Page 61
Install and Connect the Cabinets 4-24Issue 1 September 1995 !CAUTION: Do not route fibre-optic cables and the B25A cables together. Figure Notes: Figure 4-15. Single-Carrier Cabinet Fibre Routing Cable Connections When routing fibre-optic cables, connect the cables (according to the Running List provided in the Customer Service Document (CSD)) to the transceiver, and plug the transceiver into the appropriate slot on the back of the cabinet, as illustrated in Figure 4-16 through Figure 4-18. 3 4 4...
Page 62
Install Fibre-Optic Cables Issue 1 September 1995 4-25 Standard Reliability Fibre-Optic Cable Connections For Standard Reliability system configuration, route the fibre-optic cable as illustrated below. Figure 4-16. Fibre-Optic Cable Connections for Standard Reliability Single-Carrier Cabinet System 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 181 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 181 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 TerminalAUX A BCDPort Cabinet...
Page 63
Install and Connect the Cabinets 4-26Issue 1 September 1995 High Reliability Fibre-Optic Cable Connections For High-Reliability system configuration, route the fibre-optic cables as illustrated below. Figure 4-17. Fibre-Optic Cable Connections for High Reliability Single-Carrier Cabinet System 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 181 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 TerminalAUX ACDPort Cabinet Port Cabinet Control Cabinet 1 2 3 4 5 6 7 8 9 10 11...
Page 64
Install Fibre-Optic Cables Issue 1 September 1995 4-27 Critical Reliability Fibre-Optic Cable Connections For Critical Reliability system configuration, route the fibre-optic cables as illustrated below.
Page 65
Install and Connect the Cabinets 4-28Issue 1 September 1995 Figure 4-18. Expansion Port Network Fibre-Optic Cable Connections for Single-Carrier Cabinet with Critical-Reliability Switch 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 181 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 TerminalAUX BCDPort Cabinet Port Cabinet Control Cabinet 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 181 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 CDPort Cabinet Port Cabinet 1 2 3 4 5 6 7 8 9...
Page 66
Verify Port Cabinet Ad dress Plugs Issue 1 September 1995 4-29 Verify Port Cabinet Address Plugs The Cabinet Ad dress Plug is a jumper and is required for single-c arrier port cabinets only. On the backplane of a port cabinet, to the right of slot 00, a group of six pins is marked for the cabinet (c arrier) address plug jumper connections. Verify the address plug for each port carrier is in the correct location (see Figure 4-19). Figure Notes: 1. A d dress Plug 2. Jump er 3. Right side at back of...
Page 67
Install and Connect the Cabinets 4-30Issue 1 September 1995 Install Back Panels Install the b a ck panels, tightening the screws when all p anels are in place. Allow the screws labeled callout 4 in Figure 4-21 on page 4-31 to remain loose. Install Ground Plates The ground plate (Figure 4-20) provides the ground connection for the cabinets and stabilizes the cabinets. Figure 4-20. Ground Plate 1 23 Figure Notes: 1. Front Ground Plate 2. Battery3. Back Ground Plate nSide View of 2-Cabinet Port Network
Page 68
Install Ground Plates Issue 1 September 1995 4-31 See Figure 4-22 and Figure 4-23 for illustrations of the ground plate and cable clamp positions. Install Ground Plates on Systems with Earthquake Protection Refer to Ap pendix B for earthquake protection procedures. Install Ground Plates on Systems without Earthquake Protection A ground plate is required to connect each cabinet together (see the following figures). To install the ground plate, complete the following steps: 1. At the back of the c...
Page 69
Install and Connect the Cabinets 4-32Issue 1 September 1995 2. At the upper cabinet, place the top of the ground plate over the bottom of the lower-back panel so the four screws at the b ottom of the lower- back panel fit through the four ground plate keyhole slots. The bottom ed g e of the ground plate should overlap at the top edge of the lower back panel. 3. Slide the ground plate down over the top of the upper-back panel of the lower c a binet so the four sc rews attaching the upper-back panel...
Page 70
Install Ground Plates Issue 1 September 1995 4-33 Figure Notes: Figure 4-22. Single-Carrier Cabinet Ground Plate, Cabinet Clip, and Battery Locations 1 23 1. Cabinet Clip 2. Battery3. Back Ground Plate nSide View of 2-Cabinet Port Network