, : . . m IA SX-2000 S ICS Commissioning (A)UPPERSHELF-SHELF2 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 16 19 20 * * * * * * E is PERIPHERALINTERFACE CARDS 2 VJAXIMUM OF 12) 8 k-5 B (S)LObVERSHELF-SHELF1 1 2 3 4 5 6 7 6 9 10 11 12 13 14 15 16 17 16 19 20 * * * * * * I I I I I I I PERIPHERALINTERFACE CARDS (MAXIMUM OF 12) NOTES: 1. Theminbnum~~musthavethecardsindicatedbyqnstalledhslotsssshown. 2. Digital Se&e Unih may be sny of thefdlawing: Cmference card, DSI or CEPT Fumattec Cards, DTRX o( Ccmms Pmc’r cards. 3. Control RAM II card notrequired wilh Main Catdler II card. Figure 4-l SX-2000s Circuit Card Locations 9125-060-204-NA Issue 1 Revision 0 204 4-5

Commissionina load Commissioning Software 4.2 The following chart details the steps required to install commissioning software on the SX-2000 S system. Chart 4-3 Load Commissioning Software On Plane A step Action Comments 1. Remove the ‘Write Protect” tab on the Commissioning The diskette/tape and the HDMs floppy diskette. are protected from corruption since by default when tests are If the commissioning software is stored on a cartridge run on these devices only tape, then ensure that the RECORD tab is in the designated test pages are RECORD position, accessed by them. 2. Insert the commissioning floppy/tape in the external If the external storage device is an storage device. FDU II, turn the latch to lock the diskette in place. 3. Press and hold the PANEL ENABLE button on the The Main Controller executes a Maintenance Panel, and press the PLANE A LOAD series of preloading tests. Refer to button. Practice 9125-060-353-NA, General Maintenance Information, Note: DO NOT remove the diskette/tape from the for a description of the processor external storage device. Both Main Controller card diagnostic tests. If errors cards (on the redundant SX-2000 S system) occur, loading halts and an error are trying to access the external storage code is returned on the Main device. Controller numeric display. If an error should occur, repeat step 3. If the second loading attempt fails, refer to Practice 9125-060-35O-NA, Troubleshooting Procedures. 4. Check that the Maintenance Terminal returns the following message: SX-2000 (small) COMMISSIONING IN PROGRESS (Date and name of load is output) TIME: 0O:OO:OO CONFIGURATION REPORT NOW BEING GENERATED 5. Check that after a delay, the system generates a The length of the delay is configuration report for all installed cards. proportional to the number of cabinets in the system. No output appears at the terminal until all cards are configured. Refer to Appendix A., Table A2-1, for an example of a configuration report. Page 1 of 2 264 4-6 Revision 0 912!!&60-204-NA Issue 1

m IA SX-2000 S ICS Commissioning Chart 4-3 Load Commissioning Software On Plane A (continued) and reinsert the incorrectly configured card. Enter the CONFIG command to generate a new report, If the card still does ONFIGURATION REPORT ** ENTER TO CONTINUE * Press the space bar on the terminal. returns the following message: TIME 0O:nn:nn (where ‘n’ is a digit, O-9) a bus error is likely to occur. The system returns a bus error indicating that the active Main Control is ready for Any commands entered at the Maintenance Terminal after this point require the Maintenance Terminal RETURN key be pressed. Any command entered hereafter is assumed to be terminated this way. message on the Maintenance Terminal, including the address at which the fault occurred. Note the address and refer to Practice 9125-06%352-NA, Maintenance Messages, to determine which RAM card is faulty. Replace the riate card and restart this from step 3 before completed, check that the display returns to a flashing “11” indication. 10. Enter the following command: Enables the printing of error tables for each test executed, in long EPRINTL form (detailed tables). See Appendix A., Table A2-6, for an example. 11. Go to Chart 4-4 for commissioning tests. Page 2 of 2 9125-060-204-NA Issue 1 Revision 0 204 4-7

