Page 161
Unit Startup RT-SVX24K-EN161 8. Tighten the set screw to the drive shaft. 9. Stretch the belt over the pulley and engage it in the groo ve. Compressor Startup 1. Ensure that the “System” selection switch at theremote panel is in the “Off” position. 2. Before closing the disconnect switch, ensure that the compressor discharge service valve and the liquid line service valve for each circuit is back seated. 3. Close the disconnect switch or circuit protector switch that provides the supply power to the...
Page 162
Unit Startup 162RT-SVX24K-EN 3. UseTable37, p.11 2to program the following system components for the number 1 refrigeration circuit by scrolling through the displays; Supply Fan (On) VFD (100%, if applicable) OCC/UNOCC Relay (Unoccupied for VAV units) All Compressors for each circuit (On) Condenser Fans for each circuit (On) 4. Once the configuration for the components is complete, press the NEXT key until the LCD displays the “Start test in __Sec.” screen. Press the + key to designate the delay...
Page 163
Unit Startup RT-SVX24K-EN163 Evaporative Condenser Startup Important:Water treatment by a qualified water treatment expert is required to ensure proper equipment life and product performance. Dolphin Water Care™ is an option offered by Trane that is NOT a subsitute for regular water treatment by a qualified water treatment professional. If a water treatment system is not operating on the unit, do not proceed. Startup for evaporative and air-cooled condensers is initially the same. In addition, the...
Page 164
Unit Startup 164RT-SVX24K-EN Figure 113. Fan shipping bracket removal Mist Eliminator Fan Shipping Bracket ScrewsFan Shipping Bracket Access Doors Inlet Louvers Actuator Side Figure 114. Float bracket setting Fill sump so float shuts off when water is within these slots
Page 165
Unit Startup RT-SVX24K-EN165 Thermostatic Expansion Valves The reliability and performance of the refrigeration system is heavily dependent upon proper expansion valve adjustment.Therefore, the importance of maintaining the proper superheat cannot be over emphasized. On air-cooled units, the expansion valves shipped installed were factory set to control between 14-18°F at the ARI full load rating conditions (approximately 45°/125°F saturated suction/discharge). On evaporative condenser units, the...
Page 166
Unit Startup 166RT-SVX24K-EN Electric, Steam and Hot Water Startup (Constant Volume & Variable Air Volume Systems) 1. Ensure that the “System” selection switch at the remote panel is in the “Off” position. 2. Close the disconnect switch or circuit protector switchthat provides the supply power to the unit terminal block or the unit mounted disconnect switch. HIGH VOLTAGE IS PRESENT AT TERMINAL BLOCK OR UNIT DISCONNECT SWITCH. 3. Turn the 115 volt control circuit switch and the 24 volt control circuit...
Page 167
Unit Startup RT-SVX24K-EN167 monoxide, and a steady flame that minimizes nuisance shutdowns. Two Stage Gas Furnace High-Fire Adjustment 1. UseTable 37, p. 112 to program the following system components for operation by scrolling through the Human Interface displays; Gas Heat Supply Fan (On) Return Fan (On, if supplied) Variable Frequency Drive (100% Output, if applicable) RTM Occ/Unocc Output (Unoccupied) Heat Stages1&2(On) Turn the 115 volt control circuit switch 4S24 located in the heater control panel...
Page 168
Unit Startup 168RT-SVX24K-EN for the required manifold pressure during low-fire operation. If it needs adjusting, remove the cap covering the low-fire adjustment screw on the gas valve. Refer toFigure118, p.169for the adjustment screw location. Turn the screw clockwise to increase the gas pressure or counterclockwise to decrease the gas pressure. Note: Do not adjust the combustion air damper while the furnace is operating at low-fire. 4. Check the carbon dioxide levels after each adjustment. 5. Press...
Page 169
Unit Startup RT-SVX24K-EN169 Full Modulating Gas Furnace Full Modulating gas heaters are available for the 850, 1100, 1800, 2500 MBH heater sizes. – The firing rate of the 850 MBH modulating heatercan vary from 10% to 100% of the 850 MBH. – The firing rate of the 1100, 1800 and 2500 MBH can vary from 5% to 100% of its nameplate value. Heat Exchanger The heat exchanger drum, tubes and front and rearheaders are constructed from stainless steel alloys. Unit Control The unit is controlled by a supply air...
Page 170
Unit Startup 170RT-SVX24K-EN Note:The burner capacity is controlled by the movement of the air damper. This has been preset at the factory and normally does not need field adjustment. The combustion quality (air/gas) is controlled by the setup of the air damper and butterfly valve linkage relationship. 7. Use Table37, p.11 2to program the minimum (5%) firing rate. Allow the system to operate for appro ximately 10 minutes. 8. Use a carbon dioxide analyzer and measure the percentage of carbon dioxide in...