling
    A 
    						