    CHAPTER 5  OPERATION TEST
    LOOP-BACK TEST
    Table 5-2  Alarm Indications on the 30DTI Card (Loop-Back Test)
    LEDLED INDICATION FAULT
    NORMAL FAULT CAUSE ACTION
    RU N F la s h
    (120 IPM)On or Off Abnormal 
    operation of DTI 
    cardConfirm the programming data: 
    CM05, CM07 YY=01.
    Check to see if the SENS 
    switch is set as per the AP 
    number (04-15, 20-31) 
    assigned by CM05.
    Reset the MB switch 
    (Down→Up→Down)
    If the fault cannot be cleared, 
    replace the card.
    PCM Off On No PCM signals 
    arrive from the 
    distant officeCheck to see if the DTI cable is 
    correctly connected.
    Plug and unplug the DTI card.
    Repeat this two or three times.
    FRM Off On Frame Alignment 
    signals from the 
    distant office can 
    not be receivedCheck the receive line and 
    external equipment.
    Replace the remote DTI card.
    MFRM Off On Multi Frame 
    Alignment signals 
    from the distant 
    office can not be 
    receivedCheck the receive line and 
    external equipment.
    Replace the remote DTI card.
    RMT Off On Frame Alignment 
    signals cannot be 
    sent to the remote 
    PBXCheck the transmission line 
    and external equipment.
    Replace the DTI card.
    MRMT Off On Frame Alignment 
    signals from the 
    distant office can 
    not be receivedConfirm the switch setting on 
    the DTI card indicating an 
    alarm.
    Replace the DTI card not 
    indicating an alarm, with a 
    spare.
    AIS Off On Remote PBX is in 
    the loop-back testCheck the switch settings of the 
    remote DTI card.1
    2
    3
    4
    1
    2
    1
    2
    1
    2
    1
    2
    1
    2
    1 
    						
    							CHAPTER 5  OPERATION TEST
    LOOP-BACK TEST
    NEAX2000 IVS2 CCIS System Manual    
    ND-70918 (E), Issue 1.0   Page 309
    STEP 4: With respect to channels assigned as trunks, perform call origination and call
    termination tests. Prior to the performance test, make busy all trunks other than the
    test trunk by means of CME5.
    Dial the trunk route access code and a station number. In the case of a loop-back test,
    the same BL lamp lights up on the calling-side DTI card and the called-side DTI card.
    Talk with the called side and confirm that there is no noise nor distortion. Perform this
    test from both digital and analog stations if available.
    STEP 5: Reassign the system data, as needed.
    STEP 6: Turn off the operating power and disconnect the loop-back test cable. Then, connect
    the transmission line cable. 
    						
    							 NEAX2000 IVS2 CCIS System ManualPage 310  ND-70918 (E), Issue 1.0
    CHAPTER 5  OPERATION TEST
    Interoffice Transmission Line Test
    INTEROFFICE TRANSMISSION LINE TEST
    To confirm inter-office synchronization and speech quality using “In-Service” transmission lines,
    do the following steps.
    STEP 1: Connect the transmission line to the MDF or CONN card.
    STEP 2: Make busy the channels except the channel tested by CME5.
    STEP 3: Confirm indication lamps on the DTI card, as per the following table.
    Alarm Indications on the 24DTI Card (Loop-Back Test) on Page 307
    Alarm Indications on the 30DTI Card (Loop-Back Test) on Page 308
    STEP 4: Originate an outgoing call via trunk.
    STEP 5: After an outgoing connection via trunks has been established, confirm inter-office
    synchronization as follows:
    On the DTMF telephone set, keep pressing any dial button.
    Check to see if there are noise or abnormal tones.
    Do the above test again in the opposite direction.
    STEP 6: Repeat the test for all channels. When completed, make idle all channels by CME5. 
    						
    							CHAPTER 5  OPERATION TEST
    Interoffice Transmission Line Test
    NEAX2000 IVS2 CCIS System Manual    
    ND-70918 (E), Issue 1.0   Page 311
    Table 5-3  Alarm Indications on 24DTI (Interoffice Transmission Line Test)
    LEDLED INDICATION FAULT
    NORMAL FAULT CAUSE ACTION
    RU N F la s h
    (120 IPM)On or Off Abnormal 
    operation of DTI 
    cardConfirm the programming data: 
    CM05, CM07 YY=01.
    Check to see if the SENS 
    switch is set as per the AP 
    number (04-15, 20-31) 
    assigned by CM05.
    Reset the MB switch 
    (Down→Up→Down)
    If the fault cannot be cleared, 
    replace the card.
    CRC Off On Bit Error Rate 
    exceeds the 
    predetermined 
    valueCheck the receive line and 
    external equipment.
    Replace the remote DTI card.
    PCM Off On No PCM signals 
    arrive from the 
    distant officeCheck to see if the DTI cable is 
    correctly connected.
    Plug and unplug the DTI card.
    Repeat this two or three times.
    FRM Off On Frame Alignment 
    signals from the 
    distant office can 
    not be receivedCheck the receive line and 
    external equipment.
    Replace the remote DTI card.
    RMT Off On Frame Alignment 
    signals cannot be 
    sent to the remote 
    PBXCheck the transmission line 
    and external equipment.
    Replace the DTI card.
    AIS Off On Remote PBX is in 
    the loop-back testCheck the switch settings of the 
    remote DTI card.1
    2
    3
    4
    1
    2
    1
    2
    1
    2
    1
    2
    1 
    						
