Trane Intellipak 2 Service Manual
Have a look at the manual Trane Intellipak 2 Service Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 12 Trane manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.
Installation RT-SVX24K-EN71 Table 16. Sizing natural gas pipe mains and branches Gas Supply Pipe Run (ft) Gas Input (Cubic Feet/Hour)* 1¼ Pipe 1½ Pipe 2 Pipe 2½ Pipe 3 Pipe4 Pipe 10 1050 1600 3050 4800 8500 17500 20 730 1100 2100 3300 5900 12000 30 590 890 1650 2700 4700 9700 40 500 760 1450 2300 4100 8300 50 440 670 1270 2000 3600 7400 60 400 610 1150 1850 3250 6800 70 370 560 1050 1700 3000 6200 80 350 530 990 1600 2800 5800 90 320 490 930 1500 2600 5400 100 305 460 870 1400 2500 5100 125 275 410 780 1250 2200 4500 150 250 380 710 1130 2000 4100 175 225 350 650 1050 1850 3800 200 210 320 610 980 1700 3500 Notes: 1. *Table is based on a specific gravity of 0.60. Use Table 17, p. 71 for the specific gravity of the local gas supply. 2. If more than one unit is served by the same main gas supply, consider the total gas input (cubic feet/hr.) and the total length when determining the appropriate gas pipe size. 3. Obtain the Specific Gravity and BTU/Cu.Ft. from the gas company. 4. The following example demonstrates the considerations necessary when determining the actual pipe size: Example: A 40 pipe run is needed to connect a unit with a 850 MBH furnace to a natural gas supply having a rating of 1,000 BTU/Cu.Ft. and a specific gravity of 0.60 Cu.Ft/Hour = Furnace MBH Input Gas BTU/Cu.Ft. X Multiplier Table 17, p. 71 Cu.Ft/Hour = 850 Table 16, p. 71 indicates that a 2 pipe is required. Table 17. Specific gravity multipliers Specific Gravity Multiplier 0.50 1.10 0.55 1.04 0.60 1.00 0.65 0.96 Table 18. Gas heating capacity altitude correction factors Altitude (Ft.) Sea Level To 2000 2001 to 2500 2501 to 3500 3501 to 4500 4501 to 5500 5501 to 6500 6501 to 7500 Capacity Multiplier 1.00 .92 .88 .84 .80 .76 .72 Note: Correction factors are per AGA Std. 221.30 - 1964, Part VI, 6.12. Local codes may supersede. Figure 46. Two-stage natural gas train for 850, 1100 Mbh heaters
Installation 72RT-SVX24K-EN Flue Assembly Installation 1. Locate the collapsed flue assembly in the compartment above the gas heat controls by removing the panel screws. The assembly is secured by screws up through the roof of the gas controls compartment roof. 2. Separate the pieces of the collapsed assembly. 3. Then assemble the stack as shown in Figure48. 4. Insert the tube on the flue assembly into the hole located in the vertical support for the heat section. 5. Butt both tube sections together and center the pipe clamp over joint. 6. Using the pre-punch hole in the flue assembly, extension, and the vertical support, install the appropriate number of mounting brackets (Refer to the installation instructions that ship with the flue assembly.) Figure 47. Modulating (850-2500 Mbh heaters) and two-stage (1800-2500 Mbh heaters) natural gas train Ignition control board Ignition transformer Safety valveSingle stage regulating valve Combustion blower Combustion blower pressure switch Butterfly gas control valve Actuator Gas heat inlet sizes Standard Gas Heat Input (MBh) Gas Heat Inlet Sizes (in.) 850 1 1100 1 1/4 1800 1 1/2 2500 1 1/2 Figure 48. Flue assembly
