NDA-24234 CHAPTER 5
Page 321
Revision 3.0
INSTALLATION TEST PROCEDURE
Test Outline:
Tests are performed to see if system initialization can be executed. There are two kinds of test method; test by using
START button on the TOPU, and test by Power ON/OFF.
Figure 027-1  System Initialization via ‘Start’ Button
NAP-200-027
Sheet 1/2
System Initialization Test
START
Perform system initialization (via “START” button)
Set the SYSTEM DATA key on the TOPU to NON LOAD side, and set the PROGRAM key to 
NON LOAD...

Page 352

CHAPTER 5 NDA-24234
Pag e 32 2
Revision 3.0
INSTALLATION TEST PROCEDURE
NAP-200-027
Sheet 2/2
System Initialization Test
Perform system initialization (by powering ON/OFF).
Initialization by powering 
ON/OFF.On all PWR Supplies, set the circuit breaker OFF 
(Down). If a module contains two PWR Supplies, 
they must be turned ON/OFF simultaneously.
Turn ON the PWR Supplies in each module in the 
following order. If a module contains two PWR 
Supplies, they must be turned ON/OFF 
simultaneously.
LPM
→PIM0...

Page 353

NDA-24234 CHAPTER 5
Page 323
Revision 3.0
INSTALLATION TEST PROCEDURE
NAP-200-028
Sheet 1/1
Circuit Card Initialization Test
START
Make the No. 0 CPU the ACT system.
In each PIM, initialize any  
Line/Trunk circuit card.On the selected Line/Trunk circuit card, set the MB switch UP.
The OPE lamp goes out.
System Message “7-K” is displayed.
Set the MB switch DOWN.
The OPE lamp turns ON.
System Message “7-L” is displayed.
Clear the alarm Clear the alarm indication by pressing the “ALM RST” button 
on the...

Page 354

CHAPTER 5 NDA-24234
Pag e 32 4
Revision 3.0
INSTALLATION TEST PROCEDURE
4. PORT CONNECTION TEST
4.1 Outline
Tests are to be performed on all the circuits of LC and Trunk circuit cards and PWR Supplies. LC and Trunk
circuit cards are tested with respect to their operations and speech path conditions. PWR Supplies are tested with
respect to howler tone and ringing signal.
While tests are in progress, the No. 0 CPU and TSW systems must be ACT (active).
4.2 Port Connection Test Procedure
The connection test...

Page 355

NDA-24234 CHAPTER 5
Page 325
Revision 3.0
INSTALLATION TEST PROCEDURE
NAP-200-029
Sheet 1/2
ORT (RST Card) Connection Test
START
Make busy all ORTs On the front of the RST card, set all MBR switches (0-7) to 
the OFF position, making all ORTs busy.
From Station “A” (DP), test 
ORTs one circuit at a time.Un-busy (make idle) only the ORT to be tested.
Station “A” goes off-hook and after hearing DT, dials the 
station number of Station “B.”
Station “A” confirms ringing to Station “B” and Station “B”...

Page 356

CHAPTER 5 NDA-24234
Pag e 32 6
Revision 3.0
INSTALLATION TEST PROCEDURE
NAP-200-029
Sheet 2/2
ORT (RST Card) Connection Test
Perform tests for a situation where all ORTs are busy.
System Data SYS1, 
INDEX 4, b
0 =0Station “A” goes off-hook.
Station “A” confirms that Reorder Tone (ROT) is heard
Station “A” goes off-hook.
System Data SYS1, 
INDEX 4, b
0 =1Station “A” goes off-hook.
Station “A” confirms that no tone is heard.
Un-busy (make idle) a single ORT circuit.
Station “A” confirms that DT is heard....

Page 357

NDA-24234 CHAPTER 5
Page 327
Revision 3.0
INSTALLATION TEST PROCEDURE
NAP-200-030
Sheet 1/1
ATTCON (ATI Card) Connection Test
START
A station repeats an ATTCON 
call. Each ATTCON answers 
the call.Station “A” dials the operator access code (normally, “0”).
At each ATTCON, the operator confirms that the ATT lamp 
flashes and the ringer sounds.
At each ATTCON, the operator answers the call by pressing 
the ATND key.
Station “A” confirms speech with each ATTCON.
The operator at each ATTCON releases by...

Page 358

CHAPTER 5 NDA-24234
Pag e 32 8
Revision 3.0
INSTALLATION TEST PROCEDURE
NAP-200-031
Sheet 1/1
Line (LC, ELC, DLC, Card) Connection 
Te s t
An ATTCON or Dterm is called 
from each station. The called 
party confirms the station 
number.On the MDF, a telephone set is connected to the line circuit 
to be tested
The station (XXXX) to be tested goes off-hook and 
confirms DT (Dial Tone).
The station (XXXX) calls an ATTCON or D
term.
The called ATTCON or D
term answers the call, and confirms 
speech and the...

Page 359

NDA-24234 CHAPTER 5
Page 329
Revision 3.0
INSTALLATION TEST PROCEDURE
Test Outline:
The purpose of this test is to confirm, by setting up an outgoing connection test for each outgoing trunk, that speech
can be made and that the call can be released.
Outgoing trunks must be tested one at a time using the sequence of Routes and Trunk Numbers assigned at each
office
NAP-200-032
Sheet 1/3
Outgoing Trunk (COT, TLT, DTI Card) 
Connection Test
START
When a C. O. Line or Tie Line is 
not connected with a trunk...

Page 360

CHAPTER 5 NDA-24234
Pag e 33 0
Revision 3.0
INSTALLATION TEST PROCEDURE
Set up a loop-back connection between the COT (C.O. Trunk) to be tested and a station line.
Figure 032-1  COT Test Configuration
The trunk route must be assigned for Loop Start.
Figure 032-2  TLT Test Configuration
Set up a loop-back connection between the TLT (Tie Line Trunk) to be tested and another EMT.
If the TLT is a DID (Direct Inward Dialing) Trunk, connected the related leads as shown below.
If the TLT is a 2W E&M...