    							NDA-24234 CHAPTER 3
    Page 61
    Revision 3.0
    INSTALLATION PROCEDURE
    4. PROCEDURE FOR FANU IN THE FAN BOX
    When any IMG is configured by 3 or 4 PIMs, the FANU must be accommodated within the FAN BOX in the center
    of the cabinet. Because the FANU is originally mounted on the TOPU as shown in Figure 005-3, relocate the FANU
    into the dedicated FAN BOX as per the STEPs below:
    STEP 1: Referring to Figure 005-3, remove the FANU from the TOPU.
    Remove the two screws fastening the PZ-M369. Then, lift away the PZ-M369.
    Remove the four screws fastening the FAN Mounting Plate (tipped with three FANs).
    Then, lift away the FAN Mounting Plate.
    Note:Retain the removed screws.
    STEP 2: Fasten the PZ-M369 and FAN Mounting Plate onto the FAN BOX connection bar (refer to Figure
    005-8). Use two screws (for PZ-M369) and four screws (for FAN Mounting Plate) retained in STEP
    1.
    STEP 3: Connect the FAN cables for “FC0,” “FC1” and “FC2” connectors on the PZ-M369. Refer to Figure
    005-9.
    STEP 4: Insert the FANU, prepared in STEP 1 through STEP 3, into the FAN BOX. Then, secure the FANU
    with the two screws (refer to Figure 005-8).
    NAP-200-005
    Sheet 8/16
    Mounting of Units and Modules 
    						
    							CHAPTER 3 NDA-24234
    Page 62
    Revision 3.0
    INSTALLATION PROCEDURE
    Figure 005-8  Relocation of FANU and Insertion into FAN BOX
    NAP-200-005
    Sheet 9/16
    Mounting of Units and Modules
    Screws for FAN Mounting Plate
    Screws for PZ-M369FAN BOX connection bar FAN BOX connection bar
    FAN BOX
    Note
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    Note:Before inserting the FANU into the FAN BOX, connect the FAN cables for “FC0,” “FC1,” and “FC2”
    connectors on the PZ-M369. Refer to Figure 005-9. 
    						
    							NDA-24234 CHAPTER 3
    Page 63
    Revision 3.0
    INSTALLATION PROCEDURE
    Figure 005-9  FAN Cable Connections for FC0/FC1/FC2 Connectors
    NAP-200-005
    Sheet 10/16
    Mounting of Units and Modules
    FC0 FC1 FC2
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    FAN0 FAN1 FAN2
    PZ-M369
    Before installing the FANU into the FAN BOX, connect FAN cables as shown below. 
    						
    							CHAPTER 3 NDA-24234
    Page 64
    Revision 3.0
    INSTALLATION PROCEDURE
    STEP 5: Fix a FAN fuse (5.0A) onto the PZ-M369 by referring to Figure 005-4.
    STEP 6: Connect the remaining FAN cables as per Figure 005-10 and Figure 005-11.
    STEP 7: Lastly, attach the Top Cover onto the TOPU of the cabinet. Then, fasten the four screws (refer to Fig-
    ure 005-7).
    Note:The procedures, STEP 1 through STEP 7, must be performed at each PBX cabinet adopting 3-PIM or 4-
    PIM configurations.
    NAP-200-005
    Sheet 11/16
    Mounting of Units and Modules 
    						
    							NDA-24234 CHAPTER 3
    Page 65
    Revision 3.0
    INSTALLATION PROCEDURE
    Figure 005-10  Cable Connections for FANU in FAN BOX
    NAP-200-005
    Sheet 12/16
    Mounting of Units and Modules
    FAN BOX
    PZ-M369TH0TH1TH2FAN TALM0
    Note 2
    TALM
    THM
    TOPU (Top View)
    Note 1
    PZ-M369 (Front View)
    NECNEAX 2400 IMS
    PBX
    TOPU
    NEAX 2400 IMSNEC
    .
    .
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    T
    H
    2T
    H
    2(           )
    T
    H
    1T
    H
    1
    T
    H
    0T
    H
    0
    T
    A
    L
    M
    0T
    A
    L
    M(           )(           )
    Note 1:For details on the “FA N” connector (PIM backplane), refer to Figure 005-11.
    Note 2:For details on the “TALM” connector (TOPU), refer to Figure 005-3. 
    						
    							CHAPTER 3 NDA-24234
    Page 66
    Revision 3.0
    INSTALLATION PROCEDURE
    Figure 005-11  Connection of “FA N” Connector Cable (FAN BOX-PIM)
    NAP-200-005
    Sheet 13/16
    Mounting of Units and Modules
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    (FAN)
    FAN BOX
    PBX
    FAN power cable
    FAN power cable
    (FAN)
    FAN BOX
      TH2  TALM1   TALM0
      TH1   TH0   FC0   FC1   FC2ON
    OFF
    Auto  FAN
    PZ-M369 
    						
    							NDA-24234 CHAPTER 3
    Page 67
    Revision 3.0
    INSTALLATION PROCEDURE
    5. ATTACHING THE ADDITIONAL NOISE FILTER UNIT (NFILU) TO THE BASEU
    The following flowchart shows the procedure for attaching the Additional Noise Filter Unit (NFILU) to the BASEU
    of the PBX. This work should be performed when the module stack contains 3 or 4 PIMs.
    NAP-200-005
    Sheet 14/16
    Mounting of Units and Modules
    START
    Referring to Figure 005-12 and Figure 005-13, insert the NFILU to BASEU and attach the NFILU with 
    two screws.
    Referring to Figure 005-14, connect the cables equipped with NFILU to the terminals on the BASEU.
    END 
    						
    							CHAPTER 3 NDA-24234
    Page 68
    Revision 3.0
    INSTALLATION PROCEDURE
    Figure 005-12  Insertion of NFILU
    Figure 005-13  Attaching of NFILU
    NAP-200-005
    Sheet 15/16
    Mounting of Units and Modules
    NOISE FILTER UNIT (NFILU)
    SCREW
    BASEU
    SCREW
    SC
    RE
    WS
    BASEU 
    						
    							NDA-24234 CHAPTER 3
    Page 69
    Revision 3.0
    INSTALLATION PROCEDURE
    Figure 005-14  Cabling Diagram of NFILU
    NAP-200-005
    Sheet 16/16
    Mounting of Units and Modules
    (-48VB)
    (GB0)
    (G)
    (-48V)
    (PZ-M371)
    Additional 
    Noise Filter 
    Unit (NFILU)(3) (4)
    (1) (2)
    (1) (2)
    (PZ-M377)
    FRONT
    Already Attached 
    Noise Filter Unit
    BASEU
    (GB1) 
    						
    							CHAPTER 3 NDA-24234
    Page 70
    Revision 3.0
    INSTALLATION PROCEDURE
    This NAP explains the procedures for installing the power equipment.
    Note:The Circuit Breaker (NFB) for the Rectifiers DC output must remain OFF.
    NAP-200-006
    Sheet 1/1
    Installation of Power Equipment
    START
    Install the power equipment at the predetermined location using anchor bolts, etc. Install the framework 
    for the batteries to be used for backup. Secure the framework using anchor bolts, etc.
    Check the cabling at the primary and secondary sides of the power equipment, and the cabling to the 
    batteries
    Confirm that the specifications of the customer-installed AC PDB (NFB capacity, voltage, phase, etc.) 
    conform to the specifications of the Rectifier.
    Confirm that the proper communication ground is available.
    Connect the input power cable and grounding cable to the rectifier.
    Supply electrolyte to each battery as per the specifications of the battery.
    Charge the batteries after verifying that the rectifier is operating normally.
    END 
    						