Trane Rtaaiom3 Manual
Have a look at the manual Trane Rtaaiom3 Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 12 Trane manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.
51RTAA-IOM-3 Table 4 Liquid Line Size for Horizontal and/or Downflow Lines Circuit Size: Liquid Line Size (OD”)Total Equiv. Length (Ft) 100 Ton 85 Ton 70 Ton25 1 1/8 1 1/8 1 1/8 50 1 3/8 1 1/8 1 1/8 75 1 3/8 1 3/8 1 3/8 100 1 3/8 1 3/8 1 3/8 125 1 3/8 1 3/8 1 3/8 150 1 5/8 1 3/8 1 3/8 175 1 5/8 1 5/8 1 5/8 200 1 5/8 1 5/8 1 5/8 225 1 5/8 1 5/8 1 5/8 250 1 5/8 1 5/8 1 5/8 275 1 5/8 1 5/8 1 5/8 300: 1 5/8 1 5/8 1 5/8 Table 5 Equivalent Lengths of Non-Ferrous valves and Fittings Line Size Globe Angle Short Long Inches OD Valve Valve Radius ELL Radius ELL 1 1/8 87 29 2.7 1.9 1 3/8 102 33 3.2 2.2 1 5 /8 115 34 3.8 2.6 2 1/8 141 39 5.2 3.4 2 5/8 159 44 6.5 4.2 3 1/8 185 53 8.0 5.1 3 5/8 216 66 10.0 6.3 4 1/8 248 76 12.0 7.3 Reproduced by permission of Air conditioning and Refrigeration Institute. Line Sizing Equivalent Line Length To determine the appropriate size for field installed liquid and suction lines, it is first necessary to establish the equivalent length of pipe for each line. An initial approximation can be made by assuming that the equivalent length of pipe is 1.5 times the actual length of pipe. These assumed lengths can then be used with the appropriate tables in the Liquid Line Sizing section and the Suction Line Sizing sections which follow. It is also necessary to know the capacity (tons) of each circuit. Circuit capacities for each RTAA unit are listed in Table 3.The following are examples of how to determine line sizes. Liquid Line Sizing This example uses the unit installation shown in Figure 31 and assumes an 85 ton circuit. The actual length of field installed piping is 117 feet (80 + 8 + 8 + 21). Using the factor of 1.5, the equivalent line length is 175 feet.From Table 4, for horizontal and/or downflow liquid lines, and assuming an 85 ton circuit, 175 feet of equivalent line requires a liquid line with an OD of 1 5/8 in. There are 6 long-radius elbows in this example. Using Table 5 and the pipe OD of 1 5/8 in., these fittings represent 15.6 feet (6 elbows @ 2.6 feet each). Therefore our new equivalent line length is 132.6 feet (117 +15.6). Referring back to Table 4, an 85 ton circuit with 132.6 feet of equivalent pipe length (use the dimension closest to the calculated dimension) can use a pipe O.D. of 1% in. rather than 1 5/8 in. From Table 5 we see that the 6 elbows of 1 3/8 in. have an equivalent pipe length of 13.2 feet (6 elbows @ 2.2 feet each). This further reduces the equivalent pipe length to 130.2 feet (117 + 13.2), and, as shown in Table 4, still allows the use of 1 3/8 in. O.D. pipe. Table 3 RTAA Circuit Capacities Model Circuit 1 Circuit 2130 70 70 140 70 70 155 85 70 170 100 70 185 100 85 200 100 100
52 RTAA-IOM-3 Figure 31 Remote Evaporator Piping Example
53RTAA-IOM-3 Suction Line Sizing This example uses the unit installation shown in Figure 31 and assumes a 100 ton circuit. As in the liquid line sizing example, the equivalent pipe length must first be determined. It must also be determined what portion of the pipe is “horizontal and/or downflowing” and what portion is “horizontal and/or upflowing.” In Figure 31, the actual length of field installed piping is 100 feet (20 + 5 + 75). Using the factor of 1.5, the equivalent line length is 150 feet. The suction line has an elevation of 20 feet and consists of horizontal and vertical (upflowing) sections, which must be sized separately. The two vertical sections are separated by a small horizontal section. The total distance is 25 feet (20 +5). The first approximation of equivalent pipe length is 37.5 feet (1.5 times 25). Referring