Commissioning Control and Peripheral Card Tests 4.3 The following chart details the steps required to perform Control and Peripheral Interface card tests on Plane A of an SX-2000 S system. Chart 4-4 SX-2000 S ICS Plane A Control and Peripheral Interface Card Tests SW Actlon Comments 1. Enter the following commands to enable testing of the mass storage devices: EXTERNAL ON HDM ON Enable external device testing; Enable HDM testing; MHDM ON Enable mate HDM testing. EXTERNAL ON test is not possible if the write protect tab is in place on the diskette or if the RECORD tab is not in the RECORD position on the cartridge tape. By default, testing of mass storage devices is disabled. Any of these commands can be individually entered to enable testing of a specific mass storage device. Testing of mass storage devices is disabled by issuing one of the following commands, as appropriate: EXTERNAL OFF HDM OFF MHDM OFF 2. Enable testing of the Main and Peripheral Control Subsystems by entering: STEST ETEST l-20 This enables testing of all cards in slots 1 through 20 on the current shelf, both Control cards and PICs. The mass storage subsystem tests are run when the slot 20 tests are run. 3. Set the number of test passes to 1 by entering the Optional: the default number of following command: passes is 1. PASS 1 4. Start the test by entering: If the external device is a CTU the TEST test will take approximately 30 If a slot passes the tests, the system responds with: minutes to complete. 0O:OO:OO 000 TEST COMPLETE - NO ERRORS ON Tests are executed from the lowest SLOT NUMBER xx (shelf number) (cabinet number) to the highest slot. (test number) (pass number) If errors are detected, error and proceeds to test the next slot. messages are returned. Refer to the Appendices for the messages which may be encountered. Page 1 of 3 204 4-6 Revision 0 9125-060-204-NA Issue 1

m Id SX-2000 S ICS Commissioning Chart 4-4 SX-2000 S ICS Plane A Control and Peripheral Interface Card Tests (continued) rrors on an message 1s returne external device appear against the 152 CARD NOT DETECTED - NO TEST RUN 17 Main Controller test. (shelf number) (cabinet number) (test number) (pass If a CR-II or CSM-II card or a PIC fails a test, reinsert the failed card, and rerun the test on that slot by issuing the following command: 153 NO TEST AVAILABLE FOR THIS SLOT TEST (slot number) These messages may be disregarded, since there is If the card in question fails again, no testing available for any DSUs using Commissioning software. If the Main Controller must be replaced, the system must be restarted as described in The system returns the following prompt, indicating that Plane B is ready for testing: If a Peripheral Switch Controller card is installed in Shelf 2 of the Control Cabinet, enter the following command to test it: The Plane B Peripheral Switch Controller Card is only installed on fully redundant systems. If full redundancy is not provided If the card passes the test, the system returns the on the system being following message: commissioned, go to step 7. 0O:OO:OO 000 TEST COMPLETE - NO ERRORS ON Accessing Shelf 2 as a peripheral SLOT NUMBER 16 01 02 (test number) (pass shelf does not allow testing of the other control cards (slots 17-20). Suppress all previous testing. Enable testing of slots 1 - 12. Test cards in slots 1 - 12. to the next slot. messages are returned. Reinsert the card and test again. Replace Paae 2 of 3 9125-060-204-NA Issue 1 Revision 0 204 4-9

Commissioning Chart 4-4 SX-2000 S ICS Plane A Control and Peripheral Interface Card Tests (continued) SW Action Comments a. If one or more Peripheral Cabinets is provided then To enable testing in another repeat steps 6 and 7 for each shelf in each peripheral cabinet, enter the command: cabinet. SHELF (cabinet number), (shelf number) 9. Type “SHELF” to return to the prompt. Test all of the circuit switch links from the main control to all of the peripheral shelves by entering the following command: TEST CIR LINKS 10. If Main Control redundancy is provided, go to Chart 45. If the system is a non-redundant configuration, go to Chart 4-6. Page 3 of 3 load And Test Plane B And Mate links 4.4 Loading and testing of Plane B and its associated mate links on the SX-2000s system is performed as described in the following chart. This procedure does not apply to the not-t-redundant SX-2000s system since it only has one plane (Plane A). ! Chart 4-5 SX-2000 S ICS Load and Test Plane B and Control Mate Links step Action Comments 1. On completion of the self-test, disconnect the Maintenance Terminal from the TERMINAL A port on the Maintenance Connector’s panel and connect it to the TERMINAL 8 port. 2. Press and hold the PANEL ENABLE button on the Maintenance Panel. Press the ACTIVITY SWITCH button. Plane B is now active, and Plane A is inactive. 3. Hold down the PANEL ENABLE button and press the Commissioning software is loaded PLANE B LOAD button. onto the Plane B Main Controller from the external device. - Page 1 of 3 204 4-10 Revision 0 9125-060-204-NA Issue 1

