Home > Trane > Air Conditioner > Trane Intellipak 2 Service Manual

Trane Intellipak 2 Service Manual

    Download as PDF Print this page Share this page

    Have a look at the manual Trane Intellipak 2 Service Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 12 Trane manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    							Installation
    RT-SVX24K-EN71
    Table 16. Sizing natural gas pipe mains and branches
    Gas Supply
    Pipe Run  (ft) Gas Input (Cubic Feet/Hour)*
    1¼ Pipe 1½
    Pipe  2
    Pipe 2½
    Pipe  3
    Pipe4
    Pipe
    10 1050 1600 3050 4800 8500 17500
    20 730 1100 2100 3300 5900 12000
    30 590 890 1650 2700 4700 9700
    40 500 760 1450 2300 4100 8300
    50 440 670 1270 2000 3600 7400
    60 400 610 1150 1850 3250 6800
    70 370 560 1050 1700 3000 6200
    80 350 530 990 1600 2800 5800
    90 320 490 930 1500 2600 5400
    100 305 460 870 1400 2500 5100
    125 275 410 780 1250 2200 4500
    150 250 380 710 1130 2000 4100
    175 225 350 650 1050 1850 3800
    200 210 320 610 980 1700 3500
    Notes:  1. *Table is based on a specific gravity of 0.60. Use  Table 17, p.  71 for 
    the specific gravity of the local gas supply.
     2. If more than one unit is served by the same main gas supply, 
    consider the total gas input (cubic feet/hr.) and the total length when 
    determining the appropriate gas pipe size.
     3. Obtain the Specific Gravity and BTU/Cu.Ft. from the gas company.
     4. The following example demonstrates the considerations necessary 
    when determining the actual pipe size: 
    Example: A 40 pipe run is needed to connect a unit with a 850 MBH 
    furnace to a natural gas supply having a rating of 1,000 BTU/Cu.Ft. 
    and a specific gravity of 0.60
    Cu.Ft/Hour =
     Furnace MBH Input 
    Gas BTU/Cu.Ft. X Multiplier  Table 17, p.  71
    Cu.Ft/Hour = 850 
    Table  16, p.  71 indicates that a 2 pipe is required.
    Table 17. Specific gravity multipliers
    Specific 
    Gravity Multiplier
    0.50 1.10
    0.55 1.04
    0.60 1.00
    0.65 0.96
    Table 18. Gas heating capacity altitude correction factors
    Altitude (Ft.)
    Sea Level  To 2000 2001 to 
    2500 2501 to 
    3500 3501 to 
    4500 4501 to 
    5500 5501 to 
    6500 6501 to 
    7500
    Capacity 
    Multiplier
    1.00 .92 .88 .84 .80 .76 .72
    Note: Correction factors are per AGA Std. 221.30 - 1964, Part VI, 6.12. Local codes may supersede.
    Figure 46. Two-stage natural gas train for 850, 1100 Mbh heaters 
    						
    							Installation
    72RT-SVX24K-EN
    Flue Assembly Installation
    1. Locate the collapsed flue assembly in the
    compartment above the gas heat controls by removing
    the panel screws. The assembly is secured by screws
    up through the roof of the gas controls compartment
    roof.
    2. Separate the pieces of the collapsed assembly.
    3. Then assemble the stack as shown in Figure48.
    4. Insert the tube on the flue assembly into the hole located
     in the vertical support for the heat section.
    5. Butt both tube sections together and center the pipe clamp
     over joint.
    6. Using the pre-punch hole in the flue assembly, extension,
     and the vertical support, install the
    appropriate number of mounting brackets (Refer to the
    installation instructions that ship with the flue
    assembly.)
    Figure 47. Modulating (850-2500 Mbh heaters) and two-stage (1800-2500 Mbh heaters) natural gas train
    Ignition control board
    Ignition transformer
    Safety valveSingle stage 
    regulating valve 
    Combustion blower Combustion blower
    pressure switch
    Butterfly gas
    control valve
    Actuator
    Gas heat inlet sizes Standard Gas Heat  Input (MBh)  Gas Heat Inlet 
    Sizes (in.)
    850 1 
    1100 1 1/4
    1800 1 1/2
    2500 1 1/2
    Figure 48. Flue assembly 
    						
