    							CHAPTER 1 GENERAL INFORMATION
    Line/Trunk Card Mounting Conditions
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 35
    Line/Trunk Card Mounting Conditions
    (1) System Capacity for Line/Trunk Card
    Max. 64 ports per PIM
    Max. 512 ports per system
    (2) Mounting Line/Trunk Cards in PIM0
    Use Slots LT00 to LT11 to mount line/trunk cards in PIM0.
    LT11 slot (FP11 slot) of PIM0 is not available for line/trunk cards if the system is configured 
    with three or more PIMs, as this slot is used to mount FP card for that configuration.
    Figure 1-11  Line/Trunk Card Mounting Slots (PIM0)
    *18-port Line/Trunk cards can be mounted in LT00 to LT07 slots.
    *24-port Line/Trunk cards can be mounted in LT00 to LT10 slots.
    *3LT11 slot is available for 4-port line/trunk cards only when the system is configured with 
    two or less PIMs.
    LT09LT08LT07
    LTC1LTC0LTC2
    BWB
    PIM0
    FRONT
    AC/DC
    PWR
    LT10LT00LT01LT02LT03LT04LT05LT06LT11/FP11MP12
    LTC3
    DC/DC
    PWR
    PFTVM
    *2
    *3*1 
    						
    							CHAPTER 1 GENERAL INFORMATION
    Line/Trunk Card Mounting Conditions
    NEAX2000 IVS2 Installation Procedure ManualPage 36ND-70928 (E), Issue 1.0
    (3) Mounting Line/Trunk Cards in PIM1-7
    Use Slots LT00 to LT11 to mount line/trunk cards in PIM1 through 7.
    Figure 1-12  Line/Trunk Card Mounting Slots (PIM1-7)
    *1
    8-port Line/Trunk cards can be mounted in LT00 to LT07 slots.
    *2
    4-port Line/Trunk cards can be mounted in LT00 to LT11 slots.
    LT09LT08LT07
    LTC1LTC0LTC2
    BWB
    PIM
    1 - 7
    FRONTAC/DC
    PWR
    LT10LT00LT01LT02LT03LT04LT05LT06LT11FP12
    LTC3
    DC/DC
    PWR
    PFTVM
    *1
    *2 
    						
    							NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 37
    CHAPTER 2 
    INSTALLATION
    This chapter explains how to install the PBX and the peripheral equip-
    ment, system initialization and data entry, and operation test proce-
    dures you should follow after completing the installation. 
    						
    							CHAPTER 2 INSTALLATION
    Precautions
    NEAX2000 IVS2 Installation Procedure ManualPage 38ND-70928 (E), Issue 1.0
    PRECAUTIONS
    Grounding Requirements
    The system grounding must have a specific ground resistance and AC noise level, and is to be 
    connected to a predetermined terminal in the PBX. Standard grounding requirements are as
    shown below:  Communication grounding : Less than 10 ohm
       Protective ground for PIM : Less than 10 ohm
    NOTE: The AC ripple on these various grounds should be less than 0.5Vp-p.
    The following specific requirements apply to ground wiring.   An equipment grounding conductor that is at least as large as the ungrounded branch-
    supply conductors is to be installed as part of the circuit that supplies the NEAX2000 IVS
    2.
    Bare, covered, or insulated grounding conductors are acceptable. Individually covered or  
    insulated equipment grounding conductors shall have a continuous outer finish that is either  
    green, or green with one or more yellow stripes. The equipment grounding connector is to 
    be connected to ground at the service equipment.
       The attachment-plug receptacles in the vicinity of the NEAX2000 IVS
    2 are all to be of a 
    grounding type, and the equipment grounding conductors serving these receptacles are to 
    be connected to earth ground at the service equipment.
    C AU TIO N
    Grounding circuit continuity is vital for safe operation of telecommunication equipment. Never
    operate this equipment with the grounding conductor disconnected. 
    						
    							CHAPTER 2 INSTALLATION
    Static Electricity Guard
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 39
    Static Electricity Guard
    You must wear a grounded wrist strap to protect circuit cards from static electricity.
    Figure 2-1  Static Electricity Guard (1 of 2)
    
    WHEN PLUGGING/UNPLUGGING A CIRCUIT CARD
    
    WHEN HOLDING A CIRCUIT CARD
    PBX
    WRIST STRAP
    FRAME GROUND SCREW
    CARD FRONT
    NEVER TOUCH THE COMPONENTS OR 
    SOLDERED SURFACE WITH BARE HANDS. 
    						
