Here you can view all the pages of manual Lucent Technologies DEFINITY Enterprise Communication Server Release 8.2 Installation And Test For Multi-Carrier Cabinets Manual. The Lucent Technologies manuals for Communications System are available online for free. You can easily download all the documents as PDF.
Page 21
Install and Connect Cabinets 1-1 Unpack and Inspect Cabinets 1 DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 1 Install and Connect Cabinets This c hapter d isc usses installation of Multic arrier Cab inets only. For information on Sing le-Carrier Cab inets, refer to DEFINITY Enterp rise Communic ations Server Release 8 Installation and Test for Sing le-Carrier Cab inets. Floor p lans and eq uip ment layouts for typic al system...
Page 22
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-2 Check Customer’s Order 1 Unpack and Inspect Auxiliary Cabinet The Auxiliary c ab inet is normally p ositioned ad jac ent to the PPN c ab inet or the EPN c ab inet, if p rovid ed. 1. Unp ac k the c ab inets as outlined on the p revious p ag e. 2. Remove the lower rear p anel from the Auxiliary c ab inet. Install the lower rear panel when the installation is c...
Page 23
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-3 Install System Cabinets 1 Install System Cabinets Chec k the loc ation of the AC p ower rec eptac les in the eq uip ment room. The rec ep tac les must b e on a separately fused circuit not controlled b y a wall switch. They must b e loc ated within 10 ft (3 m) of the c ab inet and outsid e the Main Distrib ution Frame (MDF) area. Position the PPN Cabinet 1....
Page 24
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-4 Install System Cabinets 1 Position the Auxiliary Cabinet (Optional) 1. Position the Auxiliary c ab inet next to the PPN c abinet (or EPN c ab inet, if installed ). The loc ation of eq uip ment inside the Auxiliary c ab inet is sp ec ified in the Customer Servic e Doc ument (CSD). 2. If earthquake p rotec tion is req uired , skip to ‘‘ Earthq uake Protec tion...
Page 25
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-5 Install System Cabinets 1 The BLD1 c irc uit p ac k p rovid es 8 c hannels with up to 20 sec ond s of rec ord ing time on eac h c hannel. The BLD2 c irc uit p ac k provid es 8 c hannels with up to 40 sec ond s of rec ording time on eac h c hannel. Eac h c hassis c an b e p op ulated with any c omb ination of 2 BLD c irc uit p ac ks. The Model 15A Announc...
Page 26
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-6 Connect AC Power and Ground 1 Connect AC Power and Ground Power Requirements Tab le 1-2 shows the p ower req uirements. J58890CE-1, J58890CE-2, and J58890CH-1 The following proc ed ures app ly to the AC-powered PPN and EPN c ab inets. Either of the following p ower sourc es c an supp ly 60 Hz p ower to the AC load in Release 5 and later systems: nSing le-p...
Page 27
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-7 Connect AC Power and Ground 1 Tab le 1-3 describes the power sources and required AC input power. NOTE: The typ e of p ower req uired is shown on the c ab inet’s rear d oor. !CAUTION: The eq uip ment room AC power and ground wiring must b e p erformed b y a q ualified elec tric ian. Refer to DEFINITY Enterp rise Communic ations Server Release 8 System Desc...
Page 28
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-8 Connect AC Power and Ground 1 Connect Ground to AC-Powered System (J58890CE) Ground ing is relatively simp le for an AC-p owered system. Basic ally, the c ab inets c onnec t to the sing le-p oint g round terminal bloc k loc ated at either the AC load c enter or to a separate sing le-point g round b loc k wired to the AC load c enter (or op tional AC p...
Page 29
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-9 Connect AC Power and Ground 1 Figure 1-1. Typical Cabinet Ground Location 5. Rep eat c onnec ting eac h EPN c ab inet to the sing le-p oint g round bloc k. 6. At the AC load c enter, c onnec t a 10 AWG (#25) (6 mm 2) wire to the sing le-p oint g round b loc k. This g round wire will later b e tie-wrap p ed to the trunk c ab les and c onnec ted to the...
Page 30
DEFINITY ECS Release 8.2 Installation and Test for Multi-Carrier Cabinets 555-233-114 Issue 1 April 2000 Install and Connect Cabinets 1-10 Connect AC Power and Ground 1 AC Load Center is More Than 50 ft (15.2 m) from Cabinet 1. Mount the sing le-p oint ground b loc k to any surfac e b etween the MCC c ab inets and the AC load c enter sing le-p oint g round . The sing le-p oint g round b loc k must b e mounted to a non-metallic surfac e. 2. At the bottom rear of the PPN c ab inet, c onnec t a...