m IA SX-2000 S ICS Commissioning Chart 4-5 SX-ZUOU S ICS Load and Test Plane B and Control Mate Links (continued) owing message: SX-2000 (small) COMMISSIONING IN PROGRESS (Date and name of load is output) TIME: 0O:OO:OO CONFIGURATION REPORT NOW BEING ETEST l-20 Suppress all previous testing. MATE LINK ON test, Commissioning must be running and a maintenance terminal must be connected to both To disable the test, issue the command: MATE LINK OFF 10. Test the Peripheral Mate Links in the first cabinet by It is not necessary to have both issuing the following commands: main control planes since both peripheral processors are PERMATE LINK ON controlled by the active main TEST 16 processor. 11. Enter the following command to enable testing of Shelf 2 of the Control Cabinet: SHELF 1,2 The system responds with: Page 2 of 3 9125-060-204-NA Issue 1 Revision 0 204 4-11

Commissioning Chart 4-5 SX-2000 S ICS Load and Test Plane B and Control Mate Links (continued) Step Action Comments 12. Test the Plane B Peripheral Switch Controller card by entering the following command: TEST 16 If the card passes the test, the system returns the following message: 0O:OO:OO 000 TEST COMPLETE - NO ERRORS ON SLOT NUMBER 16 01 02 (test number) (pass number) and then returns the peripheral prompt. 13. Begin testing of PlCs on Shelf 2 by entering: STEST Suppress all previous testing. ETEST 1-12 Enable testing of slots 1 - 12. TEST Test cards in slots 1 - 12. If the card passes the test, the system returns the following message: 0O:OO:OO 000 TEST COMPLETE - NO ERRORS ON SLOT NUMBER xx (cabinet number) (shelf number) If errors are detected, error (test number) (pass number) messages are returned. Reinsert the card and test again. Replace and the system proceeds to the next slot. any cards which fail the second test. 14. If one or more peripheral cabinets is provided, then repeat steps 11 to 13 for each shelf in each peripheral cabinet. 15. After all peripheral cabinets are tested, disable the peripheral mate link tests, by issuing the command: PERMATE LINK OFF 16. Go to Chart 4-6. Page 3 of 3 204 4-12 Revision 0 9125-060-204-NA Issue 1

m IA SX-2000 S ICS Commissioning Maintenance Panel Commissioning 4.5 The following chart provides details on commissioning a maintenance panel on an SX-2000 S system. Chart 4-6 SX-2000 S Maintenance Panel Commissioning TIVE plane on the Maintenance Connector The system delivers the following message: SYS ID MODULE PRESENT Visual led test: Minor, Major, Criiical, All ON, OFF Perform the following visual checks: l Minor ALARM LED comes on and goes off. 0 Major ALARM LED comes on and goes off. l Critical ALARM LED comes on and goes off. fro:Plane A in non-redundant mber) (cabinet number) SHOW PANEL TERMINAL port on the Maintenance Connector panel on the bottom rear of the Control Cabinet. Repeat steps 2 through 4. Page 1 of 2 9125-060-204-NA Issue 1 Revision 0 204 4-13

Commissioning Chart 4-6 SX-2000 S Maintenance Panel Commissioning (continued) Step I Action Comments I 6. Remove the commissioning diskette/tape from the external device. 7;, Hardware commissioning is now complete. Refer to Practice 9121-06&200, Installation, for software installation. Page 2 of 2 I 204 4-14 Revision 0 912!3-060-204-NA Issue 1