Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Installation And Test For Single-Carrier Cabinets Manual
Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Installation And Test For Single-Carrier Cabinets Manual
Here you can view all the pages of manual Lucent Technologies DEFINITY Enterprise Communications Server Release 8.2 Installation And Test For Single-Carrier Cabinets Manual. The Lucent Technologies manuals for Communications System are available online for free. You can easily download all the documents as PDF.
Page 31
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-13 Connect AC Power 1 Connect AC Power Set the Ringer Frequency The d efault ring er freq uenc y setting on the 1217A p ower sup p ly for North Americ a is 20 Hz and the international setting c an b e either 20 Hz or 25 Hz. To set the ring er freq uenc y on the 1217A p ower sup p ly: !CAUTION: When add ing or rep lac ing any...
Page 32
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-14 Connect DC Power 1 Connect DC Power The following proc ed ures app ly to b oth the Proc essor Port Networks (PPN) and Exp a n si o n Po r t N e t w o rk s (EPN ) . DC Power Connections A 30 foot (9 m) c able c onnec ts to eac h c ab inet. A sp ec ial c onnec tor on one end of the c ab le is p lug g ed into the c ab inet p...
Page 33
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-15 Connect DC Power 1 DC Power Connections Figure 1-6. Typical DC Power Connections Figure Notes 1. System Cab inet Stac k 2. DC Power Cabinet 3. White Wires 4. Green Ground Wires and Blac k Wires Connec t to the -48 VDC Return Bus 5. -48 VDC Bus 6. Connec t White Wires to Circ uit Breakers 7. DC Power Cab le (H600-436, G1) to...
Page 34
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-16 Connect DC Power 1 DC Power Connections with DC Distribution Unit A 10 foot (3 meter) p ower c ord is eq uip p ed with the ap prop riate c onnec tors. In the configuration shown in Fi g u re 1 - 7 , eac h c ab inet stac k has a DC Power Distribution Unit assoc iated with it. Figure 1-7. Connections Using DC Power Distribution...
Page 35
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-17 Connect DC Power 1 Stacking DC Power Cabinets Up to three DC Power Cab inets c an be stac ked to sup p ly p ower to Sing le-Carrier Cab inet stac ks. See Fig ure 1-8 . Figure 1-8. DC Power Cabinet Stack — Rear Figure Notes 1. DC Power Cabinet Stac k 2. DC Power Cables Daisy Chained Between DC Power Cab inets 3. Connec t to...
Page 36
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-18 Connect Battery Cabinet 1 Connect Battery Cabinet Fi g u re 1 - 9 shows typ ic al c onnec tions from the DC Battery Cab inet to the DC Power Cab inet. Figure 1-9. DC Battery to DC Power Cabinet Connections !CAUTION: Power is present in the c ab inet even if the AC p ower c ab le is unp lug g ed . Turn off the main c irc uit b...
Page 37
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-19 Connect Optional Battery Leads 1 Connect Optional Battery Leads To p revent the internal b atteries from d isc harg ing , the Control Cab inet is ship p ed with the b attery lead s disc onnec ted . Figure 1-10. Control Cabinet Battery Location — Right Side 1. Set the c irc uit b reakers OFF. See Fig ure 1-10 . 2. Connec t the b...
Page 38
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-20 Connect AC Power to Stratum 3 Clock Cabinet 1 Connect AC Power to Stratum 3 Clock Cabinet The c loc k c ab inet requires a 120 VAC, 15 Amp rec ep tac le. The g reen wire g round p rovid ed b y the rec ep tac le is suffic ient. The c loc k c ab inet d oes not req uire a g round c onnec tion bac k to the sing le-p oint ground...
Page 39
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-21 Connect Time Division Multiplexing Bus Cables 1 Connect Stratum 3 Clock DC Power 1. Set the c loc k c ab inet c irc uit b reaker at the DC p ower p lant OFF. 2. At the c loc k c ab inet, c onnec t a 6 AWG (#40) (4 mm 2) g round wire to the -48V terminal on the terminal strip. 3. At the c loc k c ab inet, c onnec t a 6 AWG (#40)...
Page 40
DEFINITY Enterprise Communication Server Release 8.2 Installation and Test for Single-Carrier Cabinets 555-233-120 Issue 1 April 2000 Install and Connect the Cabinets 1-22 Connect Time Division Multiplexing Bus Cables 1 High or Critical Reliability Processor Port Network Two cabinet stacks: 1. Remove the Time Division Multip lexing (TDM) Bus Terminator from Slot 18 of Control Cab inet A (Proc essor Port Network (PPN)) and move it to Slot 18 of Control Cab inet B. See Fi g u re 1 - 1 2 . 2....