Page 91
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-19 Release 5/6si to Release 8r 3 Figure 3-3. TDM/LAN Connections for Release 5/6si EPN Figure Notes 1. AHF110 TDM LAN/Bus Terminator 2. Slot 17 3. TDM/LAN Cab le (WP91716 L3) 4. Slot 00 5. Slot 036. Slot 18 7.J58890H Port Cab inet (“ D” Po si t io n ) 8. J58890H Port Cab inet (“ C” Po si t io n ) 9. J58890H Port Cab inet (“ B”...
Page 92
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-20 Release 5/6si to Release 8r 3 Connect TDM/LAN Cables and ICC Cables 1. Route and c onnec t the TDM/LAN c ab les. If any of the Release 5/6si p ort c ab inets (b eing up g rad ed to Release 8r c ab inets) were orig inally R1V3 p ort c ab inets, use the following step s to route a c ab le b etween an R1V3 up p er c ab inet and...
Page 93
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-21 Release 5/6si to Release 8r 3 Figure 3-4. ICC Pinfield Blocks on J58890N Expansion Control Cabinet Figure 3-5. ICC Pinfield Blocks on J58890H Port Cabinet 114 25 12 24 00 00 20 19 20 19 0 3 2 1 2 1 2 1 ICCB ICCA TERM CURL Pinfield 5.00 4.006.00 0 3 2 100 3.00 24 2.001.00 0.00 ICCB ICCA
Page 94
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-22 Release 5/6si to Release 8r 3 Interconnect Port Networks with Fiber Optic Cabling — Standard Reliability Release 8r After all fib er op tic eq uip ment is installed , refer to Chapter A, ‘‘Fiber Link Administration’’. 1. Keep trac k of whic h fib er attac hes to whic h c onnec tor on eac h lig htwave transc eiver. Lab el every c...
Page 95
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-23 Release 5/6si to Release 8r 3 DS1 CONV-Remoted Port Networks For a stand ard reliab ility system with 1 DS1 CONV-remoted EPN, use 2 DS1 CONV c irc uit p ac ks (TN1654), 2 DS1 Conv-to-EI c ab les (846448637 and /or 846448645), two H-600-348 c ables, from 1 to 4 p airs of Channel Servic e Units (CSUs), and from 1 to 4 p airs of...
Page 96
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-24 Release 5/6si to Release 8r 3 2. Behind control cabinet A of EPN stack 2: a. Install a lig htwave transc eiver on the c onnec tor at slot 2A01. b . Connec t the other end of the fiber op tic c able from the PPN to the lig htwave transc eiver at slot 2A01. c . Carefully attac h the fib er op tic c ab le (with c ab le ties) to the...
Page 97
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-25 Release 5/6si to Release 8r 3 Figure 3-7. Typical Fiber Optic Connections For 1 or 2 Fiber-Remoted Expansion Port Networks 1. Behind p ort c arrier B of the multic arrier PPN. See Figure 3-6 and Figure 3-8: a. Install a lig htwave transc eiver on the c onnec tor at slot 1B02. NOTE: Attenuators may be required for single mode...
Page 98
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-26 Release 5/6si to Release 8r 3 2. Behind control cabinet A of EPN stack 2: a. Install a lig htwave transc eiver on the c onnec tor at slot 2A01. b . Connec t a fib er op tic c ab le to the transc eiver just installed . c . Route the c ab le d own the outsid e of the rear c overs and throug h the c ab le manag er to the PDS c ross-c...
Page 99
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-27 Release 5/6si to Release 8r 3 Interconnect Port Networks with Fiber Optic Cabling — High Reliability Release 8r 1. Keep trac k of whic h fib er attac hes to whic h c onnec tor on eac h lig htwave transc eiver. This sec tion p rovid es fig ures showing typ ic al ways of making these c onnec tions. The c onnec tors on the...
Page 100
DEFINITY Enterprise Communications Server Release 8.2 Upgrades and Additions for R8r 555-233-115 Issue 1 April 2000 Upgrading R5si/R6si to R8r EPN and Adding Memory 3-28 Release 5/6si to Release 8r 3 For a high reliab ility system with 2 DS1 Conv-remoted exp ansion p ort networks, this arrang ement req uires: n6 DS1 Converter c irc uit p ac ks (TN1654) n6 DS1 Converter-to-EI c ab les (846448637 and /or 846448645) n6 H-600-348 c ab les n3, 6, 9, or 12 p airs of CSUs n3, 6, 9, or 12 p airs of...