    Have a look at the manual Mitel Sx-2000 Integrated Communications System Control Sheet Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 55 Mitel manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    Page
    of 526
    							SX-2000 SG ICS Commissioning 
    load and Test Plane B and Mate links 
    Loading and testing of Plane B and its associated mate links on the SX-2000 SG 
    system is performed as described in the following chart. 
    Chart 54 Load and Test Plane B and Control Mate Links 
    Maintenance Terminal from the TERMINAL A port on 
    ector panel and connect it to the 
    press the PLANE B LOAD SOURCE button. 
    following message: The SX-2000 SG system has 
    the following load sources: 
    LOAD SOURCE 1 -hard disk 
    LOAD SOURCE 2 -flo 
    SX-2000 COMMISSIONING IN PROGRESS 
    (Date and name of load is output) 
    TIME: 0O:OO:OO 
    CONFIGURATION REPORT NOW BEING 
    The configuration report is followed by the prompt: 
    ENTER SPACE TO CONFIG PERIPHERALS,  TO 
    RETURN TO COMMAND MODE> 
    Press the terminal space bar. 
    The system responds with: 
    Refer to Appendix A., 
    PERIPHERAL SWITCH HARDWARE Table A2-3, for an example of a 
    CONFIGURATION IN PROGRESS peripheral and DSU 
    configuration report. 
    Page 1 of 2 
    9125-060-204-NA Issue 1 Revision 0 204 5-11  
    						
    							Commissioning 
    Chart 5-5 Load and Test Plane B and Control Mate Links 
    (continued) 
    Step Action Comments 
    6. Enable long-form printing of messages by issuing the See Appendix A., Table A2-8, for 
    EPRINTL command at Maintenance Terminal when the 
     prompt appears. an example of the EPRINTL 
    command output. 
    7. Test Plane B Control Cards by issuing the following 
    commands: 
    STEST 
    ETEST 1-25 
    TEST Suppress all previous testing. 
    Enable testing of slots 1 - 25. 
    Test cards in enabled slots. 
    a. If errors occur during testing of any slot, remove and 
    reinsert the card and retest. Replace any cards which 
    fail the second test. 
    9. Test the main control mate links by issuing the following To run the main control mate link 
    commands on both planes simultaneously: test, Commissioning must be 
    running and a maintenance 
    MATE ON terminal must be connected to 
    TEST 8 both planes at once. 
    To disable the test, issue the command: 
    MATE OFF 
    10. Test the Peripheral Mate Links in the first cabinet by It is not necessary to have both 
    issuing the following commands: main control planes since both 
    peripheral processors are 
    SHELF 1,3 controlled by the active main 
    PERMATE ON processor. 
    TEST 29 
    11. If one or more peripheral cabinets is provided, then 
    repeat step 10 for each shelf pair in each peripheral 
    cabinet. 
    12. After all peripheral cabinets have been tested, disable 
    the peripheral mate link test by issuing the command: 
    PERMATE OFF 
    13. Type “SHELF” to obtain “” prompt. 
    14. Go to Chart 5-6. 
    Page 2 of 2 
    204 5-12 
    Revision 0 9125-060-204-NA Issue 1  
    						
    							SX-2000 SG ICS Commissioning 
    Maintenance Unit Commissioning 
    5.6 Commissioning of the maintenance unit is performed on the SX-2000 SG system as 
    described in the following chart, 
    Note: In the following procedure, the terms ‘unit’ and ‘panel’ are interchangeable. 
    Chart 5-6 SX-2000 SG Maintenance Unit Commissioning 
    Connector panel on the Control Cabinet. Enzire that 
    the printer is on-line and ready to print. should be set for: 
    - 8 data biis 
    Maintenance Unit commissioning software is loaded 
    from the commissioning diskette. Once loaded, the 
    -the printer prints 20 lines of data. 
    -the MINOR ALARM LED turns ON, then OFF 
    -the MAJOR ALARM LED turns ON, then OFF. 
    -the REMOTE ALARM LED turns ON, then OFF. 
    -the following test message is scrolled across the 
    Maintenance Unit display: 
    -the Power Fail Transfer relays are operated. 
    -the fan speed is set to low, then high for each An audible click is heard as each 
    -when the tests are complete, the following 
    message appears on the Maintenance Terminal: 
    TEST COMPLETE, NO ERRORS ON SLOT 
    NUMBER (SLOT “), (SHELF *), (CAB 01)) 
    (TEST 00), (PASS 0001) If an error is detected, make note 
    of the error and refer to Practice 
    9125-060-35O-NA, 
    Troubleshooting. 
    Page 1 of 2 
    912!5-060-204-NA Issue 1 Revision 0 204 5-13  
    						
