Page 51
Installation RT-SVX24K-EN51 Unit Rigging and Placement 1. To configure the unit Center-of-Gravity, utilize TOPSS or contact the local Trane sales office. 2. Attach adequate strength lifting slings to all lifting lugs.The figures beginning with Figure20, p.51show the minimum distance between the lifting hook and the top of the unit and illustrate the installation of spreader bars to protect the unit and to facilitate a uniform lift. Table 12, p. 44lists typical approximate minimal unit operating weights....
Page 52
Installation 52RT-SVX24K-EN Figure 21. Typical unit rigging—one piece unit with four lifting lugs per side(a) 15 ft min 20 ft min Turnbuckle or Chain Adjustment for each lug Figure 22. Typical unit rigging—two-piece unit with two lifting lugs per side(a) Turnbuckle or Chain Adjustment for each lug
Page 53
Installation RT-SVX24K-EN53 Figure 23. Typical unit rigging—two-piece unit with three lifting lugs per air handler side(a) (a) Turnbuckle or Chain Adjustment required for each lifting point 24 ft min Turnbuckle or Chain Adjustment for each lug
Page 54
Installation 54RT-SVX24K-EN Figure 24. Typical unit rigging—three-piece unit Air-Cooled and Evaporative Condensers— Three-Piece Unit Fit Up 1. Rig and lift outside air section and evaporator section separately. 2. Do not assemble unit on ground and attempt to lift toroof. Unit must be assembled on roof curb. 3. Attach rail guide provided to bottom of the evaporator base rails as shown with screws. 4. Rig and set the evaporator section onto the roof curb (aligned with supply end). 5. Remove and discard...
Page 55
Installation RT-SVX24K-EN55 15. Apply gasket to side panels removed earlier. Attach side panel to unit split. 16. Apply 1.25 butyl tape on top of unit split along the roof seam. 17. Attach roof cap over roof seam and butyl tape with screws Figure 25. Rail guide locations Attach rail guides as shown Figure 26. Evaporator section shipping protection removal Discard shipping protection Figure 27. Evaporator section side panel and roof cap removal Save side panels and roof cap for reassembly Discard s...
Page 56
Installation 56RT-SVX24K-EN Figure 28. Evaporator section gasket locations Rail guides Gasket Butyl Tape Figure 29. Outside air section shipping protection removal Discard shipping protection
Page 57
Installation RT-SVX24K-EN57 Figure 30. Base rail connection Threaded rod Lifting lug Backing Plate Figure 31. Roof rail connection Brackets
Page 58
Installation 58RT-SVX24K-EN Air-Cooled and Evaporative Condensers— Two-Piece Unit Fit Up 1. Rig the low side unit (Air handler) and the high side unit (Condenser) separately. 2. First, rig and set the low side unit on the roof curb (aligned with return end). 3. Take off and discard the protection boxes. (Do not remo ve wire shields). 4. Remove the rail connector splice brackets and install the brackets on the low side unit base rails. 5. Take off the side panels (these are labeled) and the top co ver...
Page 59
Installation RT-SVX24K-EN59 Figure 35. (3) Side and top filler panel removal/(4) high side installation preparation Filler panel shipping position Top cover shipping position Filler panel shipping position Note: Remove the filler panels and top cover before putting the Indoor and Outdoor sections together and screw to both Indoor and Outdoor panels on each side as shown in fig (6). Finally the top cover is assembled in space. (3) Unconnected tubes (4)
Page 60
Installation 60RT-SVX24K-EN Figure 36. (5) Connected tubes/(6) install panels Connected tubes (5) (6)