NDA-24234 CHAPTER 5 Page 311 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-025 Sheet 1/1 Station to Station Connection Test START Confirm that a connection can be established between Station “A” and Station “B.” Station “A” goes off-hook. Station “A” hears DT. Station “A” dials the station number of Station “B.” Station “A” confirms that DT stops when the first digit has been dialed. Station “A” confirms that RBT (Ring Back Tone) is heard after dialing ends. Station “B” hears ringing on the telephone set. Station “B” lifts handset and answers the call. After answering, both Stations “A” and “B” confirm that they can talk with each other. Stations “A” and “B” hang up. The connection is released. END LC ORT ADT, ROT LCB RG * * * * *
CHAPTER 5 NDA-24234 Pag e 31 2 Revision 3.0 INSTALLATION TEST PROCEDURE 3. SYSTEM INITIALIZED TEST 3.1 Outline Tests are to be performed on the restart processing (reinitialization) and system changeover functions which en- able the system to restart its operations and services. 3.2 System Initialized Test Procedure The System Changeover Test and Initialization Tests are to be performed per the NAP Numbers indicated to the right of each item in the following flowchart. START System Changeover Test:NAP-200-026 System Initialization Test:NAP-200-027 Circuit Card Initialization Test:NAP-200-028 END
NDA-24234 CHAPTER 5 Page 313 Revision 3.0 INSTALLATION TEST PROCEDURE Test Outline: Tests are performed to see if a changeover of the dual systems (Control Systems and Speech Path Systems) of the PBX can be executed. NAP-200-026 Sheet 1/7 System Changeover Test Single IMG and Multiple IMG Configuration START Perform a Control System Changeover test by switch operations Control System change- over via MBR switch on the DSP (PZ-DK224) cardOn the DSP card of which OPE lamp is turning ON, flip the “MBR” switch DOWN➝UP➝DOWN (OFF➝ON➝OFF). The lamp indication of the DSP changes to “DSP in ST-BY mode” shown in Figure 026-1. System message “7-C” and “7-D” are displayed in succession. CPU changeover via switch (Forced Change- over)Designate CPU changeover via the “CPU SEL” switch on the EMA (PH-PC 40) card. CPU SEL SW UP Position: No. 0 ACT CPU SEL SW DOWN Position: No. 1 ACT System Messages “7-C” and “7-D” are displayed in succession. ATTENTIONContents Static Sensitive Handling Precautions Required A
CHAPTER 5 NDA-24234 Pag e 31 4 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 026-1 How to Perform a Control System Changeover (Single IMG Configuration) Figure 026-2 How to Perform a Control System Changeover (Multiple IMG Configuration) NAP-200-026 Sheet 2/7 System Changeover Test Single IMG and Multiple IMG Configuration ATTENTIONContents Static Sensitive Handling Precautions Required Flip the MBR switch on the DSP.CPUOPEWDT IMG0 IMG1 IMG2 IMG3 MBR LegendDSP in ACT modeDSP in ST-BY mode : Lamp is OFF : Lamp is Flashing (Green) : Lamp is ON (Green) CPUOPEWDT IMG0 IMG1 IMG2 IMG3 MBR Flip the MBR switch on the DSP.CPUOPEWOT IMG0 IMG1 IMG2 IMG3 MBR LegendDSP in ACT modeDSP in ST-BY mode : Lamp is OFF : Lamp is Flashing (Green) : Lamp is ON (Green)CPUOPEWDT IMG0 IMG1 IMG2 IMG3 MBR
NDA-24234 CHAPTER 5 Page 315 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 026-3 LEDs and Switches on TSW/MUX NAP-200-026 Sheet 3/7 System Changeover Test Single IMG Configuration Perform a TSW system changeover test by means of switch operations. (Refer to Figure 026-3) TSW changeover via switch.On the TSW (PH-SW10) card on which the “TSW ACT” lamp is turning ON, flip the “TSW MBR” switch DOWN-UP-DOWN. System Messages “7-E,” “7-F” and “1-T” are displayed in succession. Perform a PLO system changeover test, if TSW (PH-SW10) is provided in dual. On the TSW card of which PLO ACT lamp is turning ON, flip the “PLO MBR” switch DOWN-UP-DOWN. System message “7-G” and “7-H” are displayed in succession. END ATTENTIONContents Static Sensitive Handling Precautions Required A FRONT VIEW TSW (PH-SW10) MUX (PH-PC36) TSW ACT MUX ACTMUX ACT MB PLO ACT MB TSW MBR PLO MBR
CHAPTER 5 NDA-24234 Pag e 31 6 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-026 Sheet 4/7 System Changeover Test Multiple IMG Configuration Perform a Speech Path system changeover test by switch operations. (Refer to Figure 026-4) TSW changeover via switchOn the active GT (PA-GT09) card on which the “OPE/MB” lamp is illuminating, flip the “MBR” switch DOWN-UP- DOWN. Make sure that the active Speech Path system has been changed over to the ST-BY mode. (Check all the related circuit cards, which were formerly active, have been totally changed over to the ST-BY mode. Analyze the system messages “7-E,” “7-F” and “1-T” to be displayed automatically. Perform a PLO system changeover test by switch operations. (Refer to Figure 026-3) PLO changeover via switch.On the PLO card on which the “ACT/OPE” lamp is illuminating, flip the “MB” switch DOWN-UP-DOWN. Note Make sure that the active PLO system has been changed over to the ST-BY mode (“ACT/O PE” lamp goes OFF). END Analyze the system messages “7-U” and “7-V” to be displayed automatically. Note:As the PLO, any of the following cards can be used: PH-CK16 PH-CK17 PH-CK16-A PH-CK17-A ATTENTIONContents Static Sensitive Handling Precautions Required A Circuit Cards to be affected TSW (PH-SW12) DLKC (PH-PC20) MUX (PH-PC36) Note:Refer to Figure 026-4.
