Page 331
NDA-24234 CHAPTER 4 Page 301 Revision 3.0 SYSTEM STARTUP Figure 022-2 LED Indications of IMG0 in Normal Operation (Multiple IMG Configuration) 13 14 MUX ACT MUX(PH-PC36) MUX(PH-PC36) 13 14 MUX ACT MUX(PH-PC36) MUX(PH-PC36) 13 14 MUX ACT MUX(PH-PC36) MUX(PH-PC36) 13 14 MUX ACT 03 04 IOC(PH-IO24) EMA(PH-PC40) OPE OPE/MB TOPU PIM3 PIM2 PIM1 PIM0 LPM BASEUFA N U FRONT VIEW : Lamp is ON (Green) : Lamp is OFF: Lamp is Flashing (Green) Legend CPU 0 → ACT TSW 0 → ACT PLO 0 → ACT System State CPU OPEIMG 0 DSP 1...
Page 332
CHAPTER 4 NDA-24234 Page 302 Revision 3.0 SYSTEM STARTUP Figure 022-3 LED Indications of IMG1 in Normal Operation (Multiple IMG Configuration) 13 14 MUX(PH-PC36) MUX(PH-PC36) 13 14 MUX(PH-PC36) MUX(PH-PC36) 13 14 MUX(PH-PC36) MUX(PH-PC36) MUX(PH-PC36) MUX(PH-PC36) 13 14 08 DLKC (PH-PC20) DLKC (PH-PC20) GT (PA-GT09) TSW 00 (PH-SW12) TSW 01 (PH-SW12) TSW 02 (PH-SW12) TSW 03 (PH-SW12) TSW 10 (PH-SW12) TSW 11 (PH-SW12) TSW 12 (PH-SW12) TSW 13 (PH-SW12)PLO Note PLO Note (RES) GT (PA-GT09) TOPU PIM3 PIM2...
Page 333
NDA-24234 CHAPTER 4 Page 303 Revision 3.0 SYSTEM STARTUP Figure 022-4 LED Indications of IMG 2/3 in Normal Operation (example) (Multiple IMG Configuration) This figure shows the LED indications (example) of a fully expanded system of IMG 2/3. 1 314 MUX (PH-PC 36) M UX(PH -PC36) 1314 MU X(PH- PC36) MUX(P H-PC3 6) 13 14 MUX( PH-PC3 6) MUX (PH-PC 36) MUX (PH-PC 36) M UX(PH -PC36) 1314 TOP U P IM3 PI M2 PIM1 PIM0 DUMM Y BASE U F ANU FRO NT V IEW : Lamp is ON IM G 2/3 Leg end : Lamp is OFF System State TSW...
Page 334
CHAPTER 4 NDA-24234 Page 304 Revision 3.0 SYSTEM STARTUP Test Outline: The System has Alarm Lamps on the TOPU. Figure 023-1 shows the Alarm Lamps on the TOPU. For more information about each lamp, see the NEAX2400 IMX System Operations and Maintenance Manual. Figure 023-1 Alarm Lamps on the TOPU Note: SMJ and SMN are used in multiple IMG configuration only. NAP-200-023 Sheet 1/2 Check of Alarm Lamps of the TOPU ATTENTIONContents Static Sensitive Handling Precautions Required PWR ONMJMN SUP GRR GY SMJ...
Page 335
NDA-24234 CHAPTER 4 Page 305 Revision 3.0 SYSTEM STARTUP NAP-200-023 Sheet 2/2 Check of Alarm Lamps of the TOPU START Test of MJ (MAJOR) Lamp Set the circuit breakers of the Power Supplies (PWR0, 1) in a PIM to OFF (About 10 seconds later, set the circuit breaker(s) back ON. Confirm that the MJ lamp (red) on the TOPU turns ON. Cancel the alarm indicating by pressing the ALM RST button on the TOPU. Test of MN (MINOR) Lamp Take an act side RGU Fuse out of the PWR card. Confirm that the MN lamp (red)...
Page 337
NDA-24234 CHAPTER 5 Page 307 Revision 3.0 CHAPTER 5 INSTALLATION TEST PROCEDURE 1. HOW TO ENTER DATA IN THE TEST CHECK COLUMN Each NAP in this Chapter has check column for test result entry for each test item (see Figure 5-1). This para- graph explains the method of entering test result into the check column concerned using Figure 5-1 as an exam- ple. 1. Method of Entry Each check column consists of two sections of “PROVIDED” and “CHECK”. If the equipment or service feature pertaining to the test item...
Page 338
CHAPTER 5 NDA-24234 Pag e 30 8 Revision 3.0 INSTALLATION TEST PROCEDURE Figure 5-1 Example of Entry to Test Check Column This example is NAP-200-024: DT Connection Test When “*” is already printed in the “PROVIDED” section, the item concerned is a basic function of the system. Test the item without exception. When “PROVIDED” section is blank, the installer should enter “*” mark as per the Job Specification. The item marked with “*” must be tested without exception. Check whether the OPE lamp (G) is...
Page 339
NDA-24234 CHAPTER 5 Page 309 Revision 3.0 INSTALLATION TEST PROCEDURE 2. BASIC CONNECTION TEST 2.1 Outline After the system has been started up, establish some basic connections and verify that the system operates nor- mally. 2.2 Basic Connection Test Procedure Perform tests on the operations of the processors and the system by referring to the NAP Number indicated to the right of each item in the following flowchart. If an operation cannot be performed satisfactorily, perform the necessary repair...
Page 340
CHAPTER 5 NDA-24234 Pag e 31 0 Revision 3.0 INSTALLATION TEST PROCEDURE NAP-200-024 Sheet 1/1 DT (Dial Tone) Connection Test START Check whether the OPE lamp (G) is turning ON on the RST circuit cards. Check whether the OPE lamp (G) is turning ON on the LC circuit cards. Lift handset. Confirm DT (Dial Tone). Check whether the Busy lamp (R) is turning ON for the connected ORT and LC. Continue listening to DT for about 12 seconds. Confirm that DT changes to Reorder Tone (ROT). Continue listening to ROT for...