Page 81
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 74 2.) Disconnect the Mains power cable from the wall outlet. 3.) Disconnect all probes and external I/O cabling. 4.) Remove the LCD monitor assembly. 5.) Remove the Bulkhead cover and follow these steps to disconnect the cables from the Bulkhead board: Disconnect the Power/USB PLUG from the Bulkhead board. Bend the HDMI connector lock upwards, then disconnect the HDMI plug. To remove the LCD Arm assembly: Slide the LCD...
Page 82
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 75 upwards, until you can lift LCD arm assembly away. Install the LCD Arm Assembly To install the LCD arm assembly: Carefully install the LCD arm assembly into position, first feeding the LCD Arm cables down through the console opening. Push the LCD Mount Lock Handle into the locked position. LCD Mount Lock Handle Connect the LCD cables to the connectors on the bulkhead. Reinstall the bulkhead cover. Reinstall the LCD...
Page 83
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 76 Remove the bumper cover from the end of the first arm. Remove the covers from all three arm sections of the arm assembly: Remove the eight screws securing the first arm section cover. Remove the eight screws securing the third arm section cover. Remove the 16 screws securing the second arm section cover with Philips screwdriver. Third Arm Cover Removal Second Arm Section Cover Removal
Page 84
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 77 Cut tie wraps securing cables and remove the cable(s) Mark the cables: After removing the cable(s) to be replaced, stretch out both the existing and replacement cable side-by-side, and transfer any markings from existing cable to the replacement cable. Install the LCD Cables Warning: Do not over-stretch cables. Before putting the covers on the arms, be sure the arm has full pivot motion/rotation without stressing the cables....
Page 85
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 78 Feed cable through opening for second arm section making sure the markings line up with the midpoint placement location for the second arm. Feed the cable through the opening of the third arm section. For the Video and Power cables, make sure the markings appear past the third arm LCD bracket and connect to the LCD bracket with clips shown below: First (left) Arm Section Midpoint Location Second Arm Section Midpoint...
Page 86
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 79 Repeat steps for each cable replaced. Secure the cables in the locations indicated in Figure 8-103. Band the tie wrap through the clamp. Replace the second arm cover. Replace the third arm cover. Replace the first arm cover. Replace the bumper cover Reinstall the LCD arm. Reinstall the LCD monitor. Rotate the arm to ensure that its movement is smooth and free from binding through a full 180° rotation with the arm...
Page 87
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 80 Replacing Upper Operator Panel/Touch Panel Assembly Power down the system. Disconnect all probes and external I/O cabling. To remove the Upper OP Panel/Touch Panel assembly: Remove all five OP Panel Knobs along the base of the upper OP Panel/Touch Panel assembly, At the rear of the Vivid E9, release the console’s XY frogleg mechanism by inserting a screwdriver into the release point and pressing until it releases....
Page 88
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 81 Next disconnect the cables as shown below at the back of the Upper OP Panel/Touch Panel Assembly. Lift out the Touch Screen Assembly and place it on an ESD safe surface. Re-Install Upper OP Panel/Touch Panel Assembly To re-install the Upper OP Panel/Touch Panel Assembly: Place the Upper OP Panel/Touch Panel Assembly in the frame. Ensure that all Ground cables are connected as shown below: Connect the following cables...
Page 89
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 82 7. Bulkhead Board USB Cable 1 (from bulkhead position closest to the OP) in position J24 8. Bulkhead Board USB Cable 2 (from bulkhead position most far from the OP) in position J25 Install the Upper OP Panel/Touch Panel Assembly securing the five tabs and two hooks. Install the four screws to the Back Cover from behind. Install the five OP Panel Knobs. Use caution not to pinch or crimp the cables when replacing the...
Page 90
GE Logiq E9/Vivid E9 Training Manual © 2016 Conquest Imaging 83 Replace Lower Operator Panel Follow these steps to remove the Operator Panel: Pull out the Alphanumeric keyboard to its extended position to get access to the screws in the next step. Unscrew and remove the four screws used to mount the Operator Panel assembly to the Operator Panel tray. Loosen the screws for the cables grounding on the Bulkhead Bracket and move the OP cables away from the bracket. On the Bulkhead...