Installation RT-SVX24K-EN73 Figure 49. Gas heat piping penetration locations K 17 8 11 5 8 W D 2.5M & 1.8M (W=16 1/8in, D=14 11/16in) 1.1M, 0.8M (W=9 15/16in, D=9 12/16in) H C 2119 20 7 16 B Horizontal gas pipe inlet Pipe type: Black pipe, sch 40 Condensate drain outlet Pipe type: cpvc Hole at the base Ø3 Unit end plane Edge of mist eliminatorTop View Side View
Installation 74RT-SVX24K-EN General Coil Piping and Connection Recommendations Proper installation, piping, and trapping is necessary to ensure satisfactory coil operation and to prevent operational damage: Support all piping independently of the coils. Provide swing joints or flexible fittings on all connections that are adjacent to heating coils to absorb thermal expansion and contraction strains. Install factory supplied control valves (valves ship separately). Note: The contractor is responsible for supplying the installation hardware. When attaching the piping to the coil header, make the connection only tight enough to prevent leaks. Maximum recommended torque is 200 foot-pounds. Use pipe sealer on all thread connections. Table 19. Gas heat piping penetration measurements Tons Energy Recovery Wheel (ERW) Pieces Heat (MBH) Gas Flue Condensate Drain Outlet Gas Connection, Horizontal Gas Connection, Base Horizontal Distance Mist Elim to Flue C/L Unit End to Hole C/L Unit End to Hole C/L KCHB 90-118 No ERW 1 & 2 Pc 1800 160 1/16254 14/16 266 4/16274 11/16 90-118 No ERW 1 & 2 Pc 1100 159 15/16 263 15/16265 5/16274 11/16 90-118 No ERW 1 & 2 Pc 850 159 15/16263 15/16 265 5/16274 11/16 120-162 No ERW 1 & 2 Pc 2500 214 11/16 321 337 7/16 339 7/16 120-162 No ERW 1 & 2 Pc 1800 214 13/16 319 11/16331 339 7/16 120-162 No ERW 1 & 2 Pc 1100 214 11/16 327 14/16330 1/16339 7/16 90-118 ERW 1 & 2 Pc 1800 164 11/16 351 5/16362 10/16 371 1/16 90-118 ERW 1 & 2 Pc 1100 164 8/16360 6/16361 12/16 371 1/16 90-118 ERW 1 & 2 Pc 850 164 8/16360 6/16361 12/16 371 1/16 120-162 ERW 1 & 2 Pc 2500 219 13/16 417 7/16433 14/16 435 14/16 120-162 ERW 1 & 2 Pc 1800 220 416 2/16 427 7/16435 14/16 120-162 ERW 1 & 2 Pc 1100 219 13/16 424 5/16426 8/16435 14/16 90-118 No ERW 3 Pc 1800 179 6/16274 3/16285 8/16293 15/16 90-118 No ERW 3 Pc 1100 179 3/16283 3/16284 9/16293 15/16 90-118 No ERW 3 Pc 850 179 3/16283 3/16284 9/16293 15/16 120-162 No ERW 3 Pc 2500 240 2/16346 8/16362 15/16 364 15/16 120-162 No ERW 3 Pc 1800 240 5/16345 3/16356 8/16364 15/16 120-162 No ERW 3 Pc 1100 240 2/16353 6/16355 9/16364 15/16 90-118 ERW 3 Pc 1800 183 15/16 376 13/16388 2/16390 6/16 90-118 ERW 3 Pc 1100 183 13/16 385 13/16387 3/16390 6/16 90-118 ERW 3 Pc 850 183 13/16385 13/16 387 3/16390 6/16 120-162 ERW 3 Pc 2500 245 5/16442 15/16 459 6/16461 6/16 120-162 ERW 3 Pc 1800 245 8/16441 9/16452 15/16 461 6/16 120-162 ERW 3 Pc 1100 245 5/16449 12/16 452 461 6/16 CAUTION Connection Leaks! Use a backup wrench when attaching piping to coils with copper headers to prevent damage to the coil header. Do not use brass connectors because they distort easily and could cause connection leaks. CAUTION Over Tightening! Do not use teflon-based products for any field connections because their high lubricity could allow connections to be over-tightened, resulting in damage to the coil header.