    							Commissioning 
    Chart 5-6 SX-ZUOU SG Maintenance Unit Commissioning 
    (continued) 
    Step 
    Action Comments 
    4. Enter the following command: Refer to Appendix A., Table A2-6, 
    for an example of the SHOW 
    SHOW PANEL PANEL display. 
    Check that the Maintenance Terminal displays the 
    status of the Maintenance Unit. 
    5. 
    Enter the following command: 
    SHOW PANEL N (Where N is the desired 
    maintenance unit number) 
    Check that the Maintenance Terminal displays the 
    status of the Maintenance Unit specified. 
    6. Switch activity to Plane A, connect the Maintenance Refer to Appendix A., Table A2-6 
    Terminal to the TERMINAL A port on the Maintenance for an example of the SHOW 
    Connector panel of the Control Cabinet, and repeat PANEL N display. 
    steps 2 through 5. 
    7. Remove the commissioning diskette from the Floppy 
    Disk Unit. 
    8. Hardware commissioning is now complete. Refer to 
    Practice 9120-060-200, Installation, for software 
    installation. 
    Page 2 of 2 
    204 5-14 
    Revision 0 9125-060-204-NA Issue 1  
    						
    							6 
    ’ SX-2000FD ICS 
    COMMISSIONING 
    Install Circuit Cards 
    Non-Redundant Control Node 
    6.1 
    Ensure that the Main Control cards and Fiber Interface Modules are installed in the 
    correct card slots before loading the commissioning software. Chart 6-1 describes 
    the card installation procedure for the Non-redundant Control Node of the SX-2ooo FD 
    system. The procedure for a Redundant Control Node is shown in the next chart, 
    Chart 6-2. 
    Chart 6-l Install Circuit Cards in the SX-2UOU FD ICS Non-Redundant Control Node 
    l Main Controller II Card: Shelf 1, Slot 1 
    * Control Resource Card: Shelf 1, Slot 2 
    l Fiber Interface Modules: Shelf 2, Slots l-4, as 
    card does not begin self-test, or if 
    errors are indicated on the numeric 
    display, reinsert the card. Reset 
    the MC II card by pressing PANEL 
    ENABLE and RESET A on the 
    Maintenance Panel. If the card 
    fails self-test a second time, 
    912!5-060-204-NA Issue 1 Revision 0 204 6-l  
    						
    							Commissioning 
    Redundant Control Node 
    Ensure that the Main Control cards and Fiber interface Modules are installed in the 
    correct card slots before loading the commissioning software. 
    Chart 6-2 describes the 
    card installation procedure for the Redundant Control Node. 
    Chart 6-2 Install Circuit Cards in the SX-2000 FD ICS Redundant Control Node 
    Step Action Comments 
    1. Ensure the following cards are installed in the Control Refer to Figure 6-l. 
    Node: 
    l Plane A Main Controller II Card: Shelf 1, Slot 2 
    l Plane A Control RAM II Card: Shelf 1, Slot 3 
    l Plane A Circuit Switch Matrix II Card: Shelf I, Slot 4 
    l Plane B Circuit Switch Matrix II Card: Shelf 1, Slot 5 
    l Plane B Control RAM II Card: Shelf 1, Slot 6 
    l Plane B Main Controller II Card: Shelf 1, Slot 7 
    l Control Resource Card: Shelf 1, Slot 8 
    l Fiber Interface Modules: Shelf 3, Slots I-II, 
    as required 
    2. Apply power to the Control Node by setting the two 
    PSU power switches on the node backplate to ON. 
    3. Check that the Main Controller II (MC II) cards and If an MC II or Control Resource 
    the Control Resource card begin power-up self tests. card does not begin self-test, or if 
    errors are indicated on the numeric 
    display, reinsert the card. Reset 
    the MC II card by pressing PANEL 
    ENABLE and RESET A (or RESET 
    B for the Plane B MC II card) on 
    the Maintenance Panel. If the card 
    fails self-test a second time, 
    replace it. 
    Power-up self tests are only 
    performed when power is first 
    applied to installed cards. 
    4. Proceed to Chart 6-3 for installation of cards in the 
    Peripheral Node(s). 
    204 6-2 Revision 0 9125-060-204-NA Issue 1  
    						
