DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-99 Add a Switch Node Carrier (Standard Reliability) 
6
Prepare New Switch Node Carrier D
1. Visually insp ec t the new J58890SA Switc h Node Carrier for any d amag e. 
Verify that the bac kp lane p ins are not b ent.
NOTE:
The enhanc ed  R8r PPN AC c arrier may look d ifferent than the other 
c arriers bec ause it c omes with 16 new g round ing...

Page 362

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-100 Add a Switch Node Carrier (Standard Reliability) 
6
Install New Switch Node Carrier 
1.Install the switc h nod e c arrier into p osition “ D”  b y lining  up  the p lastic  
alig nment tip s on the top  rear of the c arrier with the sc rew holes in the 
c ab inet. These alig nment tip s sup p ort the c arrier while the sc rews are 
b eing  rep...

Page 363

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-101 Add a Switch Node Carrier (Standard Reliability) 
6
Figure 6-35. Locations of Top and Bottom Ground Straps on Standard and 
Enhanced Carriers
8.If the switc h nod e c arrier was installed in the “ D”  position of the PPN, 
install the TDM/LAN c able (b etween the “ A”  and  “ D”  c arriers) to the 
pin-field block labeled “TDM/LAN” on the right...

Page 364

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-102 Add a Switch Node Carrier (Standard Reliability) 
6
9.If a switc h node c arrier was installed  in the “ D”  p osition, verify that the 
ZAHF4 TDM/LAN b us terminator is installed  at slot 02 of the switc h nod e 
carrier “D”. See Figure 6-36
.
If a switc h nod e c arrier is b eing  installed  in the “ E”  p osition, verify that the 
ZAHF4...

Page 365

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-103 Add a Switch Node Carrier (Standard Reliability) 
6
Figure 6-36. TDM/LAN Connections for Standard Reliability R8r EPN Figure Notes
1.Port Carrier (“ C” Position)
2. Port Carrier (“ B”  Position)
3. Proc essor Carrier (“ A”  Position)4.  Switc h Nod e Carrier (“ D”  Position)
5. TDM/LAN Bus Terminator (ZAHF4)
6. TDM/LAN Cab le (WP91716 L7) 

Page 366

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-104 Add a Switch Node Carrier (Standard Reliability) 
6
Install Circuit Packs
1.Install the new c irc uit p ac ks into c arrier “ D.”  Use the d ec al and  the 
up g rad e c onfig uration doc ument (p rovid ed  with the eq uip ment) as a 
guide.
2. Install c irc uit p ac k b lanks in slots not eq uip p ed  with c irc uit p ac ks.
Interconnect Port...

Page 367

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-105 Add a Switch Node Carrier (Standard Reliability) 
6
4. Behind  p ort c arrier B of eac h EPN c ab inet:
a. Install a lig htwave transc eiver on c ab le c onnec tor at slot 1B02.
b . Connec t the other end  of the fiber op tic  c able to the lig htwave 
transc eiver, just installed .
c . Carefully attac h the fib er op tic  c ab le (with c ab le...

Page 368

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-106 Add a Switch Node Carrier (Standard Reliability) 
6
Reseat DEFINITY LAN Gateway System
1. Reseat the LAN Gateway assemb ly into its b ac kp lane c onnec tors.
Reseat DEFINITY AUDIX System
1. Reseat the AUDIX assemb ly to its b ac kp lane c onnec tors.
Power Up System
1. At the c ab inet c ontaining  the new switc h nod e c arrier, set the main c...

Page 369

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-107 Add a Switch Node Carrier (Standard Reliability) 
6
Resolve Alarms and Enable Alarm Origination
1. Examine the alarm log . Resolve any alarms using  DEFINITY Enterp rise 
Communic ations Server Release 8 Maintenanc e for R8r
.
2. If the Alarm Origination Activated f
ield  ad ministration that you 
p reviously noted  is alread y set to y
, be sure...

Page 370

DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r  555-233-115  Issue 1
April 2000
Adding or Removing Cabinet Hardware 
6-108 Add a Switch Node Carrier (High or Critical Reliability) 
6
Add a Switch Node Carrier (High or 
Critical Reliability)
To upg rad e to a hig h or c ritic al reliability R8r, a sec ond  switc h nod e c arrier is 
ad d ed  either to an emp ty “ E”  c arrier p osition of an existing  multic arrier p ort 
network or to the “ D”  c arrier p osition (as...
Start reading Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual

Related Manuals for Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Upgrades And Additions Manual

All Lucent Technologies manuals