NDA-24234 CHAPTER 5 Page 317 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 026-4 LEDs and Switches for System Changeover (Multiple IMG Configuration) NAP-200-026 Sheet 5/7 System Changeover Test Multiple IMG Configuration ATTENTIONContents Static Sensitive Handling Precautions Required MUX (PH-PC36) MUX ACT MBTSW (PH-SW12)GT (PA-GT09) OPE/MB MBRMBDLKC (PH-PC20) OPE/MB MB FRONT VIEW TSW ACT TSW MBRMB PLO Note 1 OPE/ACT Note 2 MB Note 1:PH-CK16/PH-CK17, or PH-CK16-A/PH-CK17-A Note 2:“OPE” for PH-CK16-A/PH-CK17-A, “ACT” for PH-CK16/PH-CK17
CHAPTER 5 NDA-24234 Pag e 31 8 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 026-5 System Block Diagram (TSW and MUX) (Multiple IMG Configuration) NAP-200-026 Sheet 6/7 System Changeover Test Single IMG Configuration LC/TRK LC/TRK LC/TRK LC/TRK MUX MUX MUX MUX TSW/INT/PLO CPU GT LANI PCM HW PM BUS PCM HW PM BUS PCM HW PM BUS PCM HW PM BUS D T GTSW/INT PLOLV D S MUX CFT From EM A MUSIC MUX LC/TRK PHSW10DTI DCS CPR
NDA-24234 CHAPTER 5 Page 319 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 026-6 System Block Diagram (GT and Other Controlling Blocks) (Multiple IMG Configuration) NAP-200-026 Sheet 7/7 System Changeover Test Multiple IMG Configuration This figure shows a system block diagram centering on the CPU and its controlling GT. Although each side ap- pears to have complicated connections, the controlling route of CPU 0 goes directly to GT 0, and that of CPU 1 to GT 1. Therefore, if the system of CPU is once changed over, the ACT/ST-BY of GT is also changed over. MUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUX IMG 0 IMG 1 IMG 2 IMG 3 TSW 00TSW 10 TSW 11 TSW 12 TSW 03TSW 13 DLKC 0 DLKC 1 TSW 01TSW 02 TSW I/O BUSTSW I/O BUS GT 0GT 1 LANILANI CPR 1 LANILANI CPR 0 PLO 1 PLO 0 ISAGT CPU 1ISAGT CPU 0 EMA IOC/ MISC MISC BUS ISAGT: PZ-GT13 DLKC: PH-PC20 LANI: PZ-PC19 EMA: PH-PC40 GT: PH-GT09 IOC: PH-IO24TSW: PH-SW12 PLO: PH-CK16/17, or PH-CK16-A/17AMUX: PH-PC36 Note:Because the ACT/ST-BY changeover of CPU also affects the GT status, the MBR key on the GT card is not used for GT system changeover. The key is used to switch over the Speech Path System, involving the TSW, DLKC, and MUX circuit cards. (See the next page.) As shown below, though an ex- ternal cable is physically con- nected between ISAGT #0 and GT #1, the actual control signal is sent/received only between IS- AGT 0 and GT 0 via the back- board bus. GT 0GT 1 ISAGT0 CPU IOP0 Backboard External Cable Backboard BusT
CHAPTER 5 NDA-24234 Pag e 32 0 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 026-7 System Block Diagram (Speech Path) (Multiple IMG Configuration) NAP-200-026 Sheet 8/8 System Changeover Test Multiple IMG Configuration This figure shows a system block diagram centering on the GT and its controlling Speech Path System. By chang- ing over the ACT/ST-BY of the Speech Path System, all the related systems, such as TSW/INT, DLKC, and MUX, are totally switched over. The changeover can be executed by a key operation on the active GT card. MUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUXMUX IMG 0 IMG 1 IMG 2 IMG 3 TSW 00TSW 10 TSW 11 TSW 12 TSW 03TSW 13 DLKC 0 DLKC 1 TSW 01TSW 02 TSW I/O BUSTSW I/O BUS LANILANI CPR 1 LANILANI CPR 0 PLO 1 PLO 0 ISAGT: PZ-GT13 DLKC: PH-PC20 LANI: PZ-PC19 GT: PH-GT09 TSW: PH-SW12 PLO: PH-CK16/17, or PH-CK16-A/17AMUX: PH-PC36 Note:If the MBR key is once flipped on the active GT card, all the Speech Path related systems (TSW/INT, DLKC, and MUX) in the same switching block are totally changed over. However, the ACT/ST of GT and PLO is not affected. PM BUS PCM HW PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUS PM BUSPM BUS PCM HW PCM HW PCM HW PCM HW PCM HW PCM HW PCM HW PCM HW PCM HW PCM HW PCM HWPCM HW PCM HW PCM HW PCM HW Line/Trunk PM Line/Trunk PM Line/Trunk PM Line/Trunk PM ISAGT CPU 0 GT 0 GT 1 CPU 1 ISAGT