Page 341
NDA-24306 CHAPTER 5 Page 313 Revision 1.0 INSTALLATION TEST PROCEDURE Figure 025-4 LEDs and Switches for PLO Changeover NAP-200-025 Sheet 8/13 System Changeover Test AT T E N T I O NContents Static Sensitive Handling Precautions Required Legend Lamp is ON:Lamp is OFF: PLO: ST-BY MB OPE PLO: Active MB OPE green PH-CK16-A PLO: ST-BY MB OPE PLO: Active MB OPE green PH-CK16-A / PH-CK17-A CLK: ST-BY MB OPE CLK: Active MB OPE green PH-CK18 [ISW] [Local Nodes]
Page 342
CHAPTER 5 NDA-24306 Page 314 Revision 1.0 INSTALLATION TEST PROCEDURE Figure 025-5 General Block Diagram of the Whole System (1/2) NAP-200-025 Sheet 9/13 System Changeover Test HSW TSWM0TSWM1 TSWM0TSWM1 This figure roughly shows the general block diagram of the whole system. MISCIOCEMA MISCIOCEMA TSW00TSW01TSW02TSW03 TSW00TSW01TSW02TSW03 FCCS Link ISWLN0LN1 To PLO of LN2/3 GT ISAGT-A DLKCPLO To MUX (IMG0)To MUX (IMG1) To MUX (IMG0)To MUX (IMG1)To MUX (IMG2)To MUX (IMG3) To MUX (IMG2)To MUX (IMG3) Note...
Page 343
NDA-24306 CHAPTER 5 Page 315 Revision 1.0 INSTALLATION TEST PROCEDURE Figure 025-5 General Block Diagram of the Whole System (2/2) NAP-200-025 Sheet 10/13 System Changeover Test HSW TSWM0TSWM1 TSWM0TSWM1 MI S CIOCEMA MISCIOCEMA MISCIOCEMA IOGT ISAGT FCCS LinkISWLN0 LN1 To PLO of LN1 To MUX(IMG0)To MUX(IMG1) To MUX (IMG0)To MUX (IMG1)To MUX (IMG2)To MUX (IMG3) To MUX (IMG2)To MUX (IMG3) Note 1 Note 3 Note 4 Note 4 Circuit Card (No. 0 System) Circuit Card (No. 1 System) Note 1HSW00, 01 for No. 0...
Page 344
CHAPTER 5 NDA-24306 Page 316 Revision 1.0 INSTALLATION TEST PROCEDURE Figure 025-6 System Block Diagram for ISW Switching Network NAP-200-025 Sheet 11/13 System Changeover Test This figure shows a system block diagram of ISW, which adopts a dual configuration. As seen in the figure, ISW has the following terminals for the ACT/ST-BY changeover of dual system equipment: CPU:If the ACT/ST-BY of CPU (ISW) is once changed over, the whole controlling block (including CPU, IS- AGT, LANI in ISW) are also...
Page 345
NDA-24306 CHAPTER 5 Page 317 Revision 1.0 INSTALLATION TEST PROCEDURE Figure 025-7 System Block Diagram for LN Switching Network (1/2) NAP-200-025 Sheet 12/13 System Changeover Test This figure shows a system block diagram of LN, which adopts a dual configuration. As seen in the figure, each LN has following terminals for the ACT/ST-BY changeover of dual system equipment: CPU:If the ACT/ST-BY of CPU is once changed over, the whole controlling block in the same node (in- cluding CPU, ISAGT, LANI) and GT...
Page 346
CHAPTER 5 NDA-24306 Page 318 Revision 1.0 INSTALLATION TEST PROCEDURE Figure 025-7 System Block Diagram for LN Switching Network (2/2) NAP-200-025 Sheet 13/13 System Changeover Test ISAGT-A: PZ-GT13 MUX: PH-PC36 LANI GT 0 TSW 00TSW 10TSW 01TSW 11 GT 1 EMA CLK 0 CLK 1 CPR 0LANICPR 1 MISC BUS TSW I/O BUS TSW I/O BUS Line/Trunk PMIMG 2PCM HW PCM HW PCM HW PCM HW PM BUS PCM HW PCM HW PCM HW PCM HW PM BUS ISAGT-BISAGT-B To T S W M 0 Line/Trunk PMIMG 3 TSWM1 To T S W M 0 Fr o m P L O of ISWM CPU 0...
Page 347
NDA-24306 CHAPTER 5 Page 319 Revision 1.0 Test Outline Tests are to be performed to see if the system initialization can be executed on the following basis: 1. System Initialization on a Local Node basis (in each Local Node individually) 2. System Initialization in ISW only 3. System Initialization on a system basis (in ISW and all Local Nodes simultaneously) NAP-200-026 Sheet 1/5 System Initialization Test AT T E N T I O NContents Static Sensitive Handling Precautions Required
Page 348
CHAPTER 5 NDA-24306 Page 320 Revision 1.0 1. System Initialization on a Local Node basis Perform the system initialization test in each Local Node (LN), using the keys on the TOPU (refer to Figure 026- 1): Figure 026-1 Keys on the TOPU (Local Node) NAP-200-026 Sheet 2/5 System Initialization Test START On the TOPU of the LN to be tested, set the EFFECT key to “ON” side. On the TOPU, set the SYSTEM DATA key to “NON LOAD” side, and PROGRAM key to “NON LOAD” side. Perform the system initialization by...
Page 349
NDA-24306 CHAPTER 5 Page 321 Revision 1.0 2. System Initialization in ISW Perform the system initialization test in ISW, by using the keys on the TOPU (refer to Figure 026-2): Figure 026-2 Keys on the TOPU (ISW) NAP-200-026 Sheet 3/5 System Initialization Test START On the TOPU of ISW, set the INITIAL SELECT key to “SELF” side. On the TOPU of ISW, set the EFFECT key to “ON” side. On the TOPU of ISW, set the SYSTEM DATA key to “NON LOAD” side and PROGRAM key to “NON LOAD” side. Perform the system...
Page 350
CHAPTER 5 NDA-24306 Page 322 Revision 1.0 3. System Initialization on a system basis Perform the system initialization tests in ISW and all Local Nodes simultaneously, per the flowchart cited be- low. As in the flowchart, there are two kinds of method here; test via the keys on the TOPU of ISW, and test by turning the power ON and OFF. NAP-200-026 Sheet 4/5 System Initialization Test START Perform the total system initialization via the keys on the TOPU (ISW) Note:For key allocations, refer to Figure...