    							Installation
    RT-SVX24K-EN73
    Figure 49. Gas heat piping penetration locations
    K
    17
    8
    11 5
    8
    W
    D
    2.5M & 1.8M  (W=16 1/8in,  D=14 11/16in)
    1.1M, 0.8M    (W=9 15/16in,  D=9 12/16in)
    H
    C
    2119
    20 7
    16
    B
    Horizontal gas pipe inlet
    Pipe type: Black pipe, sch 40
    Condensate drain outlet
    Pipe type: cpvc
    Hole at the base
    Ø3
    Unit end plane
    Edge of mist eliminatorTop View
    Side View 
    						
    							Installation
    74RT-SVX24K-EN
    General Coil Piping and Connection
    Recommendations
    Proper installation, piping, and trapping is necessary to
    ensure satisfactory coil operation and to prevent
    operational damage:
     Support all piping independently of the coils.
     Provide swing joints or flexible fittings on all
    connections
     that are adjacent to heating coils to
    absorb thermal expansion and contraction strains.
     Install factory supplied control valves (valves ship separately).
    Note: The
     contractor is responsible for supplying the
    installation hardware.  When attaching the piping to the coil header, make the
    connection
     only tight enough to prevent leaks.
    Maximum recommended torque is 200 foot-pounds.
     Use pipe sealer on all thread connections.
    Table 19. Gas heat piping penetration measurements
    Tons
    Energy 
    Recovery  Wheel 
    (ERW) Pieces Heat 
    (MBH) Gas Flue
    Condensate Drain 
    Outlet Gas Connection, 
    Horizontal  Gas Connection, 
    Base
    Horizontal Distance
    Mist Elim 
    to Flue C/L Unit End 
    to Hole C/L Unit End 
    to Hole C/L
    KCHB
    90-118 No ERW 1 & 2 Pc 1800 160  1/16254 14/16 266  4/16274 11/16
    90-118 No ERW 1 & 2 Pc 1100 159 15/16 263 15/16265  5/16274 11/16
    90-118 No ERW 1 & 2 Pc 850 159 15/16263 15/16 265  5/16274 11/16
    120-162 No ERW 1 & 2 Pc 2500 214 11/16 321      337  7/16 339  7/16
    120-162 No ERW 1 & 2 Pc 1800 214 13/16 319 11/16331      339  7/16
    120-162 No ERW 1 & 2 Pc 1100 214 11/16 327 14/16330  1/16339  7/16
    90-118 ERW 1 & 2 Pc 1800 164 11/16 351  5/16362 10/16 371  1/16
    90-118 ERW 1 & 2 Pc 1100 164  8/16360  6/16361 12/16 371  1/16
    90-118 ERW 1 & 2 Pc 850 164  8/16360  6/16361 12/16 371  1/16
    120-162 ERW 1 & 2 Pc 2500 219 13/16 417  7/16433 14/16 435 14/16
    120-162 ERW 1 & 2 Pc 1800 220      416  2/16 427  7/16435 14/16
    120-162 ERW 1 & 2 Pc 1100 219 13/16 424  5/16426  8/16435 14/16
    90-118 No ERW 3 Pc 1800 179  6/16274  3/16285  8/16293 15/16
    90-118 No ERW 3 Pc 1100 179  3/16283  3/16284  9/16293 15/16
    90-118 No ERW 3 Pc 850 179  3/16283  3/16284  9/16293 15/16
    120-162 No ERW 3 Pc 2500 240  2/16346  8/16362 15/16 364 15/16
    120-162 No ERW 3 Pc 1800 240  5/16345  3/16356  8/16364 15/16
    120-162 No ERW 3 Pc 1100 240  2/16353  6/16355  9/16364 15/16
    90-118 ERW 3 Pc 1800 183 15/16 376 13/16388  2/16390  6/16
    90-118 ERW 3 Pc 1100 183 13/16 385 13/16387  3/16390  6/16
    90-118 ERW 3 Pc 850 183 13/16385 13/16 387  3/16390  6/16
    120-162 ERW 3 Pc 2500 245  5/16442 15/16 459  6/16461  6/16
    120-162 ERW 3 Pc 1800 245  8/16441  9/16452 15/16 461  6/16
    120-162 ERW 3 Pc 1100 245  5/16449 12/16 452      461  6/16
    CAUTION
    Connection Leaks!
    Use a backup wrench when attaching piping to coils
    with copper headers to prevent damage to the coil
    header. Do not use brass connectors because they
    distort easily and could cause connection leaks.
    CAUTION
    Over Tightening!
    Do not use teflon-based products for any field
    connections because their high lubricity could allow
    connections to be over-tightened, resulting in damage
    to the coil header. 
    						
