Page 41
CHAPTER 2: INSTALLATION PQMII POWER QUALITY METER – INSTRUCTION MANUAL2–11 For a single-phase connection, connect current and voltage to the phase A inputs only. All other inputs are ignored. Select the S2 SYSTEM SETUP CURRENT/VOLTAGE CONFIGURATION VT WIRING: “SINGLE PHASE” setpoint . FIGURE 2–8: Single Phase Connection
Page 42
2–12PQMII POWER QUALITY METER – INSTRUCTION MANUAL CHAPTER 2: INSTALLATION 2.2.3 3-wire System using Two CTs The f igure below shows two methods for connecting CTs to the PQMII for a 3-wire system. The top drawing shows the standard wiring conf iguration using three CTs. An alternate wiring conf iguration uses only two CTs. With the two CT method, the third phase is measured by connecting the commons from phase A and C to the phase B input on the PQMII. This causes the phase A and phase C current to...
Page 43
CHAPTER 2: INSTALLATION PQMII POWER QUALITY METER – INSTRUCTION MANUAL2–13 2.2.4 Control Power The control power supplied to the PQMII must match the installed power supply. If the applied voltage does not match, damage to the unit may occur. Check the product identif ication to verify the control voltage matches the intended application. A universal AC/DC power supply is standard on the PQMII. It covers the range 90 to 300 V DC and 70 to 265 V AC at 50/60 Hz. It is not necessary to adjust the PQMII...
Page 44
2–14PQMII POWER QUALITY METER – INSTRUCTION MANUAL CHAPTER 2: INSTALLATION 2.2.7 Output Relays The basic PQMII comes equipped with one output relay; the control option supplies three additional output relays. The PQMII output relays have form C contacts (normally open (NO), normally closed (NC), and common (COM)). The contact rating for each relay is 5 A resistive and 5 A inductive at 250 V AC. Consult 1.6: Specifications for contact ratings under other conditions. The wiring diagrams show the state...
Page 45
CHAPTER 2: INSTALLATION PQMII POWER QUALITY METER – INSTRUCTION MANUAL2–15 Each switch input can be programmed with a 20-character user def ined name and can be selected to accept a normally open or normally closed switch. A list of various functions assignable to switches is shown below, followed by a description of each function. •Alarm Relay: When a switch input is assigned to the alarm relay, a change in the switch status produces an alarm condition and the alarm relay activates. •Pulse Input...
Page 46
2–16PQMII POWER QUALITY METER – INSTRUCTION MANUAL CHAPTER 2: INSTALLATION FIGURE 2–11: Analog Input Multiplexing •Aux 1/2/3 Relay: When a switch input is assigned to an Auxiliary relay, a closure on the switch input causes the programmed auxiliary relay to change state. This selection is available only if the Control (C) option is installed. •Clear Energy: When a switch input is assigned to “Clear Energy”, a closure on the switch input will clear all Energy data within the PQMII. •Clear Demand: When...
Page 47
CHAPTER 2: INSTALLATION PQMII POWER QUALITY METER – INSTRUCTION MANUAL2–17 FIGURE 2–12: Analog Output As shown in wiring diagrams, these outputs are at Terminals 25 to 28 and share Terminal 24 as their common. Shielded cable should be used, with only one end of the shield grounded, to minimize noise effects. Signals and power supply circuitry are internally isolated, allowing connection to devices (PLCs, computers, etc.) at ground potentials different from the PQMII. Each terminal, however, is...
Page 48
2–18PQMII POWER QUALITY METER – INSTRUCTION MANUAL CHAPTER 2: INSTALLATION indicates that the PQMII is transmitting data. Each PQMII must be daisy-chained to the next one as shown in the f igure below. Avoid star or stub connected conf igurations. If a large difference in ground potentials exists, communication on the serial communication link will not be possible. Therefore, it is imperative that the serial master and PQMII are both at the same ground potential. This is accomplished by joining the...
Page 49
CHAPTER 2: INSTALLATION PQMII POWER QUALITY METER – INSTRUCTION MANUAL2–19 2.2.12 RS232 Front Panel Port A 9-pin RS232C serial port provided on the front panel allows the user to program the PQMII with a personal computer. This port uses the same communication protocol as the rear terminal RS485 ports. To use this interface, the personal computer must be running the EnerVista PQMII Setup Software provided with the relay. Cabling to the RS232 port of the computer is shown below for both 9-pin and...
Page 50
2–20PQMII POWER QUALITY METER – INSTRUCTION MANUAL CHAPTER 2: INSTALLATION FIGURE 2–15: Hi-Pot Testing 746702A1.CDR 5 PQMII POWER QUALITY METER GE Multilin