GE F650 Manual
Here you can view all the pages of manual GE F650 Manual. The GE manuals for Controller are available online for free. You can easily download all the documents as PDF.
Page 191
CHAPTER 6: COMMISSIONING6.17 RECLOSER (79) GEK-113000-AFF650 DIGITAL BAY CONTROLLER 6-23 6.17.2 Recloser status BLOCK Activate the block input and verify that the recloser is in BLOCK status. Close the breaker and wait for 5 seconds. Command a trip and verify that the breaker opens but there is no reclose. INHIBITION BY RECLOSING CONDITIONS Close the breaker and wait for 5 seconds. Command a trip, verify that the breaker opens and wait for the first shot. Activate the inhibition input and command a new...
Page 192
6-24F650 DIGITAL BAY CONTROLLER GEK-113000-AF 6.18 THERMAL IMAGE ELEMENT (49) CHAPTER 6: COMMISSIONING 6.18 Thermal image element (49) Disable all protection elements except for Thermal Model (49). Set the pickup level to 2 A. Set the time constant t1 to 3 minutes and t2 to one time t1. Apply currents of 2, 5, and 10 times the tap and ensure that the operation times are within the range described on the following table: After each measuring, the thermal element must be reset to zero in order to start...
Page 193
GEK-113000-AFF650 DIGITAL BAY CONTROLLER 7-1 F650 Digital Bay Controller Chapter 7: Frequently asked questions GE Grid Solutions FREQUENTLY ASKED QUESTIONS 7.1 Communications Q1. Does the F650 support DNP and ModBus over the Ethernet port? A1. F650 units support both protocol s over both the asynchronous serial ports and the Ethernet LAN synchronous port using TCP/IP and UDP/IP la yers over the Ethernet. Q2. Does this equipment support dual IP access? A2. Yes, it supports two independent IP...
Page 194
7-2F650 DIGITAL BAY CONTROLLER GEK-113000-AF 7.1 COMMUNICATIONS CHAPTER 7: FREQUENTLY ASKED QUESTIONS Q7. How many different communication Ethernet sessions can be opened through the LAN port? A7. ModBus TCP/IP:4 sockets DNP TCP/IP:3 sessions (from version 1.72 on) Q8. May I use the cooper 10/100 BaseTX connection included in the basic model with all protocols? A8. Yes, it may be used with all protocols. In noisy substation en vironments and/or long distances, it is recommended to use f iber optic...
Page 195
CHAPTER 7: FREQUENTLY ASKED QUESTIONS7.2 PROTECTION GEK-113000-AFF650 DIGITAL BAY CONTROLLER 7-3 A17. The cable has some advantages that the f iber does not have, and it is that the signal attenuation in short and medium distances, is worthless and this is truth for low and high frequency signals. By the contrary, the light in one f iber optic is highly attenuated, being much worse in case of high frequenc ies than in the low ones. The 10-BASE-FL f iber transmission is performed in a wavelength of...
Page 196
7-4F650 DIGITAL BAY CONTROLLER GEK-113000-AF 7.3 CONTROL & HMI CHAPTER 7: FREQUENTLY ASKED QUESTIONS 7.3 Control & HMI Q1. What is the difference between Get/Send info from/to relay and Upload/Download info files to/from relay? A1. Get/Send are used for settings and configuration storage that al though both are in a unique file, are sent separately in two times. Upload/Download are used for projec t or PLC files group storage. These files are the setting_configuration file source. To operate, the...
Page 197
CHAPTER 7: FREQUENTLY ASKED QUESTIONS7.4 RELAY CONFIGURATION GEK-113000-AFF650 DIGITAL BAY CONTROLLER 7-5 7.4 Relay conf iguration Q1. Does the Service contact on the Power Supply board cover all possible failures or do I have to create an output on the I/O board that includes all the internal errors I can access in the logic? A1. The power supply ready contact only monitor hardware failur es i n the power supply, to monitor the internal error of the unit it is necessary to configure a virtual...
Page 198
7-6F650 DIGITAL BAY CONTROLLER GEK-113000-AF 7.4 RELAY CONFIGURATION CHAPTER 7: FREQUENTLY ASKED QUESTIONS
Page 199
GEK-113000-AFF650 DIGITAL BAY CONTROLLER 8-1 F650 Digital Bay Controller Chapter 8: F650 troubleshooting guide GE Grid Solutions F650 TROUBLESHOOTING GUIDE 8.1 Symptoms and recommended actions F650 units have been designed and verified using the most advanced and reliable equipment. Mounting and testing automation ensure a high consistency of the final product. Before sending a unit back to the factory, we strongly suggest you follow the recommendations below. These actions may solve the problem,...
Page 200
8-2F650 DIGITAL BAY CONTROLLER GEK-113000-AF 8.1 SYMPTOMS AND RECOMMENDED ACTIONS CHAPTER 8: F650 TROUBLESHOOTING GUIDE Ge n e r a l When feeding the unit , no indicator is lit up -Insufficient power supply - Wrong versions -Fuse failure - Loose fuse -Incorrect wiring -Verify the voltage level using a multi meter in the power supply terminals, and check that it is within the model range -Check relay and ENERVISTA 650 Setup v ersions are the same -Remove power supply, dismount the pow er supply...
All GE manuals