Installation RT-SVX24K-EN75 After completing the piping connections, seal around pipe from inner panel to outer panel. Hot Water Heat Units Hot water heating coils are factory installed inside the heater section of the unit. Once the unit is set into place, the hot water piping and the factory provided three way modulating valve must be installed. The valve can be installed inside the heat section or near the unit. If the valve is installed in a remote location, use field supplied wiring to extend the control wires from the heater section to the valve.Two access holes are provided in the unit base as illustrated in Figure 50, p. 76. Following the guidelines listed below will enhance both the installation and operation of the “wet heat” system. Figure 51, p. 77 illustrates the recommended piping configuration for the hot water coil. Table 20 on page 76 lists the coil connection sizes. Note: The valve actuators are not waterproof. Failure to protect the valve from moisture may result in the loss of heating control. 1. Support all field-installed piping independently from the heating coil. 2. Use swing joints or flexible connectors adjacent to the heating coil. (These devices will absorb the strains of expansion and contraction). 3. All return lines and fittings must be equal to the diameter of the “outlet” connection on the hot water coil. 4. Install a “Gate” type valve in the supply branch line as close as possible to the hot water main and upstream of any other device or takeoff. 5. Install a “Gate” type valve in the return branch line as close as possible to the return main and down stream of any other device. 6. Install a strainer in the hot water supply branch as shown inFigure 51, p.77. 7. Install the 3-way valve in an upright position, piped for valve seating against the flow. Ensure that the valve location lends itself to serviceability. 8. The Type “W” hot water coil is self-venting only when the tube water velocity exceeds 1.5 feet per second (fps). If the tube velocity is less than 1.5 feet per second, either: a. install an automatic air vent at the top of the return header , using the tapped pipe connection or, b. vent the coil from the top of the return header down to the return piping. At the vent connection, size the return piping to provide sufficient water velocity. 9. Install a “Globe” type valve in the Bypass line as shown inFigure 51 on page 77. Steam Heat Units Steam heating coils are factory installed inside the heater section of the unit. The coils are pitched, within the units, to provide the proper condensate flow from the coil. To maintain the designed degree of pitch for the coil, the unit must be level. Once the unit is set into place, the steam piping and the factory provided two way modulating valve must be installed. The valve can be installed inside the heater section or near the unit. If the valve is installed in a remote location, use field supplied wiring to extend the control wires from the heater section to the valve. Two access holes are provided in the unit base as illustrated in Figure 50, p. 76 . Following the guidelines listed below will enhance both the installation and operation of the “wet heat” system. Figure 52, p. 77 illustrates the recommended piping configurations for the steam coil. Table 20, p. 76lists the coil connection sizes. Note: The valve actuators are not waterproof. Failure to protect the valve from moisture may result in the loss of heating control. 1. Support all field-installed piping independently from the heating coil. 2. Use swing joints or flexible connectors adjacent to the heating coil. (These devices will absorb the strains of expansion and contraction.) 3. Install the 2-way valve in an upright position. Ensure that the valves location lends itself to serviceability. 4. Pitch the supply and return steam piping downward 1 per 10 of run in the direction of flow. 5. All return lines and fittings must be equal to the diameter of the “outlet” connection on the steam coil(s). If the steam trap connection is smaller that the coil “outlet” diameter, reduce the pipe size between the strainer and the steam trap connections only. 6. Install a 1/2 15 degree swing-check vacuum breaker at the top of the return coil header using the tapped pipe connection. Position the vacuum breaker as close to the coil as possible. Note: Vacuum breakers should have extended lines from the vent ports to the atmosphere or connect each vent line to the return pipe on the discharge side of the steam traps. CAUTION Leakage! Properly seal all penetrations in unit casing. Failure to seal penetrations from inner panel to outer panel could result in unconditioned air entering the module, and water infiltrating the insulation, resulting in equipment damage.
Installation 76RT-SVX24K-EN 7. Install a “Gate” type valve in the supply branch line as close as possible to the steam main and upstream of any other device. 8. Install a “Gate” type valve in the return branch line as close as possible to the condensate return main and downstream of any other device. 9. Install a strainer as close as possible to the inlet of the control valve and steam trap(s). 10. Steam trap selection should be based on the maximum possible condensate flow and the recommended load factors. 11. Install a Float-and-Thermostatic (FT) type trap to maintain proper flow.They provide gravity drains and continuous discharge operation. FT type traps are required if the system includes either; a. an atmospheric pressure/gravity condensate return; or , b. a potentially low pressure steam supply. 12. Position the outlet or discharge port of the steam trap at least 12 below the outlet connection on the coil(s). This will provide adequate hydrostatic head pressure to overcome the trap losses and assure complete condensate removal. The two steam coils are stacked together and must be piped in a parallel arrangement.The steps listed below should be used in addition to the previous steps. Figure 52, p. 77 illustrates the recommended piping configuration for the steam coils. 13. Install a strainer in each return line before the steam trap. 14. Trap each steam coil separately as described in steps 1 0 and 11 to prevent condensate backup in one or both coils. 