    							 NEAX2000 IVS2 CCIS System ManualPage 312  ND-70918 (E), Issue 1.0
    CHAPTER 5  OPERATION TEST
    Interoffice Transmission Line Test
    Table 5-4  Alarm Indications on 30DTI (Interoffice Transmission Line Test)
    LEDLED INDICATION FAULT
    NORMAL FAULT CAUSE ACTION
    RU N F la s h
    (120 IPM)On or Off Abnormal 
    operation of DTI 
    cardConfirm the programming data: 
    CM05, CM07 YY=01.
    Check to see if the SENS 
    switch is set as per the AP 
    number (04-15, 20-31) 
    assigned by CM05.
    Reset the MB switch 
    (Down→Up→Down)
    If the fault cannot be cleared, 
    replace the card.
    PCM Off On No PCM signals 
    arrive from the 
    distant officeCheck to see if the DTI cable is 
    correctly connected.
    Plug and unplug the DTI card.
    Repeat this two or three times.
    FRM Off On Frame Alignment 
    signals from the 
    distant office can 
    not be receivedCheck the receive line and 
    external equipment.
    Replace the remote DTI card.
    MFRM Off On Multi Frame 
    Alignment signals 
    from the distant 
    office cannot be 
    receivedCheck the receive line and 
    external equipment.
    Replace the remote DTI card.
    RMT Off On Frame Alignment 
    signals cannot be 
    sent to the remote 
    PBXCheck the transmission line and 
    external equipment.
    Replace the DTI card.
    MRMT Off On Frame Alignment 
    signals from the 
    distant office can 
    not be receivedConfirm the switch setting on 
    the DTI card indicating an 
    alarm.
    Replace the DTI card not 
    indicating an alarm, with a 
    spare.
    AIS Off On Remote PBX is in 
    the loop-back testCheck the switch settings of the 
    remote DTI card.1
    2
    3
    4
    1
    2
    1
    2
    1
    2
    1
    2
    1
    2
    1 
    						
    							CHAPTER 5  OPERATION TEST
    PLO Operation Test
    NEAX2000 IVS2 CCIS System Manual    
    ND-70918 (E), Issue 1.0   Page 313
    PLO OPERATION TEST
    To confirm the PLO operation do the following tests.
    Clock Signal Generation Test
    Clock  Signal  Synchronization  Test To be tested when the PBX is a clock receiver office.
    Interoffice Synchronization Test
    Source Office Mode Test To be tested when the PBX is a clock source office.
    Clock Signal Generation Test
    This test checks to see if the PLO keeps generating clock signals at the frequency of the previous
    source clock, when the source clock signal from network have stopped. Do the following steps
    using “In Service” transmission lines.
    STEP 1: On all the DTI cards mounted in PIM0, set the switches as follows to stop the external
    clock signal input.
    30DTI card: SW-1 and SW-2 to OFF
    24DTI card: SW0-1 and SW0-2 to OFF
    – The CLK lamp on the MP card goes out.
    STEP 2: Originate an outgoing call via trunks.
    STEP 3: After an outgoing connection via trunks has been established, confirm interoffice
    synchronization and speech quality as follows:
    On the DTMF telephone set, keep pressing any dial button.
    Check to see if noise periodically occurs on the DTMF signals coming from the call-
    ing station in the opposite office.
    Do the above test again in the opposite direction.
    STEP 4: On all the DTI cards mounted in PIM0, restore the switches as the state before testing
    to input the external clock signals.
    – The CLK lamp on the MP card lights.
    NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on
    the MP card, and do the above test again. 
    						
    							 NEAX2000 IVS2 CCIS System ManualPage 314  ND-70918 (E), Issue 1.0
    CHAPTER 5  OPERATION TEST
    PLO Operation Test
    Clock Signal Synchronization Test
    This test checks to see if the PLO keeps synchronizing with the external clock signals, when the
    external clock signals from network has input again after it has stopped once. Do the following
    steps using “In Service” transmission lines.
    (1) When providing one clock supply route 
    STEP 1: On the DTI0 card extracting clock signals, set the SW-1 and SW-2 to OFF to stop the
    external clock signal input.
    – The CLK lamp on the MP card goes out.
    STEP 2: Originate an outgoing call via trunk.
    STEP 3: After an outgoing connection via trunk has been established, confirm interoffice
    synchronization and speech quality as follows:
    On the DTMF telephone set, keep pressing any dial button.
    Check to see if noise periodically occurs on the DTMF signals coming from the call-
    ing station in the opposite office.
    Do the above test again in the opposite direction.
    STEP 4: On the DTI0 card, restore the switches as the state before testing to input the external
    clock signals.
    30DTI0 card: SW-1 to ON, SW-2 to OFF
    24DTI0 card: SW0-1 to ON, SW0-2 to OFF
    – The CLK lamp on the MP card lights.
    STEP 5: Originate an outgoing call via trunks.
    STEP 6: After an outgoing connection via trunks has been established, confirm interoffice
    synchronization and speech quality with the procedure shown in STEP 3.
    NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on
    the MP card, and do the above test again. 
    						