    							Installation
    RT-SVX24K-EN75
     After completing the piping connections, seal around
    pipe from inner panel to outer panel.
    Hot Water Heat Units
    Hot water heating coils are factory installed inside the
    heater section of the unit. Once the unit is set into place,
    the hot water piping and the factory provided three way
    modulating valve must be installed. The valve can be
    installed inside the heat section or near the unit. If the
    valve is installed in a remote location, use field supplied
    wiring to extend the control wires from the heater section
    to the valve.Two access holes are provided in the unit base
    as illustrated in Figure 50, p. 76.
    Following the guidelines listed below will enhance both
    the installation and operation of the “wet heat” system.
    Figure 51, p. 77 illustrates the recommended piping
    configuration for the hot water coil. Table 20 on page 76
    lists the coil connection sizes.
    Note: The valve actuators are not waterproof. Failure to
    protect the valve from moisture may result in the
    loss of heating control.
    1. Support all field-installed piping independently from the heating coil.
    2. Use swing joints or flexible connectors adjacent to the heating
     coil. (These devices will absorb the strains of
    expansion and contraction).
    3. All return lines and fittings must be equal to the diameter
     of the “outlet” connection on the hot water
    coil.
    4. Install a “Gate” type valve in the supply branch line as close
     as possible to the hot water main and upstream
    of any other device or takeoff.
    5. Install a “Gate” type valve in the return branch line as close
     as possible to the return main and down stream
    of any other device.
    6. Install a strainer in the hot water supply branch as shown
     inFigure 51, p.77.
    7. Install the 3-way valve in an upright position, piped for valve
     seating against the flow. Ensure that the valve
    location lends itself to serviceability.
    8. The Type “W” hot water coil is self-venting only when the
     tube water velocity exceeds 1.5 feet per second
    (fps). If the tube velocity is less than 1.5 feet per second,
    either: a. install an automatic air vent at the top of the return
    header
     , using the tapped pipe connection
    or,
    b. vent the coil from the top of the return header down to the return piping. At the vent connection, size the
    return piping to provide sufficient water velocity.
    9. Install a “Globe” type valve in the Bypass line as shown inFigure 51 on page 77.
    Steam Heat Units
    Steam heating coils are factory installed inside the heater
    section of the unit. The coils are pitched, within the units,
    to provide the proper condensate flow from the coil. To
    maintain the designed degree of pitch for the coil, the unit
    must be level.
    Once the unit is set into place, the steam piping and the
    factory provided two way modulating valve must be
    installed. The valve can be installed inside the heater
    section or near the unit. If the valve is installed in a remote
    location, use field supplied wiring to extend the control
    wires from the heater section to the valve. Two access
    holes are provided in the unit base as illustrated in
    Figure 50, p. 76 .
    Following the guidelines listed below will enhance both
    the installation and operation of the “wet heat” system.
    Figure 52, p. 77 illustrates the recommended piping
    configurations for the steam coil. Table 20, p. 76lists the
    coil connection sizes.
    Note: The valve actuators are not waterproof. Failure to
    protect the valve from moisture may result in the
    loss of heating control.
    1. Support all field-installed piping independently from the heating coil.
    2. Use swing joints or flexible connectors adjacent to the heating
     coil. (These devices will absorb the strains of
    expansion and contraction.)
    3. Install the 2-way valve in an upright position. Ensure that
     the valves location lends itself to serviceability.
    4. Pitch the supply and return steam piping downward 1 per
     10 of run in the direction of flow.
    5. All return lines and fittings must be equal to the diameter
     of the “outlet” connection on the steam
    coil(s). If the steam trap connection is smaller that the
    coil “outlet” diameter, reduce the pipe size between
    the strainer and the steam trap connections only.
    6. Install a 1/2 15 degree swing-check vacuum breaker at the
     top of the return coil header using the tapped pipe
    connection. Position the vacuum breaker as close to
    the coil as possible.
    Note: Vacuum breakers should have extended lines from
    the vent ports to the atmosphere or connect each
    vent line to the return pipe on the discharge side of
    the steam traps.
    CAUTION
    Leakage!
    Properly seal all penetrations in unit casing. Failure to
    seal penetrations from inner panel to outer panel could
    result in unconditioned air entering the module, and
    water infiltrating the insulation, resulting in equipment
    damage. 
    						
