Page 51

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading G3vs (w/Intel 386) to R8si 
1-25 Upgrade to Release 8si 
1
Figure 1-4. Exploded View of G3vs System
Return Replaced Equipment
1. Return replaced equipment to Lucent Technologies according to the 
requirements outlined in:
BCS/Material Logistics, MSL/Attended Stocking Locations
Methods and Procedures for Basic Material Returns
2. If the original translation card is not being used with the Release 8...

Page 52

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading G3vs (w/Intel 386) to R8si 
1-26 DEFINITY AUDIX Power Procedures 
1
DEFINITY AUDIX Power Procedures
If the AUDIX System is located in the DEFINITY cabinet, then follow these 
procedures.
Power Down the AUDIX System
A yellow caution sticker on the system’s power unit notifies technicians to shut 
down the DEFINITY AUDIX System prior to powering down the system.
1. Log into the AUDIX System as craft. 
2....

Page 53

Upgrading R5vs/R6vs to R8si 
2-1  
2
DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
2
Upgrading R5vs/R6vs to R8si
This chapter provides the information necessary to upgrade a G3vs with a TN790 
processor to a Release 8si. 
This upgrade requires replacing the existing cabinet with a new Single-Carrier 
Control Cabinet. The port circuit packs from the present system may be reused 
only if a site inspection determines that the port circuit pack vintages are...

Page 54

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-2 Read This First 
2
Read This First
Service Interruption
The upgrade process for a standard reliability system requires a service 
interruption. Coordinate the service interruption with the customer and the local 
account team.
Call Management System (CMS)
The CMS link is dropped and restarted during the upgrade. This causes CMS 
data to be lost. This data loss can be minimized if...

Page 55

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-3 Read This First 
2
Between customer confirmation and the actual update or upgrade, check the 
screens to ensure the translations meet the customer’s needs. After rebooting the 
system, enter the translations either locally or remotely. If done remotely, Contact 
Field Support Administration Center (FSAC) for the remote entry. For information 
to make the required changes, refer...

Page 56

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-4 Read This First 
2
Required Hardware
The equipment in Table 2-1 must be on-site before the upgrade begins. To place a 
claim for missing equipment, as part of the Streamlined Implementation process, 
call 1-800-772-5409, or the number provided by your Lucent Technologies 
representative.
Table 2-1. Required Hardware
Equipment Description Quantity
J58890L-1 L5 Single Carrier Control...

Page 57

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-5 Read This First 
2
Table 2-2. Carriers that use the TN794 NetCon circuit pack
DEFINITY R7.1 or later 
Carrier/Backplane Equipment Notes
SCC Processor Cabinet J58890L-2 List 25 This replaces List 10 
SCC Processor Cabinet 
(Survivable Remote)J58890L-2 List 31 This replaces List 30 
SCC Processor Cabinet (Knock 
Down)J58890L-2 List 52 This replaces List 51 
Backplane for the...

Page 58

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-6 Task Table 
2
Ta s k  Ta b l e
Table 2-3 provides the high-level tasks to perform the upgrades. Refer to the 
appropriate page for instructions for each step.
Table 2-3. Tasks to Upgrade to Release 8si
áTask Description Page
Unpack and Inspect Control Cabinet2-7
Install Control Cabinet2-8
Add Earthquake Protection2-8
Label Existing Cables2-8
Install TDM/LAN Bus Terminators2-9
Swing...

Page 59

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-7 Upgrade to Release 8si 
2
Upgrade to Release 8si
Unpack and Inspect Control Cabinet 
1. Unpack J58890L-1 L5 Single-Carrier Control Cabinet  and verify  comcode 
vintage of the control carrier.
!CAUTION:
Take care to avoid injury while cutting and removing bands.
NOTE:
Verify the vintage of the control carrier and check it against Table 2-2. 
If your carrier is NOT listed, you need...

Page 60

DEFINITY ECS Release 8.2
Upgrades and Additions for R8.2si  555-233-122  Issue 1
April 2000
Upgrading R5vs/R6vs to R8si 
2-8 Upgrade to Release 8si 
2
Install Control Cabinet
1. Position the control cabinet at the desired location (as close to the Main 
Distribution Frame [MDF] as possible).
!CAUTION:
The cabinet may weigh as much as 130 pounds (58 kg). Use lifting 
precautions to avoid injury.
2. If earthquake protection is not required, install hole plugs (provided with 
cabinet) in the holes...
Start reading Lucent Technologies DEFINITY Enterprise Communication Server Release 8.2 Upgrades And Additions Manual

Related Manuals for Lucent Technologies DEFINITY Enterprise Communication Server Release 8.2 Upgrades And Additions Manual

All Lucent Technologies manuals