    							CHAPTER 5  OPERATION TEST
    PLO Operation Test
    NEAX2000 IVS2 CCIS System Manual    
    ND-70918 (E), Issue 1.0   Page 315
    (2) When providing two clock supply routes
    STEP 1: On the DTI cards extracting clock signals, set the switches as follows to change the
    clock supply route from 0 to 1.
    30DTI0 card: SW-1 to OFF, SW-2 to OFF
    30DTI1 card: SW-1 to OFF, SW-2 to ON
    24DTI0 card: SW0-1 to OFF, SW0-2 to OFF
    24DTI1 card: SW0-1 to OFF, SW0-2 to ON
    STEP 2: Originate an outgoing call via trunks.
    STEP 3: After an outgoing connection via trunks has been established, confirm interoffice
    synchronization and speech quality as follows:
    On the DTMF telephone set, keep pressing any dial button.
    Check to see if noise periodically occurs on the DTMF signals coming from the call-
    ing station in the opposite office.
    Do the above test again in the opposite direction.
    STEP 4: On the DTI cards, set the switches as follows to stop the external clock signal input.
    30DTI0/1 card: SW-1 and SW-2 to OFF
    24DTI0/1 card: SW0-1 and SW0-2 to OFF
    – The CLK lamp on the MP card goes out.
    STEP 5: Repeat the procedure shown in STEP 2 and STEP 3.
    STEP 6: On the DTI0/1 cards, set the switches as shown in STEP 1 to input clock signals from
    the clock supply route 1.
    STEP 7: Repeat the procedure shown in STEP 2 and STEP 3.
    STEP 8: On the DTI cards, set the switches as follows to change the clock supply route from 1
    to 0.
    30DTI0 card: SW-1 to ON, SW-2 to OFF
    30DTI1 card: SW-1 to OFF, SW-2 to ON
    24DTI0 card: SW0-1 to ON SW0-2 to OFF
    24DTI1 card: SW0-1 to OFF, SW0-2 to ON
    – The CLK lamp on the MP card lights. 
    						
    							 NEAX2000 IVS2 CCIS System ManualPage 316  ND-70918 (E), Issue 1.0
    CHAPTER 5  OPERATION TEST
    PLO Operation Test
    STEP 9: Repeat the procedure shown in STEP 2 and STEP 3.
    NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on
    the MP card, and do the above test again.
    Interoffice Synchronization Test
    This test checks to see if noise occurs while calling with the opposite office, by difference of the
    clock signal frequency between the offices. Do the following steps using “In Service”
    transmission lines.
    STEP 1: Originate an outgoing call via trunks.
    STEP 2: Check the speech quality (if noise, distortion or click occurs during a few minutes) with
    the opposite office mutually.
    STEP 3: On the DTMF telephone set, keep pressing any dial button, and check to see if noise
    periodically occurs on the DTMF signals coming from the calling station in the opposite
    office.
    STEP 4: Do the above test again in the opposite direction.
    NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on
    the MP card, and do the above test again.
    Source Office Mode Test
    When the PBX is operated as a clock source office, do the following steps using “In Service”
    transmission lines.
    STEP 1: Confirm that the following switches on all the DTI cards mounted in PIM0 are set to
    “OFF”.
    30DTI card: SW-1 and SW-2 to OFF
    24DTI card: SW0-1 and SW0-2 to OFF
    STEP 2: Confirm the following switches on the MP card are set to “OFF”.
    SW2-2 and SW2-3 to OFF
    SW4-2 and SW4-3 to OFF 
    						
    							CHAPTER 5  OPERATION TEST
    PLO Operation Test
    NEAX2000 IVS2 CCIS System Manual    
    ND-70918 (E), Issue 1.0   Page 317
    STEP 3: Confirm indication lamps on the MP card.
    NOTE:When the CLK lamp lights on the MP card, the clock signal is not generated from the
    MP card. Check the switch settings on the DTI and MP card.
    For details of the lamp indications, refer to CHAPTER 4 on Page 259.
    STEP 4: Originate an outgoing call via trunks.
    STEP 5: After an outgoing connection via trunk has been established, confirm interoffice
    synchronization and speech quality as follows:
    On the DTMF telephone set, keep pressing any dial button.
    Check to see if noise periodically occurs on the DTMF signals coming from the call-
    ing station in the opposite office.
    Do the above test again in the opposite direction.
    NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on
    the DTI and MP card, and do the above test again. 
    						
    All NEC manuals Comments (0)

    Related Manuals for NEC Neax 2000 Ivs2 Ccis System Manual