NDA-24234 CHAPTER 5 Page 321 Revision 3.0 INSTALLATION TEST PROCEDURE Test Outline: Tests are performed to see if system initialization can be executed. There are two kinds of test method; test by using START button on the TOPU, and test by Power ON/OFF. Figure 027-1 System Initialization via ‘Start’ Button NAP-200-027 Sheet 1/2 System Initialization Test START Perform system initialization (via “START” button) Set the SYSTEM DATA key on the TOPU to NON LOAD side, and set the PROGRAM key to NON LOAD side. Perform system initialization by pressing the “START” button on the TOPU. Confirm When the system is initialized, the “CPU OPE” lamp (Green) on the DSP circuit card lights. When the system is initialized, System Message “7-B” is displayed on the MAT. ATTENTIONContents Static Sensitive Handling Precautions Required A * To perform system initialization, set the switch keys on the TOPU as shown below, then press the START button. ALM RSTPFT ON OFFINITIAL STARTEFFECT PROGRAM LOAD SYSTEM DATA NON LOAD ON OFF NON LOAD PZ-DK222
CHAPTER 5 NDA-24234 Pag e 32 2 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-027 Sheet 2/2 System Initialization Test Perform system initialization (by powering ON/OFF). Initialization by powering ON/OFF.On all PWR Supplies, set the circuit breaker OFF (Down). If a module contains two PWR Supplies, they must be turned ON/OFF simultaneously. Turn ON the PWR Supplies in each module in the following order. If a module contains two PWR Supplies, they must be turned ON/OFF simultaneously. LPM →PIM0 →PIM1 →PIM2 →PIM3 Confirm When the system is initialized, the CPU OPE lamp (Green) on the DSP turns ON. When the system is initialized, System Message “7- B” is displayed on the MAT. Assignment of Date and Time Upon completion of all the initialization tests, assign data and time via MAT command “AT I M .” END ATTENTIONContents Static Sensitive Handling Precautions Required A *
NDA-24234 CHAPTER 5 Page 323 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-028 Sheet 1/1 Circuit Card Initialization Test START Make the No. 0 CPU the ACT system. In each PIM, initialize any Line/Trunk circuit card.On the selected Line/Trunk circuit card, set the MB switch UP. The OPE lamp goes out. System Message “7-K” is displayed. Set the MB switch DOWN. The OPE lamp turns ON. System Message “7-L” is displayed. Clear the alarm Clear the alarm indication by pressing the “ALM RST” button on the TOPU. Make the No. 1 CUP the ACT system. In each PIM, initialize any Line/Trunk circuit card.On the selected Line/Trunk circuit card, set the MB switch UP. The OPE lamp goes out. System Message “7-K” is displayed. Set the MB switch DOWN. The OPE lamp turns ON. System Message “7-L” is displayed. Clear the alarm Clear the alarm indication by pressing the “ALM RST” button on the TOPU. END *
CHAPTER 5 NDA-24234 Pag e 32 4 Revision 3.0 INSTALLATION TEST PROCEDURE 4. PORT CONNECTION TEST 4.1 Outline Tests are to be performed on all the circuits of LC and Trunk circuit cards and PWR Supplies. LC and Trunk circuit cards are tested with respect to their operations and speech path conditions. PWR Supplies are tested with respect to howler tone and ringing signal. While tests are in progress, the No. 0 CPU and TSW systems must be ACT (active). 4.2 Port Connection Test Procedure The connection test procedure for each type of circuit card is described in the NAP indicated to the right of each item in the following flowchart. START ORT (RST Card) Connection Test:NAP-200-029 ATTCON (ATI Card) Connection Test:NAP-200-030 Line (LC, ELC Card) Connection Test:NAP-200-031 Outgoing Trunk (COT, TLT, DTI Card) Connection Test:NAP-200-032 Incoming Trunk (COT, TLT, DTI Card) Connection Test:NAP-200-033 Direct-In Termination Trunk (COT Card) Connection Test:NAP-200-034 SND (RST Card) Connection Test:NAP-200-035 3-Party Conference Trunk Function Test:NAP-200-036 Connection Test - Announcement Trunk for Announcement Service:NAP-200-037 Connection Test - Digital Announcement Trunk for Announcement Service:NAP-200-038 Connection Test - Paging Trunk for Paging Access Service:NAP-200-039 Connection Test - Paging Trunk for Paging Transfer Service:NAP-200-040 Radio Paging Trunk (COT Card) Connection Test:NAP-200-041 Howler and Ringing Signal Test:NAP-200-042 END
NDA-24234 CHAPTER 5 Page 325 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-029 Sheet 1/2 ORT (RST Card) Connection Test START Make busy all ORTs On the front of the RST card, set all MBR switches (0-7) to the OFF position, making all ORTs busy. From Station “A” (DP), test ORTs one circuit at a time.Un-busy (make idle) only the ORT to be tested. Station “A” goes off-hook and after hearing DT, dials the station number of Station “B.” Station “A” confirms ringing to Station “B” and Station “B” answers. Stations “A” and “B” go on-hook. From Station “B” (PB), test ORTs on circuit at a time.Un-busy only the ORT to be tested. Station “B” goes off-hook and after hearing DT, dials the station number of Station “A.” Station “B” confirms ringing to Station “A” and Station “A” answers. Stations “A” and “B” go on-hook. LC ORT A (DP)DT, RBT LCB (PB) RG A * *
