CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure Manual ND-70928 (E), Issue 1.0Page 65 Placing PIM on BASE TRAY for Stationary Equipment Place the PIM and the BASE on the BASE TRAY. Figure 2-14 Placing PIM on BASE TRAY BASE TRAY
CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure ManualPage 66ND-70928 (E), Issue 1.0 Connection of PIMs NOTE: The FRONT STOPPER, BUILD PLATES, and screws are attached to the PIM. (1) Insert the BUILD PLATES (R)/(L) into the slits of the SIDE FRAME, then slide them backward and lock them. (2) Place the FRONT STOPPER on the PIM, then secure it with three screws. Figure 2-15 Connection of BUILD PLATE BUILD PLATE (L) BUILD PLATE (R) SIDE FRAME
CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure Manual ND-70928 (E), Issue 1.0Page 67 Figure 2-16 Connection of FRONT STOPPER SCREWPIM SIDE FRAME SCREWSCREWPZ-PW121PIM TOP FRAME FRONT STOPPER SCREWS FRONT STOPPER
CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure ManualPage 68ND-70928 (E), Issue 1.0 (3) Hook the PIM onto the BUILD PLATE’s hooks. (4) Slide the PIM backward until it comes to the back end. (5) Secure the PIM with three screws. Figure 2-17 Connection of Modules SCREWS
CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure Manual ND-70928 (E), Issue 1.0Page 69 Installation of I/F BRACKET Install the I/F BRACKET to the top-stack PIMs if the equipment is stacked with four or more PIMs. Secure the I/F BRACKET to rear side of top-stack PIMs with two screws from inside of PIMs. NOTE: Screws are attached to the I/F BRACKET. SCREW FRONT SIDE SCREW I/F BRACKET
CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure ManualPage 70ND-70928 (E), Issue 1.0 Installation of TOP COVER (1) Hang four hooks of the TOP COVER on the back board of PIM as shown below. (2) Secure the TOP COVER to the front side of the PIM with two screws. NOTE: Screws are attached to BASE/TOP ASSEM. HOOK
CHAPTER 2 INSTALLATION Floor Standing Installation NEAX2000 IVS2 Installation Procedure Manual ND-70928 (E), Issue 1.0Page 71 Installation of MOUNTING BRACKET Install the MOUNTING BRACKET to the top-stack PIM if the equipment is stacked with four or more PIMs. (1) Remove four screws located on the rear side of the top-stack PIM. (2) Secure the MOUNTING BRACKET to the PIM with the removed screws. (3) Secure the PIM to the wall or ceiling by using wires, chains and eyebolts (locally provided). Figure 2-18 Installation of MOUNTING BRACKET SCREWSFRONT PIM MOUNTING BRACKET
CHAPTER 2 INSTALLATION Wall Mounting Installation NEAX2000 IVS2 Installation Procedure ManualPage 72ND-70928 (E), Issue 1.0 Wall Mounting Installation Check the site for installing the PBX with the work drawing to verify that the required floor space is ensured and that service entrances and ducts for trunk/extension cables, power cables and grounding conductors have been properly worked at correct positions. See Figure 2-7 and Figure 2-8. Detach the front cover of each PIM. See “Detaching FRONT COVER” on Page 60 . Mark hole positions for installation of the PBX main equipment. See Figure 2-19. Secure the HANGER ASSEM to the wall. Hang the PIM to the HANGER ASSEM. See Figure 2-20. NOTE:The BATTM cannot be installed on the wall. After hanging each PIM to the respective HANGER ASSEMs, connect PIMs using screws. See “Connection of PIMs” on Page 66 . Carefully review every step above to ensure that all necessary screws are properly placed and tightened. Start Checkup before installation Marking Installation of PIM Multiple-PIM Checking Detaching Front Cover End Configuration
CHAPTER 2 INSTALLATION Wall Mounting Installation NEAX2000 IVS2 Installation Procedure Manual ND-70928 (E), Issue 1.0Page 73 Figure 2-19 Wall Marking for HANGER ASSEM 352 (13.9) 356.5 (14.0)210.8 (8.3) HANGER ASSEM ANCHOR/ SCREW (x 3/PIM) BASE167.5 (7.0)167.5 UNIT : mm (inch) (7.0) 352 (13.9) 352 (13.9) 352 (13.9) 210.8 (8.3) 210.8 (8.3) 210.8 (8.3) 210.8 (8.3)
CHAPTER 2 INSTALLATION Wall Mounting Installation NEAX2000 IVS2 Installation Procedure ManualPage 74ND-70928 (E), Issue 1.0 Hanging PIM to HANGER ASSEM (1) Secure the HANGER ASSEM to the surface of a wall with three screws. Select screws to match with the wall type as follows. A concrete wall is recommended because it is the most firm to mount the PBX of the three. The plaster board is the least firm wall of the three. (2) Hang the slits of the rear of a PIM to the hooks of the HANGER ASSEM. (3) Secure the PIM to the HANGER ASSEM with two screws. NOTE: Screws are attached to the HANGER ASSEM. Figure 2-20 Hanging PIM to HANGER ASSEM WALL TYPE RECOMMENDED SCREW CONCRETE ANCHOR BOLT TYPE Recommended 4 mm (0.16 inch) by 25 mm (0.98 inch) WOOD WOOD TYPE SCREWS Min. 3.5 mm (0.14 inch) DIA Max. 4.5 mm (0.17 inch) DIA PLASTER BOARD [THICKNESS Min. 9.6 mm (0.38 inch)]MOLLY ANCHOR TYPE Min. 3.5 mm (0.14 inch) DIA Max. 4.5 mm (0.17 inch) DIA HOOK HOOK HANGER ASSEM PIM BASE SCREWS FRONT