Page 31
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-5 Read This First 1 Table 1-2. Carriers that use the TN794 NetCon circuit pack DEFINITY R7.1 or later Carrier/Backplane Equipment Notes SCC Processor Cabinet J58890L-2 List 25 This replaces List 10 SCC Processor Cabinet (Survivable Remote)J58890L-2 List 31 This replaces List 30 SCC Processor Cabinet (Knock Down)J58890L-2 List 52 This replaces List 51 Backplane for the...
Page 32
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-6 Task Table 1 Ta s k Ta b l e Table 1-3 lists the high-level tasks to perform the upgrades. Refer to the appropriate page for instructions for each step. Table 1-3. Tasks to Upgrade to Release 8si áTask Description Page Unpack and Inspect Control Cabinet1-7 Install Control Cabinet1-8 Add Earthquake Protection1-8 Label Existing Cables1-8 Install TDM/LAN Bus...
Page 33
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-7 Upgrade to Release 8si 1 Upgrade to Release 8si Unpack and Inspect Control Cabinet 1. Unpack the J58890L-1 L5 Single-Carrier Control Cabinet and verify comcode vintage of the control carrier. !CAUTION: Take care to avoid injury while cutting and removing bands. NOTE: Verify the vintage of the control carrier and check it against Table 1-2. If your carrier is NOT...
Page 34
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-8 Upgrade to Release 8si 1 Install Control Cabinet 1. Position the control cabinet at the desired location (as close to the Main Distribution Frame [MDF] as possible). !CAUTION: The cabinet may weigh as much as 130 pounds (58 kg). Use lifting precautions to avoid injury. 2. If earthquake protection is not required, install hole plugs (provided with cabinet) in the holes...
Page 35
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-9 Upgrade to Release 8si 1 Figure 1-1. Location of TDM/LAN Bus Terminators Swing Existing System into Maintenance Position 1. While lifting on the left side of the existing cabinet, allow the left side to swing outward and to the right. Check SPE Ty p e status system 1 and press En te r to check the health of the system. Disable Scheduled Maintenance and Alarm...
Page 36
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-10 Upgrade to Release 8si 1 If scheduled maintenance has not begun, set the Start Time field to a time after the upgrade is completed. For example, if you start the upgrade at 8:00 p.m. and the upgrade takes 90 minutes, set the Start Time field to 21:30. !CAUTION: If you do not disable Alarm Origination, the system may generate alarms, resulting in unnecessary trouble...
Page 37
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-11 Upgrade to Release 8si 1 Save Translations 1. Type save translation and press En t e r to write all translation information from memory to the original translation flashcard, which takes about 10 minutes. When the save translations command is successful, the error code must be a zero; otherwise, the translations are not copied. If the translations were corrupted,...
Page 38
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-12 Upgrade to Release 8si 1 7. For each link where the Prot field is set to ISDN, set the Enable field to n and press En t e r. 8. Type display communication-interface processor-channels and press En t e r. 9. For each processor channel where the Application field is set to ISDN, record the information in all fields (in case you need to back out of the upgrade). 10....
Page 39
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-13 Upgrade to Release 8si 1 2. If administered recorded announcements are listed, type save announcements cabinet carrier slot and press En te r. For example, 01 D03. This takes about 30 minutes. NOTE: For some software loads, type save announcements from cabinet carrier slot . Type help and press En t e r for complete command syntax. Verify Software Version If...
Page 40
DEFINITY ECS Release 8.2 Upgrades and Additions for R8.2si 555-233-122 Issue 1 April 2000 Upgrading G3vs (w/Intel 386) to R8si 1-14 Upgrade to Release 8si 1 Power Down Existing System !CAUTION: Powering down the control cabinet causes important system data, such as BCMS data, records of queued ACD calls, Automatic Wakeup request, and Do Not Disturb requests, to be lost. 1. Behind the G3vs cabinet, set the circuit breaker to OFF. See Figure 1-2 . Figure 1-2. Rear of G3vs System Cabinet Figure...