    							NDA-24306 CHAPTER 4
    Page 273
    Revision 1.0
    CHAPTER 4 SYSTEM STARTUP
    1. GENERAL
    This chapter describes the method to start up the system initially after completion of the installation of the PBX,
    and the method to check as to whether the system has started up normally. Before beginning the system startup,
    thoroughly read Section 2., “PRECAUTIONS BEFORE BEGINNING SYSTEM STARTUP” in this chapter,
    and observe the precautions while performing the system startup. Failure to so may delay the system cutover or
    may result in damage to the system equipment.
    2. PRECAUTIONS BEFORE BEGINNING SYSTEM STARTUP
    1. The system is to be started up using the basic system data.
    2. When starting up the system, it is necessary to start up the MAT.
    3. The following preparatory steps must be completed before the tests are begun:
     All circuit card switches should be correctly set.
     Flat cables should be securely connected.
     CHAMP connectors should be securely connected.
     All connector-ended cables should be secured at both ends.
     The –48 V (Blue) and G (Red) power supply leads must be correctly connected.
     An earth lead (less than 10 ohms) must be connected to the communication ground.
     The installer should confirm at this point that all installation steps have been completed.
    4. Do not place any object (a tool, manual, etc.) on top of the Module Group or within a unit (module).
     An object such as a book, when placed on top of the Module Group, will adversely affect heat dissipa-
    tion from the Module Group.
     If an object placed on top of the Module Group or left within a unit (module) falls out, it may cause
    backplane pins, circuit cards, etc. to short-circuit.
    5. Before initially turning ON power to the system, read the Power On Procedure (NAP-200-018).
     Until the normal operation of all circuit cards has been confirmed, leave power ON only during testing.
    6. Observe the temperature in the switch room.
     Does the air-conditioning function properly at night?
     Does the temperature fluctuate constantly because people go in and out frequently, or rise above the rec-
    ommended level due to excessive heat being generated by any single piece of equipment?
     The fan should be left ON constantly until the installation tests are completed. 
    						
    							CHAPTER 4 NDA-24306
    Page 274
    Revision 1.0
    SYSTEM STARTUP
    7. A floppy disk (FD) copy of the programmed Office Data should be created. If a backup is not made, and
    the contents of the Data Memory are accidentally altered or destroyed, all the Office Data will have to be
    programmed again.
    8. If any portion of the Office Data (especially data related to ringing patterns) has been changed via com-
    mands “ARTD/ARTDN,” “AKYD,” or “ASYD/ASYDL/ASYDN,” the system must be initialized and tests
    involving the changed data must be performed.
    9. After the system is initialized, perform the following.
     Set the current date and time using MAT command “ATIM/ATIMN.”
     When the system is initialized, the system begins operating in Day Mode. To change over to Night
    Mode, press the NITE key on the Attendant Console.
     If no Attendant Console is equipped, the system begins operating in night mode.
    10. The following cross connections must be made at the MDF:
     Complete necessary cross connections by extracting the related circuit cards from their mounting slots
    or by disconnecting the circuits with a cut plug if test springs are in use.
     If the connection to a D
    term is made incorrectly, the electronic fuse of the circuit card will blow out.
    (Repair Method:  Correct the cross connections and flip the MB switch on the card Down-Up-Down).
     While a test is in progress, do not perform cross connections without first consulting with the person
    conducting the test (Ringing signal: AC 20 Hz, effective value 90 V, may be flowing through the termi-
    nals).
     Remove all temporary cross connections after the tests have been performed (If Office Data was as-
    signed for test purposes, restore the original Office Data).
    11. Observe the following when connecting cables:
     Before connecting or disconnecting the control cable (Front & Backplane), turn OFF the power to the
    Module Group (LPM / PIM etc).
     Before connecting or disconnecting a CHAMP connector, turn OFF the power to the Module Group.
    This will prevent an accident from occurring in the event that a metal object such as a screw, screwdriver,
    etc. accidentally contacts the backplane circuitry or pins.
     When connecting or disconnecting the connector cable of the Attendant Console, first set the MB switch
    on the ATI circuit card to the UP position, then connect/disconnect the cable.
    12. Precautions when Handling Circuit Cards
     When handling a circuit card, use a Field Service Kit to protect against static discharge (example:  3M
    No. 8012 Portable Field Service Kit; available from NEC).
     When touching a circuit card, be sure to wear the grounded wrist strap provided with the Portable Field
    Service Kit.
     Set the MB switch to the UP position and extract the circuit card from its mounting slot. 
    						