to Table 6 for a horizontal and/or upflow suction line on a 100 ton circuit with 37.5 feet of line, the pipe O.D. should be 3 1/8 in.Add the 75 feet of horizontal and/or downflow line to the 45.4 feet of horizontal and/or upflow line, resulting in 120.5 of equivalent pipe length. Table 7 at 125 feet (use the dimension closest to the calculated dimension) indicates the use of 4 1/8 in. O.D. pipe. Therefore, the 4 1/8 in line will have to be reduced for the vertical sections of the line and expanded again for the horizontal sections. There are four long-radius elbows in this section of piping. Using Table 5 and the pipe OD of 3 1/8 in., these fittings represent 20.4 feet (4 elbows @ 5.1 feet each). Therefore our new equivalent line length is 45.4 feet (25 + 20.4). Table 6 indicates that 45.4 equivalent feet still permits the use of 3 1/8 in. O.D. pipe. In sizing the horizontal and/or downflow portion of the suction line, it is necessary to account for the total equivalent length of the line. Note: In this example, the horizontal line is pitched downward in the direction of flow Using Table 7 and 150 feet of equivalent pipe length for a 100 ton circuit, a pipe O.D. of 4 1/8 in. is specified. There are no fittings in the 75 foot horizontal run, so no equivalent fitting lengths need to be determined. Table 6 Suction Line Size for Horizontal and/or Upflow Lines Circuit Size: Suction Line Size (OD”)Total Vertical Equiv. Length (Ft) 100 Ton 85 Ton 70 Ton50: 3 1/8 3 1/8 2 1/8 75: 3 1/8 3 1/8 2 1/8 100: 3 1/8 3 1/8 2 1/8 Table 7 Suction Line Size for Horizontal and/or Downflow Lines Circuit Size: Total Equiv. Length (Ft) Suction Line Size (OD”) (Including vertical section, if any) 100 Ton 85 Ton 70 Ton50: 3 1/8 3 1/8 2 5/8 75: 3 1/8 3 1/8 2 5/8 100: 3 1/8 3 1/8 3 1/8 125: 4 1/8 3 1/8 3 1/8 150: 4 1/8 3 1/8 3 1/8 175: 4 1/8 4 1/8 3 1/8 200: 4 1/8 4 1/8 3 1/8 225: 4 1/8 4 1/8 3 1/8 250: 4 1/8 4 1/8 3 1/8 275: 4 1/8 4 1/8 3 1/8 300: 4 1/8 4 1/8 3 1/8
54RTAA-IOM-3 Piping Installation Procedures The outdoor unit and the evaporator are shipped with a 25 psig holding pressure of dry nitrogen. Do not relieve this pressure until field installation of the refrigerant piping is to be accomplished. This will require the removal of the temporary pipe caps. Note: Use Type L refrigerant-grade copper tubing only. The refrigerant lines must be isolated to prevent line vibration from being transferred to the building. Do not secure the lines rigidly to the building at any point. All horizontal suction lines should be pitched downward, in the direction of flow, at a slope of 1/2 in. per 10 feet of run, This allows for larger line size, which will improve unit efficiency. Do not use a saw to remove end caps, as this may allow copper chips to contaminate the system. Use a tubing cutter or heat to remove the end caps. When sweating copper joints, flow dry nitrogen through the system. This prevents scale formation and the possible formation of an explosive mixture of R-22 and air. This will also prevent the formation of toxic phosgene gas, which occurs when refrigerant is exposed to open flame. WARNING: To prevent Injury or death, due to explosion and/or inhalation of phosgene gas, purge the system thoroughly while sweating connections. Use a pressure regulator in the line between the unit and the high pressure nitrogen cylinder to avoid over-pressurization and possible explosion. Refrigerant Sensors The suction line refrigerant sensors must be installed by the contractor installing the refrigerant piping. The sensors are pre-wired and each is “wire-tied” to its respective liquid line. Fittings and adapters for mounting of the sensors are located in the remote evaporator terminal box. See Figure 32 for mounting instructions.
