    							CHAPTER 3 ND-45492 (E)
    Pag e 5 4
    Revision 2.0
    3.2. Multiple-PIM Installation
    (1) Secure the 19” BRACKET to the 19-inch Rack as shown in Figure 003-26.
    (2) Mount a PIM on the 19” BRACKET as shown in Figure 003-26.
    Then, secure the PIM to the 19” BRACKET as shown in Figure 003-26.
    (3) Repeat step (1) and (2) according to the number of modules. A maximum of 5 modules (4 PIMs and 1 MD-
    FM) can be mounted in the 19-inch Rack.
    Figure 003-26  Mounting the PIM to the 19-Inch Rack (2 of 2)
    NAP 200-003
    Sheet 32/37
    Installation of Main Equipment
    A
    B
    C
    A
    BPIM 19” BRACKET
    C
    FRONT19” BRACKET19-INCH RACK
    Note:The MDFM can be installed in the same manner as the PIM.
    PIM 
    						
    							ND-45492 (E) CHAPTER 3
    Page 55
    Revision 2.0
    (4) Position the TOP COVER on the top PIM, and connect them with 4 screws (provided) as shown in Figure
    003-27.
    Figure 003-27  Mounting of the TOP COVER
    NAP 200-003
    Sheet 33/37
    Installation of Main Equipment
    FRONT
    TOP COVER
    19 BRACKET
    PIM 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 5 6
    Revision 2.0
    (5) Connect the BASE to the bottom PIM as shown in Figure 003-28.
    Figure 003-28  Connecting the BASE to the PIM
    NAP 200-003
    Sheet 34/37
    Installation of Main Equipment
    Note:The MDFM can be connected to the BASE in the same manner as the PIM.
    FRONT
    BASE
    BASE  PIM
    19 BRACKET
    19 BRACKET
    PIM 
    						
    							ND-45492 (E) CHAPTER 3
    Page 57
    Revision 2.0
    (6) Do the following cable connectons in the same manner as for Floor Standing Installation.
    (a) Connect the AC CORD-B cables to the terminals inside the BASE (Refer to Figure 003-11 through
    Figure 003-13).
    (b) Connect the PZ-PW86 cards to each other using PWR CA-A cables (Refer to Figure 003-14 through
    Figure 003-15).
    (c) Mount the PN-BS00 card in the BUS slot of PIM0, and mount the PN-BS01 card in each BUS slot of
    PIM1 through PIM3 (Refer to Figure 003-16).
    Then, connect all the BUS cards (PN-BS00/PN-BS01) to each other using BUS cables (Figure 003-
    17 and Figure 003-18).
    NAP 200-003
    Sheet 35/37
    Installation of Main Equipment 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 5 8
    Revision 2.0
    4. Desk Top Installation
    (1) Connect the TOP COVER, BOTTOM COVER and AC CORD-A to the PIM as shown in Figure 003-29.
    The AC CORD-A is pre-installed with the BOTTOM COVER.
    Figure 003-29  Connecting the Covers and AC CORD-A to the PIM
    NAP 200-003
    Sheet 36/37
    Installation of Main Equipment
    TOP COVER
    TO PZ-PW86 PIM
    AC CORD-A
    BOTTOM COVER
    LOCAL CABLE DUCT
    PWR CA-A/BUS CABLE DUCT 
    						
    							ND-45492 (E) CHAPTER 3
    Page 59
    Revision 2.0
    (2) Connect the RUBBER FEET to the PIM as shown in Figure 003-30.
    Figure 003-30  Connecting the RUBBER FOOT to the PIM
    NAP 200-003
    Sheet 37/37
    Installation of Main Equipment
    BOTTOMPIM
    RUBBER FOOT
    PIN
    PUSH 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 6 0
    Revision 2.0
    1. Installation of External MDF
    • Secure the external MDF onto the floor or mount the MDF onto the wall.
    • Mount the required MDF components.
    • If required, install the cable ducts for the cables to be laid between the MDF and the Main Equipment.  In
    this case, confirm the locations of the cable holes for the Main Equipment.  Refer to Figure 004-1.
    Figure 004-1  Location of the Cable Hole
    NAP 200-004
    Sheet 1/12
    Installation of Peripheral Equipment
    FRONT
    430 mm (16.9 inch)
    RACK PARTS
    214 mm (8.4 inch)
    184 mm (7.2 inch)30 mm (1.2 inch) CABLE HOLE 
    						
    							ND-45492 (E) CHAPTER 3
    Page 61
    Revision 2.0
    2. Installation of SN610 ATTCON
    (1) Screw the handset support onto the bottom of the console as shown in Figure 004-2.
    Figure 004-2  Mounting of the Handset Support to the SN610 ATTCON
    NAP 200-004
    Sheet 2/12
    Installation of Peripheral Equipment
    AT TENTION
    Contents
    Static Sensitive
    Handling
    Precautions Required 
    HANDSET
    SUPPORT
    SN610 ATTCON 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 6 2
    Revision 2.0
    (2) To provide the console with the headset in place of the handset, unplug the modular cord from the handset
    and plug the modular cord to the Jack Set.
    Figure 004-3  Jack Set Installation for the SN610 ATTCON
    NAP 200-004
    Sheet 3/12
    Installation of Peripheral Equipment
    AT TENTION
    Contents
    Static Sensitive
    Handling
    Precautions Required 
    SN610
    AT T C O N
    MODULAR
    CORD
    JACK SET 
    						
    							ND-45492 (E) CHAPTER 3
    Page 63
    Revision 2.0
    (3) Set the switch located inside the console according to the type of headset/handset connected.  Refer to Fig-
    ure 004-4.
    Figure 004-4  Switch Setting on the SN610 ATTCON (1 of 2)
    NAP 200-004
    Sheet 4/12
    Installation of Peripheral Equipment
    AT TENTION
    Contents
    Static Sensitive
    Handling
    Precautions Required 
    • Slide the directory out of the way.
    Then insert a flat screw driver’s blade into the notched opening and apply light upward pressure
    until the access panel is clear of the front lip.  At the same time apply pressure (toward you) at
    the rear of the pedestal to move the access panel.