    							Installation
    76RT-SVX24K-EN
    7. Install a “Gate” type valve in the supply branch line as
    close as possible to the steam main and upstream of
    any other device.
    8. Install a “Gate” type valve in the return branch line as close
     as possible to the condensate return main and
    downstream of any other device.
    9. Install a strainer as close as possible to the inlet of the control
     valve and steam trap(s).
    10. Steam trap selection should be based on the maximum
     possible condensate flow and the
    recommended load factors.
    11. Install a Float-and-Thermostatic (FT) type trap to maintain
     proper flow.They provide gravity drains and
    continuous discharge operation. FT type traps are
    required if the system includes either;
    a. an atmospheric pressure/gravity condensate return;
    or
    
    ,
    b. a potentially low pressure steam supply.
    12. Position the outlet or discharge port of the steam trap at
     least 12 below the outlet connection on the coil(s).
    This will provide adequate hydrostatic head pressure to overcome the trap losses and assure complete
    condensate removal.
    The two steam coils are stacked together and must be piped
     in a parallel arrangement.The steps listed below
    should be used in addition to the previous steps.
    Figure 52, p. 77 illustrates the recommended piping
    configuration for the steam coils.
    13. Install a strainer in each return line before the steam trap.
    14. Trap each steam coil separately as described in steps 1
     0 and 11 to prevent condensate backup in one or both
    coils.
    15. In order to prevent condensate backup in the piping header
     supplying both coil sections, a drain must be
    installed utilizing a strainer and a steam trap as
    illustrated in Figure52, p.77. Figure 50. Hot water and steam heat connection location
    T
     able 20. Hot water and steam coil connection sizes
    Hot Water Coil Steam Coil
    Unit  Size Supply Return Drain/
    Vent Supply Return Vent
    90-162  To n 2 ½ 2 ½ ½ 3.0 1 ¼ 1 ¼
    Notes:
     1. Type W coils, with center offset headers, are used in Hot Water units; 
    Type NS coils are used in Steam units.
     2. Hot water and Steam units have multiple headers.
     3. All sizes are in inches.
     4. All connection threads are internal.
    Table 21. Hot water and steam heat connection
    dimensions
    Tons ABY Diameter
    90-118 276  9/16 290  5/16 18       5      
    120-162 341  5/16 355  1/16 18       5      
    A
    B
    Y
    Supply Air Opening Return Air Opening
    Unit bottom view
    InletOutletRecommended 
    						
    							Installation
    RT-SVX24K-EN77
    Figure 51. Hot water coil piping
    Figure 52. Steam coil piping 
    						
