Page 201
NEAX2000 IVS2 ISDN System ManualPage 190 ND-70919 (E), Issue 1.0 CHAPTER 5 OPERATION TEST Interoffice Transmission Line Test INTEROFFICE TRANSMISSION LINE TEST To confirm inter-office synchronization and speech quality using “In-Service” transmission lines, do the following procedure: STEP 1: Connect the transmission line to the MDF or CONN card. STEP 2: Make busy the channels except the channel tested by CME5. STEP 3: Confirm indication lamps on the DTI/PRT/BRT card, as per the following table. ...
Page 202
CHAPTER 5 OPERATION TEST Interoffice Transmission Line Test NEAX2000 IVS2 ISDN System Manual ND-70919 (E), Issue 1.0 Page 191 Table 5-1 Alarm Indications on 24DTI LEDLED INDICATION FAULT NORMAL FAULT CAUSE ACTION RU N F la s h (120 IPM)On or Off Abnormal operation of DTI cardConfirm the programming data: CM05, CM07 YY=01. Check to see if the SENS switch is set as per the AP number (04-15, 20-31) assigned by CM05. Reset the MB switch (Down→Up→Down) If the fault cannot be cleared, replace...
Page 203
NEAX2000 IVS2 ISDN System ManualPage 192 ND-70919 (E), Issue 1.0 CHAPTER 5 OPERATION TEST Interoffice Transmission Line Test Table 5-2 Alarm Indications on 30DTI LEDLED INDICATION FAULT NORMAL FAULT CAUSE ACTION RU N F la s h (120 IPM)On or Off Abnormal operation of DTI cardConfirm the programming data: CM05, CM07 YY=01. Check to see if the SENS switch is set as per the AP number (04-15, 20-31) assigned by CM05. Reset the MB switch (Down→Up→Down) If the fault cannot be cleared, replace the...
Page 204
CHAPTER 5 OPERATION TEST Interoffice Transmission Line Test NEAX2000 IVS2 ISDN System Manual ND-70919 (E), Issue 1.0 Page 193 Table 5-3 Alarm Indications on 24PRT LEDLED INDICATION FAULT NORMAL FAULT CAUSE ACTION RU N F la s h (120 IPM)On or Off Abnormal opera- tion of PRT cardConfirm the programming data: CM05, CM07 YY=01. Check to see if the SENS switch is set as per the AP number (04-15, 20-31) assigned by CM05. Reset the MB switch (Down→Up→Down) If the fault cannot be cleared, replace...
Page 205
NEAX2000 IVS2 ISDN System ManualPage 194 ND-70919 (E), Issue 1.0 CHAPTER 5 OPERATION TEST Interoffice Transmission Line Test Table 5-4 Alarm Indications on BRT LEDLED INDICATION FAULT NORMAL FAULT CAUSE ACTION BRT RU N F la s h (120 IPM)On or Off Abnormal operation of BRT cardConfirm the programming data: CM05, CM07 YY=02. Check to see if the SENS switch is set as per the AP number (04-15) assigned by CM05. Reset the MB switch (Down→Up→Down) If the fault cannot be cleared, replace the card....
Page 206
CHAPTER 5 OPERATION TEST PLO Operation Test NEAX2000 IVS2 ISDN System Manual ND-70919 (E), Issue 1.0 Page 195 PLO OPERATION TEST To confirm the PLO operation do the following tests: Clock Signal Generation Test Clock Signal Synchronization Test To be tested when the PBX is a clock receiver office. Interoffice Synchronization Test Source Office Mode Test To be tested when the PBX is a clock source office. Clock Signal Generation Test This test checks to see if the PLO keeps generating clock...
Page 207
NEAX2000 IVS2 ISDN System ManualPage 196 ND-70919 (E), Issue 1.0 CHAPTER 5 OPERATION TEST PLO Operation Test Clock Signal Synchronization Test This test checks to see if the PLO keeps synchronizing with the external clock signals, when the external clock signals from network has input again after it has stopped once. Do the following procedure using “In Service” transmission lines. (1) When providing one clock supply route STEP 1: On the DTI0/PRT0/BRT0 card extracting clock signals, set the switches...
Page 208
CHAPTER 5 OPERATION TEST PLO Operation Test NEAX2000 IVS2 ISDN System Manual ND-70919 (E), Issue 1.0 Page 197 STEP 6: After an outgoing connection via trunks has been established, confirm interoffice synchronization and speech quality with the procedure shown in STEP 3. NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on the MP card, and do the above test again. (2) When providing two clock supply routes STEP 1: On the DTI/PRT/BRT cards extracting clock...
Page 209
NEAX2000 IVS2 ISDN System ManualPage 198 ND-70919 (E), Issue 1.0 CHAPTER 5 OPERATION TEST PLO Operation Test STEP 6: On the DTI0/1, PRT0/1, BRT0/1 cards, set the switches as shown in STEP 1 to input clock signals from the clock supply Route 1. STEP 7: Repeat STEP 2 and STEP 3 of this procedure. STEP 8: On the DTI/PRT/BRT cards, set the switches as follows to change the clock supply route from 1 to 0: 30DTI0 card: SW-1 to ON, SW-2 to OFF 30DTI1 card: SW-1 to OFF, SW-2 to ON PRT0/24DTI0 card:...
Page 210
CHAPTER 5 OPERATION TEST PLO Operation Test NEAX2000 IVS2 ISDN System Manual ND-70919 (E), Issue 1.0 Page 199 STEP 4: Do the above test again in the opposite direction. NOTE:If noise periodically occurs, replace the MP card after checking the switch settings on the MP card, and do the above test again. Source Office Mode Test When the PBX is operated as a clock source office, do the following procedure using “In Service” transmission lines. STEP 1: Confirm that the following switches on all the...