CHAPTER 5 NDA-24234 Pag e 32 6 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-029 Sheet 2/2 ORT (RST Card) Connection Test Perform tests for a situation where all ORTs are busy. System Data SYS1, INDEX 4, b 0 =0Station “A” goes off-hook. Station “A” confirms that Reorder Tone (ROT) is heard Station “A” goes off-hook. System Data SYS1, INDEX 4, b 0 =1Station “A” goes off-hook. Station “A” confirms that no tone is heard. Un-busy (make idle) a single ORT circuit. Station “A” confirms that DT is heard. Station “A” goes off-hook. END A *
NDA-24234 CHAPTER 5 Page 327 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-030 Sheet 1/1 ATTCON (ATI Card) Connection Test START A station repeats an ATTCON call. Each ATTCON answers the call.Station “A” dials the operator access code (normally, “0”). At each ATTCON, the operator confirms that the ATT lamp flashes and the ringer sounds. At each ATTCON, the operator answers the call by pressing the ATND key. Station “A” confirms speech with each ATTCON. The operator at each ATTCON releases by pressing the CANCEL key. Station “A” goes on-hook. Each ATTCON calls a station by pressing LOOP keys one at a time.At each ATTCON, the operator dials the number of Station “A” by using LOOP keys (L1-L6) one at a time. Ringing at Station “A” is confirmed. Station “A” answers the call and confirms speech. The operator at the ATTCON releases by pressing the CANCEL key. Station “A” goes on-hook. END ATI DT, RBT LCA ATI ATTCON * *
CHAPTER 5 NDA-24234 Pag e 32 8 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-031 Sheet 1/1 Line (LC, ELC, DLC, Card) Connection Te s t An ATTCON or Dterm is called from each station. The called party confirms the station number.On the MDF, a telephone set is connected to the line circuit to be tested The station (XXXX) to be tested goes off-hook and confirms DT (Dial Tone). The station (XXXX) calls an ATTCON or D term. The called ATTCON or D term answers the call, and confirms speech and the station number of the calling station. The call is released. The ATTCON or D term calls a station being tested.The ATTCON or Dterm dials the station number of the station being tested. The called station answers and confirms speech. The ATTCON or D term confirms that the number dialed and the number of the station being tested are the same. The call is released. The test conducted when the station involved is assigned as a Hot Line/House Phone.The station being tested goes off-hook and confirms Ring Back Tone (RBT). The station checks whether the call is routed to the predetermined station/ATTCON or that a call is originated to a predetermined trunk. The called side answers the call and confirms speech. The call is released. END Line being tested (XXXX) ATTCON D term ATI/ELC LC/ELC DT, RBT A * *
NDA-24234 CHAPTER 5 Page 329 Revision 3.0 INSTALLATION TEST PROCEDURE Test Outline: The purpose of this test is to confirm, by setting up an outgoing connection test for each outgoing trunk, that speech can be made and that the call can be released. Outgoing trunks must be tested one at a time using the sequence of Routes and Trunk Numbers assigned at each office NAP-200-032 Sheet 1/3 Outgoing Trunk (COT, TLT, DTI Card) Connection Test START When a C. O. Line or Tie Line is not connected with a trunk circuit, temporary cross connections between the Outgoing trunk being tested and the terminating trunk should be set up on the MDF as a loop-back circuit.Referring to Figures 032-1 through 032-3, make temporary cross connections on the MDF for a loop-back circuit. Temporarily assign Office Data from the MAT so that a loop- back connection from the trunk can be established. Make busy all Outgoing Trunks. On the front of the Trunk circuit card, set the MB switch to the OFF position, making the trunk busy. Test the trunk circuits one at a time by establishing access from a station.Un-busy (make idle) only the trunk to be tested. The station dials the Access Code of the trunk being tested and the number for the call destination. The called side answers. The station confirms speech. The call is released. Make temporary cross connections for the next trunk to be tested. Restore the temporary connections, temporary Office Data, etc. to the original. END
CHAPTER 5 NDA-24234 Pag e 33 0 Revision 3.0 INSTALLATION TEST PROCEDURE Set up a loop-back connection between the COT (C.O. Trunk) to be tested and a station line. Figure 032-1 COT Test Configuration The trunk route must be assigned for Loop Start. Figure 032-2 TLT Test Configuration Set up a loop-back connection between the TLT (Tie Line Trunk) to be tested and another EMT. If the TLT is a DID (Direct Inward Dialing) Trunk, connected the related leads as shown below. If the TLT is a 2W E&M System, connect the related leads as shown below. NAP-200-032 Sheet 2/3 Outgoing Trunk (COT, TLT, DTI Card) Connection Test LCC LCB LCACOT LCTLTA LCBTLT T RT RTLT TLT T RT R E ME M TLT TLT