    							Installation
    78RT-SVX24K-EN
    Disconnect Switch w/External Handle
    Units come equipped with a factory mounted disconnect
    switch with an externally mounted handle.This allows the
    operator to disconnect power from the unit without having
    to open the control panel door. The handle locations and
    its three positions are shown below;
    “ON” - Indicates that the disconnect switch is closed,allowing the main power supply to be applied at the
    unit.
    “OFF” - Indicates that the disconnect switch is open, interrupting the main power supply to the unit
    controls.
    “RESET” - Turning the handle to this position resets the circuit breaker (if so equipped).
    The handle can be locked in the “OFF” position. While holding the handle in the “OFF” position, push the spring
    loaded thumb key, attached to the handle, into the base
    slot. Place the lock shackle between the handle and the
    thumb key. This will prevent it from springing out of
    position.
    An overall layout of the field required power wiring is illustrated beginning with Figure 54, p. 79. To ensure that
    the unit supply power wiring is properly sized and
    installed, follow these guidelines. Note:
    All field installed wiring must conform to NEC
    guidelines as well as State and Local codes.
    Verify that the power supply available is compatible with the unit nameplate rating for all components. The
    available power supply must be within 10% of the rated
    voltage stamped on the nameplate. Use only copper
    conductors to connect the
    3-phase power supply to the unit.
    Electric Heat Units
    Electric Heat Units require one power entry as illustrated
    in Figure 54, p. 79. Use the information provided in
    Table 24, p. 82 and the “Power Wire Sizing & Protection
    Device Equations”, to determine the appropriate wire size
    and Maximum Over current Protection for the heaters/
    unit.
    Note: Each power supply must be protected from short
    circuit and ground fault conditions.To comply with
    NEC, protection devices must be sized according to
    the “Maximum Over current Protection” (MOP) or
    “Recommended Dual Element” (RDE) fuse size data on the unit nameplate.
    Provide grounding for the supply power circuit in the
    electric heat control box.
    WARNING
    Hazardous Voltage w/Capacitors!
    Disconnect all electric power, including remote
    disconnects and discharge all motor start/run
    capacitors before servicing. Follow proper lockout/
    tagout procedures to ensure the power cannot be
    inadvertently energized. Verify with an appropriate
    voltmeter that all capacitors have discharged. Failure to
    disconnect power and discharge capacitors before
    servicing could result in death or serious injury.
    For additional information regarding the safe discharge
    of capacitors, see PROD-SVB06A-EN
    Figure 53. Disconnect switch external handle
    WARNING
    Live Electrical Components!
    During installation, testing, servicing and
    troubleshooting of this product, it may be necessary to
    work with live electrical components. Have a qualified
    licensed electrician or other individual who has been
    properly trained in handling live electrical components
    perform these tasks. Failure to follow all electrical
    safety precautions when exposed to live electrical
    components could result in death or serious injury.
    CAUTION
    Use Copper Conductors Only!
    Unit terminals are not designed to accept other types
    of conductors. Failure to use copper conductors may
    result in equipment damage. 
    						
    							Installation
    RT-SVX24K-EN79
    Main Unit Power Wiring
    Figure 56, p. 80lists the field connection wire ranges for
    both the main power terminal block and the optional main
    power disconnect switch. The electrical tables beginning
    with Table 22, p. 81 list the component electrical data.The
    electrical service must be protected from over current and
    short circuit conditions in accordance with NEC
    requirements. Protection devices must be sized according
    to the electrical data on the nameplate. Refer to the “Power
    Wire Sizing and Protection Device Equations”, for determining;
    the appropriate electrical service wire size based on
    “Minimum Circuit Ampacity” (MCA), 
    the “Maximum Over current Protection” (MOP)
    device,
     the “Recommended Dual Element fuse size” (RDE).
    1. Location for the electrical service entrance is illustrated inFigure 54, p. 79. Complete the unit power wiring
    connections onto either the main terminal block, or the
    factory mounted non-fused disconnect switch, inside
    the unit control panel. Refer to the customer
    connection diagram that shipped with the unit for
    specific termination points.
    2. Provide proper grounding for the unit in accordance with local and national codes
    Figure 54. Typical field power wiring
    Field Supplied SurviceOver Current Protection
    Pitch Pocket
    Pitch Pocket
    3-Wire Power 
    Supply+Ground
    Front View Control Box
    1TB1 or
    1S1
    Electric Heat Control Panel Gas Heat Control Panel
    Steam or Hot Water Control Panel
    Heat Control Box Condenser
    Section 
    						
    							Installation
    80RT-SVX24K-EN
    Figure 55. Typical field power wiring
    Figure 56.Customer connection wire range
    Note:Non-fused disconnect switch size is
    calculated by selecting the size
    greater than or equal to 1.15 X (sum of
    unit loads). See unit literature for unit
    load values. (See following page for
    circuit breaker sizing) 
    						
    All Trane manuals Comments (0)

    Related Manuals for Trane Intellipak 2 Service Manual