    							CHAPTER 3 ND-45492 (E)
    Pag e 7 4
    Revision 2.0
    1.1. Internal Battery Connection
    (1) Install the two batteries (12VDC, 3.0-3.4AH) into each PIM as shown in Figure 005-1.
    Figure 005-1  Internal Battery Mounting
    NAP 200-005
    Sheet 3/7
    Connection of Battery
    FRONT 67mmDIMENSION OF BATTERY
    BATTERY UNIT
    (2 
    ´ 12VDC, 3.0 to 3.4AH)
    (2.6 inch)
    134mm
    (5.3 inch) 60mm
    (2.4 inch)
    BASE PIM PIM
    Recommended Batteries
    Yuasa NPH-3.2-12
    Matsushita LCR-12V3.4NE 
    						
    							ND-45492 (E) CHAPTER 3
    Page 75
    Revision 2.0
    (2) Plug the battery cable connector into the BATT1 connector on the PZ-PW86 as shown in Figure 005-2.
    (3) Secure the batteries and battery cable using tie wraps as shown in Figure 005-2.
    Figure 005-2  Internal Battery Connection
    NAP 200-005
    Sheet 4/7
    Connection of Battery
    PLUG IN TO BATT 1
    CONNECTOR ON PZ-PW86
    FRONT
    TIE WRAP
    BASEPIM 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 7 6
    Revision 2.0
    (4) When the system is a multiple PIM configuration, provide the following connections to the internal batter-
    ies.
    Figure 005-3  Internal Battery Connection for a Multiple PIM Configuration
    NAP 200-005
    Sheet 5/7
    Connection of Battery
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM3
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM2
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM1
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM0
    BATTERY CABLE
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM7
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM6
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM5
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM4
    BATTERY CABLE Blue
    Red 
    						
    							ND-45492 (E) CHAPTER 3
    Page 77
    Revision 2.0
    1.2. Battery Connection in the BATTM
    (1) Connect the battery cables to the batteries, and mount the battery units (24 V DC, 24AH per unit) into the
    Battery Module (BATTM) as shown in Figure 005-4.
    Figure 005-4  Battery Mounting into the BATTM
    NAP 200-005
    Sheet 6/7
    Connection of Battery
    +
    +
    +
    +
    BATTERY CABLE
    TO PZ-PW86 IN PIM0/PIM4
    BATTM
    BATTERY UNIT (24 V DC, 24AH)
    BATTERY UNIT (24 V DC, 24AH) FRONT
    TO PZ-PW86 IN PIM0/PIM4
    Recommended Batteries
    Yuasa NP-24-12B
    Matsushita LCL-12V-24
    Specifications
    UL Listed
    12VDC, 24AH
    Terminal:  bolt/nut type with hole for 5mm bolt
    Dimensions:
    166mm L x 175mm W x 125mm H
    (6.54in L x 6.89in W x 4.92in H)
    A: 12mm
    5.5mm
    B: 2mm
    (.216in)(.472in)
    (.079in) 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 7 8
    Revision 2.0
    (2) Plug the battery cable connector into the BATT1 connector on the PZ-PW86 in PIM0 or PIM4. Figure 005-
    5 shows an example of battery connection in the BATTM for 8-PIM configuration.
    Figure 005-5  Battery Connection in the BATTM for a Multiple PIM Configuration
    NAP 200-005
    Sheet 7/7
    Connection of Battery
    –+–+
    –+–+
    BATT2
    BATT1 PZ-PW86
    PIM3
    BATT2
    BATT1 PZ-PW86
    PIM2
    BATT2
    BATT1 PZ-PW86
    PIM1
    BATT2
    BATT1 PZ-PW86
    –+–+
    PIM0
    BATTERY CABLE
    BATT2
    BATT1 PZ-PW86
    PIM7
    BATT2
    BATT1 PZ-PW86
    PIM6
    BATT2
    BATT1 PZ-PW86
    PIM5
    BATT2
    BATT1 PZ-PW86PIM4
    –+–+
    BATTERY CABLE
    Note:External batteries can be connected in the same manner as the batteries in the BATTM.
    BATTM BATTM 
    						
