DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-15 Synchronization Installation and Testing 3 Table 3-4 lists the sp litter mod el(s) ap p lic ab le to sp ec ific c ountries. Table 3-4. Country-specific splitter applications CountrySplitter model 400A/401A T1 100 W402A E1 120 W403A E1 75 W Argentina Y Australia Y Austria Y Y Bahrain Y Y Belg ium Y Y Brazil Y Canad a Y China Y Columb ia Y Denmark Y Y Eg y p t Y...
Page 52
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-16 Synchronization Installation and Testing 3 Philip p ines Y Y Pol an d Y Y Portugal Y Y Rus si a Y Y Saud i Arabia Y Y Sing ap ore Y Sou t h A f r ic a Y Y Sp a i n Y Y Sri Lanka Y Y Sw ed e n Y Y Sw it z er l an d Y Y Ta i w a n Y Y Ukraine Y Y UAE Y Y UK Y Y USA Y Uzb ekistan Y Y Vie t na m Y Y 1. Jap an uses b oth 75-W and 120-W T1; 402A and 403A sync sp...
Page 53
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-17 Synchronization Installation and Testing 3 Verify the DS1 service To verify the DS1 servic e, use the p roc ed ure in Table 3-5. Have the ATM switch installer verify the synchronization sourc e. Table 3-5. T1 or E1 service verification procedure ÖStep Action Command Description 1. Chec k timing signalChec k that the GREEN STATUS 3 LED on the d esignated...
Page 54
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-18 Synchronization Installation and Testing 3 Table 3-6. Interpretation of the list measurements report Displayed Field Function Indication Test: cpe-loopbac k-jack3-in-24 stress test patternThe loop b ac k jac k test is ac tive Synchronize d= Y = NThe DS1 c irc uit p ac k is sync hronized to the loop ed 3-in-24 p attern and is c ounting the b it errors d...
Page 55
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-19 Synchronization Installation and Testing 3 Installing and testing the splitter The sp litter must be installed and tested b efore the up g rad e and c utover. The p urp ose of testing the sp litter is to nProve that there is enoug h sig nal level for the c ab le leng th to the ATM switc h: — up to 130 ft. (39.65 m) for 400A — within the stand ard 6 d B...
Page 56
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-20 Synchronization Installation and Testing 3 Installing a 400A T1 splitter NOTE: Make sure you are c onnec ted to the network b efore c onnec ting to the DEFINITY ECS. Onc e the sync sp litter p asses the DS1 sp an tests, it c an b e installed and tested in p lac e. The 400A sync sp litter c an b e either nConnected through an ICSU nConnected through a...
Page 57
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-21 Synchronization Installation and Testing 3 Connected through an ICSU. Use the p roc ed ures in Table 3-9 to install the sp litter b etween an ICSU and a DS1 c irc uit p ac k. Table 3-9. Installing the splitter through an ICSU ÖStep Action Command Description 1. Disab le sync hronization switc hdisable sync hronization -switc h Prevent the system from...
Page 58
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-22 Synchronization Installation and Testing 3 Test the 120A ICSU with either a 700A DS1 CPE loop bac k jac k or a 103A b loc k. Use the p roc ed ure in Table 3-10 to test a sp litter c onnec ted throug h an ICSU. 15. Run rep ort list measurements d s1 summary UUCSSWait 15 minutes b efore entering the c ommand. If the DS1 c irc uit p ac k is not error-free,...
Page 59
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-23 Synchronization Installation and Testing 3 6.Rec onnec t the cableConnec t the H600-383 c able to the smart jac k or dumb block. 1. For more information about Smart Jac k CPE Testing , see DEFINITY ECS Release 8 Maintenanc e for R8r, Chap ter 6, “ DS1 CPE Loop b ac k Jac k Installation and Op erations Instruc tions.” Table 3-10. The 120A ICSU test...
Page 60
DEFINITY ECS Release 8.2 ATM Installation, Upgrades, and Administration 555-233-124 Issue 1 April 2000 Installing a DEFINITY ECS ATM-PNC 3-24 Synchronization Installation and Testing 3 Use the p roc ed ures in Table 3-11 to test the 120A ICSU with the 700A DS1 CPE loopback jack. Connected through a DSU/CSU. Before c onnec ting any of the timing hard ware, ensure that the DSU/CSU is c onfigured to report loss of sig nal alarms. If using a 316X CSU c onnec ted to a T1 fac ility and used as...