    							CHAPTER 2 INSTALLATION
    Static Electricity Guard
    NEAX2000 IVS2 Installation Procedure ManualPage 40ND-70928 (E), Issue 1.0
    Figure 2-1  Static Electricity Guard (2 of 2)
    
    WHEN MAKING A SWITCH SETTING ON A CIRCUIT CARD
    
    WHEN CARRYING A CIRCUIT CARD
    WEAR A WRIST STRAP AND PERFORM
    THE WORK ON A GROUNDED
    CONDUCTIVE WORK SURFACE.
    CIRCUIT
    CARD
    WHEN CARRYING A CIRCUIT
    CARD AROUND, KEEP THE
    CARD IN A CONDUCTIVE
    POLYETHYLENE BAG.
    CIRCUIT
    CARDCONDUCTIVE
    POLYETHYLENE
    BAG 
    						
    							CHAPTER 2 INSTALLATION
    Procedure for Unplugging/Plugging Circuit Cards
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 41
    Procedure for Unplugging/Plugging Circuit Cards
    When removing a circuit card from the PIM or when mounting a circuit card in the PIM, follow the
    procedure in Table 2-1.
    Table 2-1  Procedure for Unplugging/Plugging Circuit Cards
    CIRCUIT CARDPROCEDURE
    CONDITION
    PLUG UNPLUG
    PN-CP14 (MP)
    PZ-PW121 (AC/DC PWR)
    PZ-PW122 (DC/DC PWR)
    PZ-M537 (EXTMEM)(1) Power off
    (2) Plug in
    (3) Power on(1) Power off
    (2) Unplug
    (3) Power onThese circuit cards must be
    plugged in or unplugged only
    with power off to prevent dam-
    age to the card or other system
    circuitry.
    PN-AP00-A (DBM)
    PN-AP00-B (AP00)
    PN-AP01 (AP01)
    PN-BRTA (BRT)
    PN-2BRTC (BRT)
    PN-CP15 (FP)
    PN-DAIA (DAI)
    PN-DAIB (DAI)
    PN-DAIC (DAI)
    PN-DAID (DAI)
    PN-DAIE (DAI)
    PN-DAIF (DAI)
    PN-24DTA-C (DTI)
    PN-30DTC-A (DTI)
    PN-IPTA (IPT)
    PN-24PRTA (PRT)
    PN-PW00 (EXTPWR)
    PN-4RSTB (MFR)
    PN-4RSTC (CIR)
    PN-SC00 (CCH)
    PN-SC01 (DCH)
    PN-SC03 (ICH)
    PN-SC03-A (CSH)
    PZ-M542 (CONN)
    PZ-M557 (CONN)
    PZ-VM00-M (VM)
    PZ-VM01 (VM)(1) Power off 
    or MB 
    switch on
    (2) Plug in
    (3) Power on 
    or MB 
    switch off(1) Power off 
    or MB 
    switch on
    (2) Unplug
    (3) Power onThese circuit cards must be
    plugged in or unplugged under
    Make Busy condition or power
    off to prevent damage to the
    card or other system circuitry. 
    						
    							CHAPTER 2 INSTALLATION
    Procedure for Unplugging/Plugging Circuit Cards
    NEAX2000 IVS2 Installation Procedure ManualPage 42ND-70928 (E), Issue 1.0
    CAUTION
    You must hold the edge of a circuit card when plugging or unplugging the circuit card. If you
    touch another area, you may be exposed to hazardous voltages.
    CARD FRONT
    NEVER TOUCH THE COMPONENTS 
    OR SOLDERED SURFACE WITH 
    BARE HANDS.
    PBX 
    						
    							CHAPTER 2 INSTALLATION
    Turning Power ON
    NEAX2000 IVS2 Installation Procedure Manual
    ND-70928 (E), Issue 1.0Page 43
    Turning Power ON
    (1) Check the switch position of each PZ-PW121 card before turning power on.
    • Make sure that the AC120V/240V selector switch is positioned to appropriate voltage for 
    each country (AC120V or AC240V).
     Make sure that the battery mode selector switch is positioned as shown below to meet the 
    kind of battery:
    (2) Turn the SW1 switches of all the PZ-PW121 cards to ON. First, turn ON PIM1 to PIM7. 
    Then, turn ON PIM0 last of all.
    CAUTION
    1. When the operating power is being supplied to the PZ-PW121 card, do not plug/unplug this
    circuit card into/from its mounting slot.
    2. When the system is configured with two or more PIMs, the BUS cable provides gang control
    for the PZ-PW121 card of PIM0 and other PIMs. Therefore, if the power of PIM0 is off, no
    power is supplied to the whole system even when the power switch(es) of other PIMs are
    left on. Note, however, that the battery continues to charge even under these circumstances.
    3. Do not turn off the PZ-PW121 card on PIM1 to PIM7 when the system is operating.
    SW
    240V 100V/120V
    ON OFF
    12
    SW101
    1 : Not used 
    2 : ON   (SEAL/FLOAT2) 
         OFF (OPEN/FLOAT1) 
      
    						
    							CHAPTER 2 INSTALLATION
    Turning Power OFF
    NEAX2000 IVS2 Installation Procedure ManualPage 44ND-70928 (E), Issue 1.0
    Turning Power OFF
    (1) Before turning power off, make sure that all line/trunk cards are not operating by no busy 
    lamps indication.
    (2) Turn the SW1 switches of all the PZ-PW121 cards to OFF. First, turn OFF PIM0. Then, turn 
    OFF PIM1 to PIM7. 
    						