Page 81

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure Manual
ND-70928 (E), Issue 1.0Page 55

For Fixed Equipment
(1) Fix the BASE PLATE to the floor with anchor bolts. 
(2) Fix the BASE to the BASE PLATE with screws. See Figure 2-12.
(3) Fix the PIM onto the BASE with screws. See Figure 2-13.

For Stationary Equipment
(1) Fix the BASE TRAY to the floor with anchor bolts. 
(2) Fix the PIM onto the BASE with screws. See Figure 2-13.
(3) Place the Module and the BASE on...

Page 82

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure ManualPage 56ND-70928 (E), Issue 1.0
Figure 2-7  Floor Space
PIM/BATTM
FRONT
BASE
1000 (39.4)223 (8.8)
200 (7.9) 430 (16.9)
200 (7.9)UNIT : mm (inch)
MAINTENANCE 
AREA 

Page 83

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure Manual
ND-70928 (E), Issue 1.0Page 57
Figure 2-8  Cable Hole Location
BASE PIM
 : CABLE HOLE FRONT 

Page 84

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure ManualPage 58ND-70928 (E), Issue 1.0
Figure 2-9  Floor Marking for BASE PLATE (for Fixed Equipment)
Figure 2-10  Floor Marking for BASE TRAY (for Stationary Equipment)
(WALL)UNIT : mm (inch)
202.6 
(7.9)ANCHOR BOLT x 4
347.2 (13.7)
412.4 (16.2) 30 
(1.2)30 
(1.2)
34 
(1.3)128 
(5.0)40.6 
(1.6)
 
Using MOUNTING BRACKET: 10 (0.4) 
Not Using MOUNTING BRACKET
: 1.7 (0.1)
ANCHOR BOLT x 4
45 128
(1.8) (5.0)
43.9
(1.7)347.2...

Page 85

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure Manual
ND-70928 (E), Issue 1.0Page 59
Drilling
(1) Make a preliminary hole in the concrete, using a drill bit for small-diameter holes.
(2) Drill a hole in the concrete with a drill suitable for a plug bolt a little deeper than the plug 
bolt length.
Anchor Bolt Size : 10mm (0.39 inch) DIA for Fixed Equipment
6mm (0.24 inch) DIA for Stationary Equipment
(3) Insert the anchor bolt into the hole.
(4) Push anchor bolt...

Page 86

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure ManualPage 60ND-70928 (E), Issue 1.0
Detaching FRONT COVER
(1) Push portion A of the COVER PARTS to release the LATCH.
(2) Pivot the COVER PARTS on its left side to remove it.
(3) Loosen its one screw.
(4) Lift up the STOPPER to unlock.
(5) Pivot the FRONT COVER on its bottom to remove it.
Detaching FRONT COVER
(1) PUSH COVER PARTS.
(2) REMOVE COVER PARTS.
COVER PARTSPUSH
PORTION A 

Page 87

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure Manual
ND-70928 (E), Issue 1.0Page 61
(3) LOOSEN A SCREW.
(4) LIFT UP STOPPER (UNLOCK). 

Page 88

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure ManualPage 62ND-70928 (E), Issue 1.0
(5) REMOVE FRONT COVER. 

Page 89

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure Manual
ND-70928 (E), Issue 1.0Page 63
Connection of BASE and BASE PLATE for Fixed Equipment
(1) Mount the BASE on the BASE PLATE by placing it over the hooks.
(2) Slide the BASE into the inner end.
(3) Secure the BASE to the BASE PLATE with two screws.
NOTE:
Screws are attached to the BASE PLATE.
Figure 2-12  Connection of BASE and BASE PLATE
FRONT
BASE PLATEBASE
HOOKS
BASE
BASE PLATESLIDE BASE INTO INNER END. 

Page 90

CHAPTER 2 INSTALLATION
Floor Standing Installation
NEAX2000 IVS2 Installation Procedure ManualPage 64ND-70928 (E), Issue 1.0
Connection of PIM and BASE for Fixed/Stationary Equipment
(1) Mount the PIM on the BASE by placing it over the hooks.
(2) Slide the PIM into the inner end.
(3) Fix the PIM to the BASE with three screws.
NOTE:
Screws are attached to the Module.
Figure 2-13  Connection of PIM and BASE
SCREWS
BASE PIMBASE
HOOKS
    
  SLIDE PIM INTO 
      INNER END. 