55RTAA-IOM-3 Figure 32 Customer Interconnect Wiring for RTAA Outdoor unit with Remote Evaporator – 130 to 200 Tons 2306-9133A
56RTAA-IOM-3 Leak Test and Evacuation After installation of the refrigerant piping, thoroughly test the system for leaks. Pressure test the system at pressures required by local codes. Immediately before evacuation, install the liquid line filter cores. These will be shipped with the evaporator. Note: Do not install these before the circuit is ready for evacuation, as the cores will absorb moisture from the atmosphere. For field evacuation, use a rotary-type vacuum pump capable of pulling a vacuum of 100 microns or less. Follow the pump manufacturer’s instructions for proper use of the pump. The line used to connect the pump to the system should be copper and be the largest diameter that can be practically used. A larger line size with minimum flow resistance can significantly reduce evacuation time. Use the ports on the compressor suction service valves and the liquid line shutoff valves for access to the system for evacuation. Insure that the compressor suction service valve, the liquid line shutoff valve, the oil line shutoff valve and any field installed valves are open in the proper position before evacuating. Insulate the entire suction line and the suction accumulator line. Where the line is exposed to the weather, wrap it with weatherproof tape and seal with weatherproof compound. Refrigerant and Additional Oil Charge Refrigerant Charge Determination The approximate amount of refrigerant charge required by the system must be determined by referring to Table 8 and must be verified by running the system and checking the liquid line sightglasses. Table 8 System Refrigerant Charge Circuit Size Lbs. of R-2270 130 85 165 100 170 To determine the appropriate charge, first refer to Table 8 to establish the required charge required without the field-installed piping. Next, determine the charge required for the field- installed piping by referring to Table 9. Table 9 Field-installed Piping Charge Pipe O.D. Suction Liquid (inches) Line Line 1 3/8 1.2 63.0 1 5/8 1.7 89.2 2 1/8 2.9 155.2 2 5/8 4.5 239.4 3 1/8 6.4 — 4 1/8 11.3 — Note: The amounts of refrigerant listed in Table 9 are based on 100 feet of pipe. Actual requirements will be in direct proportion to the actual length of piping. Note: Table 9 assumes: Liquid Temperature = 100 F Suction Temperature = 35 F Suction Superheat Temperature = 8 FThe approximate amount of refrigerant is therefore the sum of the values determined from Tables 8 and 9. Example: Determine the approximate amount of charge required for an RTAA 200 ton unit with a remote evaporator that is located 75 feet away (i.e. the actual length of field installed pipe is 75 feet for each suction line and liquid line). Assume that the suction lines have been previously determined to be 4 1/8 in., O.D. and the liquid lines are 1 3/8 in. O.D. A 200 ton unit has two 100 ton circuits. From Table 8 above, a 100 ton circuit requires 170 lbs. of R-22. In addition, the 4 1/8 in. 0. D. suction line for the 100 ton circuit will require 11.3 lbs. per 100 feet of the 75 feet of line will therefore require 8.5 lbs. (11.3 times 75/100). Similarly from Table 9, the 1 3/8 in. O.D. liquid line will require 47.3 lbs. of R-22 (63 times 75/100). The total R-22 charge for the 100 ton circuit will be 225.8 lbs. (170 + 8.5 + 47.3). And because the RTAA 200 has two 100 ton circuits, the total system charge will be twice as much, or 461.6 lbs. Oil Charge Determination The unit is factory charged with the amount of oil required by the system, without the field-installed piping. The amount of additional oil required is dependent upon the amount of refrigerant that is added to the system for the field-installed piping. Use the following formula to calculate the amount of oil to be added: Pints of Oil (Trane Oil-15) = lbs. of refrigerant added for field-installed piping/18.375 From the example above, in which the weight of the additional refrigerant added for the field-installed piping was 55.8 lbs. (47.3 + 8.5), the amount of oil to be added equals 3 pints (55.8/18.375) per circuit.
57RTAA-IOM-3 Installation – Electrical Figure 33 Warning Label General Recommendations WARNING: The Warning Label shown in Figure 33 is displayed on the equipment and shown on wiring diagrams and schematics. Strict adherence to these warnings must be observed. All wiring must comply with local codes and the National Electric Code. Typical field wiring diagrams are shown in Figures 34 thru 36. Minimum circuit ampacities and other unit electrical data are on the unit nameplate and are shown in Table 10. See the unit order specifications for actual electrical data. Specific electrical schematics and connection diagrams are shipped with the unit. Caution: To avoid corrosion and overheating at terminal connections, use copper conductors only. Do not allow conduit to interfere with other components, structural members or equipment. Control voltage (115V) wiring in conduit must be separate from conduit carrying low voltage (
58RTAA-IOM-3 (Continued on Next Page)Figure 34 Typical Field Wiring for RTAA Packaged Unit – 130 to 200 Tons
59RTAA-IOM-3 (Continued from Previous Page) See Notes on Next Page
60RTAA-IOM-3 Figure 34 (Continued from Last Page) Typical Field Wiring for RTAA Packaged Unit – 130 to 200 Tons 2306-9123-A