    							NDA-24306 CHAPTER 4
    Page 275
    Revision 1.0
    SYSTEM STARTUP
     When holding a circuit card with bare hands, do not touch the component mounted side of the card or
    the connector portion.
    Wrist Strap
    Place the Circuit 
    Card on a 
    conductive sheet. Connect ground wire to the Earth 
    terminal of the Module Group.
    (Component-Mounted 
    Side)
    Connector 
    (Contact) PortionFront Side
    Card Puller Tab 
    						
    							CHAPTER 4 NDA-24306
    Page 276
    Revision 1.0
    SYSTEM STARTUP
     When placing a circuit card on a table or other flat surface, spread out a conductive sheet and set the
    card on the sheet.
     Set the MB switch of the circuit card to the UP position and confirm its mounting slot (Note). Then in-
    sert the card into its mounting slot.
    Note:Confirm that the color of the card puller tab is the same as the color of the label showing the Slot Number.
    3. SYSTEM STARTUP PROCEDURE
    The NAPs indicated in the following flowchart describe the procedures for powering on, starting up the system,
    assigning Office Data, and checking the startup conditions.
    START
    Power ON:NAP-200-018
    Program Install/Load:NAP-200-019
    Office Data Assignment:NAP-200-020
    Check of Lamp Indication and System Messages:NAP-200-021
    Check of Alarm Lamps of the TOPU:NAP-200-022
    END
    Circuit 
    Card
    Perform work on the conductive sheet 
    while wearing a grounded wrist strap.  
    						
    							NDA-24306 CHAPTER 4
    Page 277
    Revision 1.0
    SYSTEM STARTUP
    NAP-200-018
    Sheet 1/2
    Powe r  ON
    START
    Visual Inspection Check whether any pins are shorting on the backplane of each 
    Module.
    Check whether any foreign matter such as a cleaning fluid 
    residue is present on the connector portion of the circuit cards.
    On each circuit card equipped with ROM (CPU, etc.), check 
    whether any pins of the ROM are bent or improperly seated.
    Leave all circuit cards inserted 
    halfwayMount all circuit cards (including PWR Supplies) in the 
    Module, leaving them inserted only halfway. (They should not 
    be inserted into their connectors.)
    Check  input  voltage Check insulation across the -48 V and G terminals on the power 
    receiving terminal of the Base Unit.
    Turn power to the rectifier ON and check the voltage (DC -48V 
    ± 5V) and its polarity on the power receiving terminal of the 
    Base Unit.
    Turn ON Fan Units Turn FAN UNIT ON.
    Verify that air is blown upwards.
    If the Fuse blows, the input polarity is reversed.
    Turn OFF the FAN UNIT.
    Correct polarity, replace the fuse and turn FAN UNIT ON.
    Verify that the FAN blows air upwards.
    Check  PWR  Supply Check the Power Supplies for each Module one at a time. Check 
    Steps:
    1. Turn circuit breaker OFF and insert the PWR Supply.
    2. Turn circuit breaker ON (See Note).
    3. Various lamps (Green) illuminate.
    4. Observe the PWR Supply for a while and confirm that 
    nothing abnormal (unusual smell, smoke, etc.) occurs.
    5. Turn the circuit breaker ON/OFF a few times and observe the 
    condition.
    6. Turn the circuit breaker OFF and remove the PWR Supply.
    Note:If a Module is equipped with dual PWR Supplies, they
    must be turned ON/OFF simultaneously.
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    A 
    						
    							CHAPTER 4 NDA-24306
    Page 278
    Revision 1.0
    SYSTEM STARTUP
    NAP-200-018
    Sheet 2/2
    Powe r  ON
    Insert all PWR Supplies Insert all PWR Supplies into their positions.
    Insertion Steps:
    1. Turn each Power Supply’s circuit breaker OFF and insert 
    them one at a time.
    2. Turn circuit breakers ON.
    3. Confirm that there are no abnormal indications (unusual 
    smell, smoke, alarm, etc.)
    Insert and check Line/Trunk 
    circuit cardsInsert Line (16LC, etc.) and Trunk (16COT, etc.) circuit cards
    into their backplane connectors one at a time and confirm that
    no fuses are blown in the process.
    Check Steps:
    1. Set MB switch UP and insert the card.
    2. Set MB switch DOWN.
    3. Confirm that there are no abnormal indications.
    4. Set MB switch UP and remove the card.
    Insert and check control system
    cardsInsert control system circuit cards (TSW, MUX, etc.) one at a
    time and confirm that no fuses are blown in the process.
    Check Steps:
    1. Set MB switch UP and insert the card.
    2. Set MB switch DOWN.
    3. Confirm that there are no abnormal indications.
    4. Set MB switch UP and remove the card.
    Note:If a Module contains dual PWR Supplies, they must be turned ON or OFF simultaneously.
    For LNs: IMG3 → IMG2 → IMG1 → IMG0
    IMG3:  PIM0 → PIM1 → PIM2 → PIM3
    IMG2:  TSWM1 → PIM0 → PIM1 → PIM2 →PIM3
    IMG1:  TSWM0 → PIM0 → PIM1 → PIM2 → PIM3
    IMG0:  CPR0 → CPR1 → PIM0 → PIM1 → PIM2 → PIM3
    For ISW: CPR0 → CPR1 → ISWM
    For LNs:IMG3 → IMG2 → IMG1 → IMG0
    IMG3:  PIM3 → PIM2 → PIM1 → PIM0
    IMG2:  PIM3 → PIM2 → PIM1 → PIM0 → TSWM1
    IMG1:  PIM3 → PIM2 → PIM1 → PIM0 → TSWM0
    IMG0:  PIM3 → PIM2 → PIM1 → PIM0 → CPR1 → CPR0
    For ISW: ISWM → CPR1 → CPR0
    END
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    A 
    						