    							ND-45492 (E) CHAPTER 3
    Page 79
    Revision 2.0
    1. MDF Cable
    To facilitate the termination of the 25 pair cables (MDF cables) from the system to the MDF shown in Figure
    006-1, the length of each cable to be used should be predetermined according to the distance between the MDF
    and the system. Each cable should be labeled at both ends using a cable number or cable designation as shown
    in Table 006-1.
    Figure 006-1  MDF Cable
    NAP 200-006
    Sheet 1/7
    Cable Running to the MDF
    TO PIMCHAMP CONNECTOR
    TO MDFTWISTED 25 PAIR CABLES 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 8 0
    Revision 2.0
    NAP 200-006
    Sheet 2/7
    Cable Running to the MDF
    Table 006-1  MDF Cables for each PIM
    FROM
    CABLE NUMBER TOCABLE
    DESIGNATION
    MODULE CONNECTION
    PIM0LT C 0 1
    MDF0   LTC0
    LT C 1 2 0    LT C 1
    LT C 2 3 0    LT C 2
    PIM1LT C 0 4
    MDF1   LTC0
    LT C 1 5 1    LT C 1
    LT C 2 6 1    LT C 2
    PIM2LT C 0 7
    MDF2   LTC0
    LT C 1 8 2    LT C 1
    LT C 2 9 2    LT C 2
    PIM3LT C 0 1 0
    MDF3   LTC0
    LTC1 11 3   LTC1
    LTC2 12 3   LTC2
    PIM4LT C 0 1 3
    MDF4   LTC0
    LTC1 14 4   LTC1
    LTC2 15 4   LTC2
    PIM5LT C 0 1 6
    MDF5   LTC0
    LTC1 17 5   LTC1
    LTC2 18 5   LTC2
    PIM6LT C 0 1 9
    MDF6   LTC0
    LTC1 20 6   LTC1
    LTC2 21 6   LTC2
    PIM7LT C 0 2 2
    MDF7   LTC0
    LTC1 23 7   LTC1
    LTC2 24 7   LTC2 
    						
    							ND-45492 (E) CHAPTER 3
    Page 81
    Revision 2.0
    2. Cable Running to the External MDF
    (1) When not using the cable hole of the PIM
    (a) Bring the MDF cable up to the Main Equipment through the cable hole(s) of the BASE.
    (b) Connect the champ connector of each MDF cable to an LTC connector located on a PIM using the
    screws provided, as shown in Figure 006-2.
    (c) Pare the sheath of each MDF cable and secure the shield to the front bracket on the PIM using tie
    wraps, as shown in Figure 006-2.
    Figure 006-2  Cable Running to the External MDF (1 of 2)
    NAP 200-006
    Sheet 3/7
    Cable Running to the MDF
    LTC CONNECTOR
    CHAMP CONNECTOR
    FRONT
    TO MDF BASE PIM0 PIM1PBXTIE WRAP SHIELDPIMMDF CABLE
    25 ~ 30 mm(1.0 ~ 1.2 inch) 
    						
    							CHAPTER 3 ND-45492 (E)
    Pag e 8 2
    Revision 2.0
    (2) When using the cable hole of the PIM
    (a) Make the cable hole on the left side of PIM as shown in Figure 006-3.
    Figure 006-3  Making Cable Hole on the PIM
    (b) Bring the MDF cable up to the PIM0 through the cable hole (s) of the BASE and bring the MDF cable
    up to the other PIM through the cable hole (left side) of each PIM.
    (c) Connect the champ connector of each MDF cable to an LTC connector located on a PIM using the
    screws provided, as shwon in Figure 006-4.
    (d) Pare the sheath of each MDF cable and secure the shield to the front bracket on the PIM using tie
    wraps, as shown in Figure 006-4.
    NAP 200-006
    Sheet 4/7
    Cable Running to the MDF
    Front
    Cut off the plate.
    File the projections.Put in the edgings. 
    						
    							ND-45492 (E) CHAPTER 3
    Page 83
    Revision 2.0
    Figure 006-4  Cable Running to the External MDF (2 of 2)
    NAP 200-006
    Sheet 5/7
    Cable Running to the MDF
    LTC CONNECTOR
    CHAMP CONNECTOR
    FRONT
    TO MDF BASE PIM0 PIM1PBXTIE WRAP SHIELDPIMMDF CABLE
    25 ~ 30 mm(1.0 ~ 1.2 inch)