Here you can view all the pages of manual Lucent Technologies DEFINITY Enterprise Communication Server Release 8.2 Installation And Test For Multi-Carrier Cabinets Manual. The Lucent Technologies manuals for Communications System are available online for free. You can easily download all the documents as PDF.
Page 161
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-3 Test TDM Bus in PPN 4 Screen 4-2. Example System Configuration Screen NOTE: Under Assigned Ports , a “ u” ind ic ates unassig ned p orts and a numb er ind ic ates the p ort has b een translated . Test TDM Bus in PPN 1. Verify the sc reen d isp lays: Command: 2. Type test tdm port-network 1 and p ress En te r. 3. Verify the sc reen d isp lays the results similar to Sc...
Page 162
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-4 Test Tone-Clock Circuit Packs 4 Screen 4-3. Example Test Results for TDM Port Network 1 4. If the result is FAIL for any test, c hec k the c onnec tors of the TDM bus c ab les in PPN 1. Test Tone-Clock Circuit Packs This test also d etec ts p rob lems with the TDM b us c ab les. 1. Verify the sc reen d isp lays: Command: 2. Type test tone-clock 1a and p ress En te r. 3....
Page 163
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-5 Test SPE Duplication Memory Shadowing Link 4 Screen 4-4. Example Test Results for Tone-Clock 1A Test SPE Duplication Memory Shadowing Link For hig h and critic al reliab ility systems only. 1. Verify the sc reen d isp lays: Command: 2. Type test shadow-link and p ress En te r. 3. Verify the sc reen d isp lays test results similar to Sc re e n 4 - 5 . Screen 4-5. Example...
Page 164
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-6 Test Duplicated Switch Processing Element Interchange 4 Test Duplicated Switch Processing Element Interchange For hig h and critic al reliab ility systems only. 1. Verify the sc reen d isp lays: Command: 2. Type status cabinet and press En t e r. 3. Verify the sc reen d isp lays test results similar to Sc re e n 4 - 6 . Screen 4-6. Example System Status Report for All...
Page 165
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-7 Test Expansion Interface Circuit Packs 4 Test Expansion Interface Circuit Packs 1. Verify the sc reen d isp lays: Command: 2. Type test board (where UUCCss is the c ab inet, c arrier, and slot for an exp ansion interfac e c irc uit p ac k in the system) and p ress En t e r. Lab els on the port network and c arrier c ontaining the board and the lab el on the strip...
Page 166
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-8 Test TDM for each EPN 4 Test TDM for each EPN 1. Verify the sc reen d isp lays: Command: 2. Type test tdm port-network 2 and p ress En te r . 3. Verify a test results sc reen similar to Sc reen 4-8 is d isp layed . Screen 4-8. Example Test Results for TDM Port Network 2 4. If result is FAIL for any test, c hec k the c onnec tors of the TDM b us c ab les in PPN 2 . 5. Rep...
Page 167
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-9 Test Tone-Clock Interchange for each EPN 4 If any result is FAIL , c hec k the assoc iated TDM b us c ables and interc ab inet c ab les in the EPN. 3. Rep eat Step 2 for eac h installed Tone-Cloc k c irc uit pac k. Test Tone-Clock Interchange for each EPN Critic al reliab ility only. 1. Verify the sc reen d isp lays: Command: 2. Type status system all-cabinets and p ress...
Page 168
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-10 Check Circuit Pack Configuration Again 4 3. Type set expansion-link xxxx (where xxxx is the either 1 of the c ab inet, c arrier, and p ort loc ations of the standb y exp ansion link). Press En t e r. 4. Verify the sc reen d isp lays: Command successfully completed Command: 5. Type status cabinet and press En t e r. See Sc reen 4-10. Screen 4-10. Example of System...
Page 169
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-11 LED Indicators 4 Next Steps After the b asic hard ware is installed and tested , 3 more step s must b e completed: 1. Install the telep hones and other equip ment. See Chap ter 5, ‘‘ Install and Wire Telep hones and Other Eq uip ment’’. 2. Ad minister the features, telep hones, and other eq uipment ac c ord ing to c ustomer d ata on the p rovisioning p lan. The d...
Page 170
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Test the System 4-12 LED Indicators 4 Attendant Console LEDs The console has 2 red LEDs, lab eled “ ALM” and “ ACK” . The ALM LED lig hts stead ily when there is a major or minor alarm at the system c ab inet. The ACK LED lig hts stead ily if the alarm has been suc c essfully rep orted to INADS. If the system is unab le to rep ort the alarm to INADS, the LED flashes; this sig nals the...