    							NDA-24306 CHAPTER 4
    Page 279
    Revision 1.0
    SYSTEM STARTUP
    Procedure for Program Install consists of the following items.
    Perform the procedures below for all the LNs and ISW, individually:
    Note:The control of 7-seg LED is the next page.
    (Case of program install and restart processing)
    NAP-200-019
    Sheet 1/6
    Program Install and Load
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
     Generic Software 2~11
     Internal MAT Software 1~2
     TCP/IP Software 1
    Install
    Application
    Software Install
    HD Initial
    Off-Line Star t Up
    Refer to (a) Procedure for Off-Line Start Up
    Refer to (b) Procedure for HD Initial
     HD format
     Generic Software (1) Install
     Making Directory in the HD
    Refer to (d) Procedure for Application Software Install START
    END
    Refer to (c) Procedure for Basic Software Install 
    						
    							CHAPTER 4 NDA-24306
    Page 280
    Revision 1.0
    SYSTEM STARTUP
    Note:
    Procedures (a) through (e) must be performed in all LNs and ISW, individually.
    NAP-200-019
    Sheet 2/6
    Program Install and Load
    (a)  Procedure for off-line start-up Status change of 7 Segment LED on the EMA card
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    START
    END
    Set the SENSE switch
    (CPU0, CPU1) to “c” on
     Push the CPURST 
      button on the CPU
      Front Panel. 
    or 
     Turn Power-SW ON.
    Star tup 
    end
    corresponding to the 
    system to be initialized 
    (OFF-LINE MODE)  the CPU Front Panel. 
    						
    							NDA-24306 CHAPTER 4
    Page 281
    Revision 1.0
    SYSTEM STARTUP
    Note:
    Procedures (a) through (e) must be performed in all LNs and ISW, individually.
    NAP-200-019
    Sheet 3/6
    Program Install and Load
    (b) Procedure for HD Initial Status change of 7 Segment LED on the CPU Front 
    Panel.
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    START
    END
     HD Format
    Set the SENSE switch 
    corresponding to the 
    system to be initialized 
    (CPU0, CPU1) to “1” on 
    the CPU Front Panel.
    Insert the FD Generic Disk 1 
    into the FDD.
    Flip the MBR key on the 
    CPU Front Panel [OFF → ON → OFF].
    Display end 
    123
    SENS SW 7SEG LED FUNCTION
    ‘1’FORMAT → COPY → MAKING DIRECTORY → 
     →  
    						
    							CHAPTE R 4   NDA-2 4306
    P ag e 282
    R evis io n 1.0
    S Y STEM  S TA RTU P
    Note:  
    Pro ced ures (a)  t h rough  ( e )  mu st b e p erf ormed  in all  LNs and  I S W , i nd iv idua ll y .
    N AP-2 00-0 19
    S hee t 4 /6
    Pro gram  In sta ll  a nd Lo ad
    (c )   P roce dure f or Gene ric  So ftw are (2  ~  11)  Inte rn al 
    M AT  S oftw are  ( 1  ~  2 ),  T C P /  IP  S oftw are  (1) I n sta ll S
    ta tus  cha nge  of 7  Segment  LED  on t h e  CPU  Front  
    P an el.
    W ARNING:  Rem oval  or  Ma ke  Busy  of  th e HFD c ard  is
    not allowed while the Floppy Disk or Hard
    Disk is being accessed.
    ATTENTIONContents
    Static Sensitive
    Handling
    Precautions Required
    START
    END * Repeat
    Insert the FD Generic 
    Disk 2 into the FDD.
    *
    Set the SENSE switch
    to “3” on the CPU Front Panel. corresponding to the 
    system to have DATA 
    Flip the MBR key on the 
    CPU Front Panel card 
    OFF
    →ON→OFF.
      Generic Software 3 ~ 11
       Internal MAT Software 1 ~ 2
       TCP/IP Software 1
    installed (CPU0, CPU1) 
      
    						