    							r 
    m IA 
    SX-2000 FD ICS Commissioning 
    Peripheral Nodes 
    Ensure that the Peripheral Control cards, Peripheral Interface cards, and one Fiber 
    Interface Module are installed in the correct card slots in each Peripheral Node before 
    loading the commissioning software. Chart S--S describes the card installation 
    procedure for the Peripheral Node. 
    Chart 63 Install Circuit Cards in the SX-2000 FD ICS Peripheral Nodes 
    . Fiber Interface Module: Shelf 1, Slot 17 
    l Peripheral Resource Card: Shelf 2, Slot 17 
    ower switches on th 
    indicated on the numeric display, 
    reinsert the card. If the card fails 
    self-test a second time, replace it. 
    9125-060-204-NA Issue 1 Revision 0 204 6-3  
    						
    							Commissioning 
    DSU Nodes 
    Ensure that the Peripheral Resource cards, Digital Service Unit (DSU) cards, and Fiber 
    Interface Module(s) are installed in the correct card slots in each DSU Node before 
    loading the commissioning software. Chart 6-4 describes the card installation 
    procedure for the DSU Nodes, 
    Chart &4 Install Circuit Cards in the SX-2000 FD ICS Peripheral Nodes 
    Step Action Comments 
    1. Ensure that the following cards are installed in the first Refer to Figure 6-2. 
    DSU Node: 
    Leave all other cards (except filler 
    l Fiber Interface Module: Shelf 1, Slot 1 plates) uninstalled. 
    l Peripheral Resource Cards: Shelf 2, Slot 1 and 6 
    l Fiber Interface Module: Shelf 1, Slot 6 (optional) 
    2. Apply power to the DSU Node by setting the PSU 
    power switch on the node backplate to ON. 
    3. Check that the Peripheral Resource cards in each 
    node begin power-up self tests. If the Peripheral Resource card 
    does not begin self-test, or if errors 
    are indicated on the numeric 
    display, reinsert the card. If the 
    card fails self-test a second time, 
    replace it. 
    Power-up self tests are only 
    performed when power is first 
    applied to installed cards. 
    4. 
    Install DSUs in slots 2 to 5 (Shelf 1) of the DSU Node. 
    5. Repeat Steps 1 to 4 for each additional DSU Node. 
    6. 
    After circuit cards have been installed in all DSU 
    Nodes, the card installation process is completed. Go 
    to Chart 6-5 for instructions on loading 
    commissioning software onto Plane A of the SX-2000 
    FD system. 
    204 6-4 
    Revision 0 912!%060-204-NA issue 1  
    						
    							m IA 
    SX-2000 FD ICS Commissioning 
    SLOT 
    SLOT 
    SLOT 
    SLOT SHELF 1 
    I r-------. NON-REDUNDANT CONTROL NODE 
    SHELF2 
    1 
    2 3 4 
    -----________ SLOT 
    SHELF3 
    SHELF2 SHELF 1 
    ,-_____-_________ 
    _I , - - - - - - - _I ,_ _ _ _ _ 
    I 
    1 I 
    ’ I 
    ooco 
    1 
    2 3 4 
    oo[ll 
    5 6 7 6 
    mlFl REWNDANT CONTROL NODE 
    Figure 6-l SX-2000 FD Control Node Circuit Card Locations 
    9125-060-204-NA 
    Issue 1 Revision 0 204 6-5  
    						
    							Commissioning 
    SHELF2 SHELF 1 SHELF2 
    I 1 
    Bm.37 
    I I 
    SHELF1 
    ____-____---______--____________________--------------, 
    Figure G2 SX-2000 FD Peripheral and DSU Node Circuit Card Locations 
    204 6-6 
    Revision 0 9125-060-204-NA issue 1  
    						