Page 101
Unit Startup RT-SVX24K-EN101 Set Drain Duration Timer Enter service test mode from unit Human Interface. Navigate to the compressor condenser fan submenu. Under head pressure control, use manual control. Close drain valve and energize water inlet solenoid valve until water reaches nominal level. Once level is achieved, de-energize fill solenoid. Open drain valve and time how long it takes for the water level to drop one inch, make sure to take into account the closing time of the valve. Chemical Water...
Page 102
Unit Startup 10 2RT-SVX24K-EN 2. The second setpoint will be the emergency point – The second setpoint will open the normally closedK2 relay which will interrupt the sump proving circuit which will generate a manual lockout. This second setpoint will be used to protect the unit from extremely high conductivity that would indicate a failure in the system. 3. Inside the enclosure for the controller, there will be a thermostat and strip heater that will protect LCD from cracking at low ambient conditions....
Page 103
Unit Startup RT-SVX24K-EN10 3 protection circuit before closing “Stage 1. After the first functional stage has started, the compressor module monitors the saturated refrigerant temperature and closes the condenser fan output contact, when the saturated refrigerant temperature rises above the “lower limit” setpoint. Units with an Economizer Upon entering an “occupied” mode of operation, the RTM receives input from the remote panel to start the supply fan. For constant volume applications, the RTM supply...
Page 104
Unit Startup 10 4RT-SVX24K-EN control devices as well as a split condenser coil with one section in the indoor air stream and the other in the outdoor coil compartment. During active dehumidification the discharge air will be controlled to the Supply Air Reheat Setpoint by modulating the amount of reheat produced by the reheat coil. The Supply Air Reheat Setpoint, Occupied and Unoccupied Dehumidification Setpoints are adjustable via the human interface, BAS/Network control, or GBAS. Active...
Page 105
Unit Startup RT-SVX24K-EN10 5 non-adjustable limit of 35° F for 10 continuous minutes. Once capacity is reduced, it will remain reduced until the current cycle of dehumidification is terminated or a purge cycle occurs. If the Entering EvaporatorTemp remains below 35° F for an additional 10 minutes both circuits will be de-activated and remain off until the Entering EvaporatorTemp rises above 45°F. Even though all compressors have been de-activated the unit will remain in dehumidification mode and re-...
Page 106
Unit Startup 10 6RT-SVX24K-EN Figure 66. Energy recovery wheel exhaust air setpoint temperatures Figure 67. Energy recovery wheel operation Outside Air Intake Damper (Mist Eliminator not shown) Exhaust Air, Leaving Energy Recovery Wheel, Path to Exhaust Fan Building Return Air Outside Air Bypass Damper Unit Return Airflow Exhaust Air Bypass Damper Energy Recovery Wheel Conditioned Outside Air Return Air Damper Path to Filters & Coil ERW Unit Entering Air (Mixed Return Air & Conditioned...
Page 107
Unit Startup RT-SVX24K-EN10 7 Gas Heating Sequence of Operation Standard Two Stage Gas Furnace The control system for the rooftop units are wired to ensure that the heating and cooling do not occur simultaneously. Refer to the wiring diagram that shipped with the unit while reviewing the following sequence of operation. Honeywell Ignition System (850 & 1100 MBH Two Stage Natural Gas) When a heating requirement exists, the Rooftop Module(RTM) starts the supply fan and sends a request for heat to the Heat...
Page 108
Unit Startup 10 8RT-SVX24K-EN (1800 & 2500 MBH Two Stage Natural Gas) When a heating requirement exists, the Rooftop Module (RTM) starts the supply fan and sends a request for heat to the Heat Module. The Heat Module closes contacts and starts the combustion blower motor through the combustion blower relay. The supply airflow switch and the combustion air switch closes. Power is applied through the high limit cutout to the Honeywell ignition control board. The ignition control board begins the pre-purge...
Page 109
Unit Startup RT-SVX24K-EN10 9 sequence of operation. As you review the sequence of operations, remember these points: 1. The high limit switch will trip if exposed to a temperature greater than the trip point, and will reset automatically once the temperature falls below the reset point. 2. The linear high limit switch is encased in a capillarythat extends across the unit supply air opening. The limit will trip if any 6” span of the capillary exceeds the trip point. Refer to Table42, p. 135. 3. Electric...
Page 110
Unit Startup 11 0RT-SVX24K-EN Temperature Differential Setpoint minus 5°F but not the Evaporator Temperature Differential Setpoint, an information only, auto-reset, High Superheat diagnostic is initiated. If the calculated superheat exceeds the Evaporator Temperature Differential Setpoint, a manual reset, low refrigerant charge diagnostic is initiated and all compressors on the circuit are locked out. Wet Heat Sequence of Operation Electrical circuitry for units with steam or hot water heat is limited to...