15. In order to prevent condensate backup in the piping header supplying both coil sections, a drain must be installed utilizing a strainer and a steam trap as illustrated in Figure52, p.77. Figure 50. Hot water and steam heat connection location T able 20. Hot water and steam coil connection sizes Hot Water Coil Steam Coil Unit Size Supply Return Drain/ Vent Supply Return Vent 90-162 To n 2 ½ 2 ½ ½ 3.0 1 ¼ 1 ¼ Notes: 1. Type W coils, with center offset headers, are used in Hot Water units; Type NS coils are used in Steam units. 2. Hot water and Steam units have multiple headers. 3. All sizes are in inches. 4. All connection threads are internal. Table 21. Hot water and steam heat connection dimensions Tons ABY Diameter 90-118 276 9/16 290 5/16 18 5 120-162 341 5/16 355 1/16 18 5 A B Y Supply Air Opening Return Air Opening Unit bottom view InletOutletRecommended
Installation RT-SVX24K-EN77 Figure 51. Hot water coil piping Figure 52. Steam coil piping
Installation 78RT-SVX24K-EN Disconnect Switch w/External Handle Units come equipped with a factory mounted disconnect switch with an externally mounted handle.This allows the operator to disconnect power from the unit without having to open the control panel door. The handle locations and its three positions are shown below; “ON” - Indicates that the disconnect switch is closed,allowing the main power supply to be applied at the unit. “OFF” - Indicates that the disconnect switch is open, interrupting the main power supply to the unit controls. “RESET” - Turning the handle to this position resets the circuit breaker (if so equipped). The handle can be locked in the “OFF” position. While holding the handle in the “OFF” position, push the spring loaded thumb key, attached to the handle, into the base slot. Place the lock shackle between the handle and the thumb key. This will prevent it from springing out of position. An overall layout of the field required power wiring is illustrated beginning with Figure 54, p. 79. To ensure that the unit supply power wiring is properly sized and installed, follow these guidelines. Note: All field installed wiring must conform to NEC guidelines as well as State and Local codes. Verify that the power supply available is compatible with the unit nameplate rating for all components. The available power supply must be within 10% of the rated voltage stamped on the nameplate. Use only copper conductors to connect the 3-phase power supply to the unit. Electric Heat Units Electric Heat Units require one power entry as illustrated in Figure 54, p. 79. Use the information provided in Table 24, p. 82 and the “Power Wire Sizing & Protection Device Equations”, to determine the appropriate wire size and Maximum Over current Protection for the heaters/ unit. Note: Each power supply must be protected from short circuit and ground fault conditions.To comply with NEC, protection devices must be sized according to the “Maximum Over current Protection” (MOP) or “Recommended Dual Element” (RDE) fuse size data on the unit nameplate. Provide grounding for the supply power circuit in the electric heat control box. WARNING Hazardous Voltage w/Capacitors! Disconnect all electric power, including remote disconnects and discharge all motor start/run capacitors before servicing. Follow proper lockout/ tagout procedures to ensure the power cannot be inadvertently energized. Verify with an appropriate voltmeter that all capacitors have discharged. Failure to disconnect power and discharge capacitors before servicing could result in death or serious injury. For additional information regarding the safe discharge of capacitors, see PROD-SVB06A-EN Figure 53. Disconnect switch external handle WARNING Live Electrical Components! During installation, testing, servicing and troubleshooting of this product, it may be necessary to work with live electrical components. Have a qualified licensed electrician or other individual who has been properly trained in handling live electrical components perform these tasks. Failure to follow all electrical safety precautions when exposed to live electrical components could result in death or serious injury. CAUTION Use Copper Conductors Only! Unit terminals are not designed to accept other types of conductors. Failure to use copper conductors may result in equipment damage.
Installation RT-SVX24K-EN79 Main Unit Power Wiring Figure 56, p. 80lists the field connection wire ranges for both the main power terminal block and the optional main power disconnect switch. The electrical tables beginning with Table 22, p. 81 list the component electrical data.The electrical service must be protected from over current and short circuit conditions in accordance with NEC requirements. Protection devices must be sized according to the electrical data on the nameplate. Refer to the “Power Wire Sizing and Protection Device Equations”, for determining; the appropriate electrical service wire size based on “Minimum Circuit Ampacity” (MCA), the “Maximum Over current Protection” (MOP) device, the “Recommended Dual Element fuse size” (RDE). 1. Location for the electrical service entrance is illustrated inFigure 54, p. 79. Complete the unit power wiring connections onto either the main terminal block, or the factory mounted non-fused disconnect switch, inside the unit control panel. Refer to the customer connection diagram that shipped with the unit for specific termination points. 2. Provide proper grounding for the unit in accordance with local and national codes Figure 54. Typical field power wiring Field Supplied SurviceOver Current Protection Pitch Pocket Pitch Pocket 3-Wire Power Supply+Ground Front View Control Box 1TB1 or 1S1 Electric Heat Control Panel Gas Heat Control Panel Steam or Hot Water Control Panel Heat Control Box Condenser Section
Installation 80RT-SVX24K-EN Figure 55. Typical field power wiring Figure 56.Customer connection wire range Note:Non-fused disconnect switch size is calculated by selecting the size greater than or equal to 1.15 X (sum of unit loads). See unit literature for unit load values. (See following page for circuit breaker sizing)