CHAPTER 3 ND-45492 (E) Pag e 4 4 Revision 2.0 (14) When the system is a multiple-rack configuration, connect the PN-BS00 in rack 1 to the PN-BS00 in rack using BUS cable, as shown in Figure 003-19 and Figure 003-20. Figure 003-19 BUS Cable NAP 200-003 Sheet 22/37 Installation of Main Equipment 1 meter (39 inches) 48-TW-1 CONN CA
Page 62
ND-45492 (E) CHAPTER 3 Page 45 Revision 2.0 Figure 003-20 Connection of the BUS Cables NAP 200-003 Sheet 23/37 Installation of Main Equipment PIM7 PIM6 PIM5 PIM4 PIM3 PIM2 PIM1 PIM0BS01 CN2 CN1 CN2 CN1 CN2 CN1 CN2 CN1BS01 CN2 CN1 CN2 CN1 CN2 CN1 CN2 CN1 48-TW-1 CONN CA BS01 BS01 BS00BS01 BS01 BS01 48-TW-.07 CONN CARack 1 Rack 2
Page 63
CHAPTER 3 ND-45492 (E) Pag e 4 6 Revision 2.0 2. Wall Mounting Installation (1) Using four appropriate fasteners (locally provided; see Table 003-1) for the type of wall construction, se- cure the RACK PARTS as shown in Figure 003-21. For the wall mounting points, refer to Figure 002-2 in NAP-200-002. Note:For the wall-mounting installation, a concrete wall is recommended because the concrete wall is more firm to mount the PBX than a wooden wall or a plaster board. The plaster board is the most infirm...
Page 64
ND-45492 (E) CHAPTER 3 Page 47 Revision 2.0 Figure 003-21 Screwing the RACK PARTS to a Wall NAP 200-003 Sheet 25/37 Installation of Main Equipment 350 mm (13.8 inch) 350 mm (13.8 inch) 250 mm (9.8 inch) ANCHOR (x4/PIM) (SEE FIGURE 002-2) (WALL)382 mm (15.0 inch) M4 MACHINE SCREW-B (x4/PIM) SECURED TO RACK PARTS (PROVIDED WITH RACK PARTS) SCREW-A (x4/PIM) SECURING RACK PARTS TO WALL (LOCALLY PROVIDED) (SEE TABLE 003-1) M5 MACHINE SCREW-C (x4/PIM) (PROVIDED WITH RACK PARTS) (SEE FIGURE 003-20)...
Page 65
CHAPTER 3 ND-45492 (E) Pag e 4 8 Revision 2.0 (2) When mounting the RACK PARTS to a wall, connect all the RACK PARTS to each other, and connect the BASE to the bottom RACK PARTS using the M5 Machine screws (provided), as shown in Figure 003-21. Figure 003-22 Connecting the RACK PARTS and the BASE NAP 200-003 Sheet 26/37 Installation of Main Equipment (JOINT) RACK PARTS M5 MACHINE SCREW-C (x2/JOINT AREA) (PROVIDED WITH RACK PARTS) (JOINT) BASE
Page 66
ND-45492 (E) CHAPTER 3 Page 49 Revision 2.0 (3) Attach four M4 machine screws (provided) to the RACK PARTS as shown in Figure 003-21. For proper mounting of each PIM, approximately 4 mm (0.2 inch) spacing should be provided between the inner face of the M4 machine screw and the RACK PARTS front channel. See Figure 003-23. (4) Align and insert the key hole slots of the rear cover of each PIM to the machine screws secured in step (3). See Figure 003-23. Figure 003-23 Mounting the PIM to the RACK PARTS...
Page 67
CHAPTER 3 ND-45492 (E) Pag e 5 0 Revision 2.0 (5) After hanging each PIM onto the RACK PARTS, tighten each M4 machine screw using a Phillips screw driver as shown in Figure 003-24. Figure 003-24 Screwing the PIM to the RACK PARTS NAP 200-003 Sheet 28/37 Installation of Main Equipment M4 MACHINE SCREW-B (X4) PIMRACK PARTS
Page 68
ND-45492 (E) CHAPTER 3 Page 51 Revision 2.0 (6) Connect the bottom PIM and the BASE, and connect PIMs to each other using 3 bolts (provided), as shown in Figure 003-6 and Figure 003-7. Then, position the TOP COVER on the top PIM and connect them to- gether with 4 screws (provided), as shown in Figure 003-8. (7) Connect the AC CORD-B to the terminals inside the BASE in the same manner as for the Floor Standing Installation (Refer to Figure 003-11 through Figure 003-13). (8) When the system is a...
Page 69
CHAPTER 3 ND-45492 (E) Pag e 5 2 Revision 2.0 3. 19-Inch Rack-Mounting Installation 3.1. Single-PIM Installation (1) Before mounting the PIM, connect the TOP COVER, BOTTOM COVER and AC CORD-A to the PIM as shown in Figure 003-25. The AC CORD-A is pre-installed with the BOTTOM COVER. Figure 003-25 Connecting the Covers and AC CORD-A to the PIM NAP 200-003 Sheet 30/37 Installation of Main Equipment TOP COVER TO PZ-PW86 PIM AC CORD-A BOTTOM COVER LOCAL CABLE DUCT PWR CA-A/BUS CABLE DUCT
Page 70
ND-45492 (E) CHAPTER 3 Page 53 Revision 2.0 (2) Secure the 19” BRACKET to the 19-inch Rack as shown in Figure 003-26. (3) Mount the PIM on the 19” BRACKET as shown in Figure 003-26. Then, secure the PIM to the 19” BRACKET as shown in Figure 003-26. Figure 003-26 Mounting the PIM to the 19-Inch Rack (1 of 2) NAP 200-003 Sheet 31/37 Installation of Main Equipment A B C A BPIM 19” BRACKET C FRONT19” BRACKET19-INCH RACK PIM BOTTOM COVER