Page 71
CHAPTER 3 ND-45492 (E) Pag e 5 4 Revision 2.0 3.2. Multiple-PIM Installation (1) Secure the 19” BRACKET to the 19-inch Rack as shown in Figure 003-26. (2) Mount a PIM on the 19” BRACKET as shown in Figure 003-26. Then, secure the PIM to the 19” BRACKET as shown in Figure 003-26. (3) Repeat step (1) and (2) according to the number of modules. A maximum of 5 modules (4 PIMs and 1 MD- FM) can be mounted in the 19-inch Rack. Figure 003-26 Mounting the PIM to the 19-Inch Rack (2 of 2) NAP 200-003 Sheet...
Page 72
ND-45492 (E) CHAPTER 3 Page 55 Revision 2.0 (4) Position the TOP COVER on the top PIM, and connect them with 4 screws (provided) as shown in Figure 003-27. Figure 003-27 Mounting of the TOP COVER NAP 200-003 Sheet 33/37 Installation of Main Equipment FRONT TOP COVER 19 BRACKET PIM
Page 73
CHAPTER 3 ND-45492 (E) Pag e 5 6 Revision 2.0 (5) Connect the BASE to the bottom PIM as shown in Figure 003-28. Figure 003-28 Connecting the BASE to the PIM NAP 200-003 Sheet 34/37 Installation of Main Equipment Note:The MDFM can be connected to the BASE in the same manner as the PIM. FRONT BASE BASE PIM 19 BRACKET 19 BRACKET PIM
Page 74
ND-45492 (E) CHAPTER 3 Page 57 Revision 2.0 (6) Do the following cable connectons in the same manner as for Floor Standing Installation. (a) Connect the AC CORD-B cables to the terminals inside the BASE (Refer to Figure 003-11 through Figure 003-13). (b) Connect the PZ-PW86 cards to each other using PWR CA-A cables (Refer to Figure 003-14 through Figure 003-15). (c) Mount the PN-BS00 card in the BUS slot of PIM0, and mount the PN-BS01 card in each BUS slot of PIM1 through PIM3 (Refer to Figure 003-16)....
Page 75
CHAPTER 3 ND-45492 (E) Pag e 5 8 Revision 2.0 4. Desk Top Installation (1) Connect the TOP COVER, BOTTOM COVER and AC CORD-A to the PIM as shown in Figure 003-29. The AC CORD-A is pre-installed with the BOTTOM COVER. Figure 003-29 Connecting the Covers and AC CORD-A to the PIM NAP 200-003 Sheet 36/37 Installation of Main Equipment TOP COVER TO PZ-PW86 PIM AC CORD-A BOTTOM COVER LOCAL CABLE DUCT PWR CA-A/BUS CABLE DUCT
Page 76
ND-45492 (E) CHAPTER 3 Page 59 Revision 2.0 (2) Connect the RUBBER FEET to the PIM as shown in Figure 003-30. Figure 003-30 Connecting the RUBBER FOOT to the PIM NAP 200-003 Sheet 37/37 Installation of Main Equipment BOTTOMPIM RUBBER FOOT PIN PUSH
Page 77
CHAPTER 3 ND-45492 (E) Pag e 6 0 Revision 2.0 1. Installation of External MDF • Secure the external MDF onto the floor or mount the MDF onto the wall. • Mount the required MDF components. • If required, install the cable ducts for the cables to be laid between the MDF and the Main Equipment. In this case, confirm the locations of the cable holes for the Main Equipment. Refer to Figure 004-1. Figure 004-1 Location of the Cable Hole NAP 200-004 Sheet 1/12 Installation of Peripheral Equipment FRONT 430...
Page 78
ND-45492 (E) CHAPTER 3 Page 61 Revision 2.0 2. Installation of SN610 ATTCON (1) Screw the handset support onto the bottom of the console as shown in Figure 004-2. Figure 004-2 Mounting of the Handset Support to the SN610 ATTCON NAP 200-004 Sheet 2/12 Installation of Peripheral Equipment AT TENTION Contents Static Sensitive Handling Precautions Required HANDSET SUPPORT SN610 ATTCON
Page 79
CHAPTER 3 ND-45492 (E) Pag e 6 2 Revision 2.0 (2) To provide the console with the headset in place of the handset, unplug the modular cord from the handset and plug the modular cord to the Jack Set. Figure 004-3 Jack Set Installation for the SN610 ATTCON NAP 200-004 Sheet 3/12 Installation of Peripheral Equipment AT TENTION Contents Static Sensitive Handling Precautions Required SN610 AT T C O N MODULAR CORD JACK SET
Page 80
ND-45492 (E) CHAPTER 3 Page 63 Revision 2.0 (3) Set the switch located inside the console according to the type of headset/handset connected. Refer to Fig- ure 004-4. Figure 004-4 Switch Setting on the SN610 ATTCON (1 of 2) NAP 200-004 Sheet 4/12 Installation of Peripheral Equipment AT TENTION Contents Static Sensitive Handling Precautions Required • Slide the directory out of the way. Then insert a flat screw driver’s blade into the notched opening and apply light upward pressure until the access...