Page 121
121RTAA-IOM-3 Pre-Start Checkout General When installation is complete, but prior to putting the unit into service, the following pre-start procedures must be reviewed and verified correct: [ ] Inspect all wiring connections to be sure they are clean and tight. WARNING: Disconnect all electric power including remote disconnects before servicing’ Failure to disconnect power before servicing can cause severe personal injury or death. Caution: Check the tightness of all connections in the compressor power...
Page 122
122RTAA-IOM-3 [ ] Energize the evaporator and Domestic Water Heater heat tape. [ ] Fill the evaporator chilled water circuit. Refer to Table 1 for evaporator liquid capacities. Vent the system while it is being filled. Open the vent on the top of the evaporator during filling and close when filling is completed. Customer Note The use of improperly treated or untreated water in this equipment may result in scaling, erosion, corrosion, algae or slime. The services of a qualified water treatment...
Page 123
123RTAA-IOM-3 Unit Voltage Phasing It is important that proper rotation of the compressors be established before the unit is started. Proper motor rotation requires confirmation of the electrical phase sequence of the power supply. The motor is internally connected for clockwise rotation with the incoming power supply phased A, B, C. Basically, voltages generated in each phase of a polyphase alternator or circuit are called phase voltages. In a three-phase circuit, three sine wave voltages are generated,...
Page 124
124RTAA-IOM-3 1. Turn the Chiller Switch on the UCM to the STOP/RESET position. 2. Open the electrical disconnect or circuit protection switch that provides line power to the line power terminal block(s) in the starter panel (or to the unit-mounted disconnect). 3. Connect the phase sequence indicator leads to the line power terminal block, as follows: Phase Seq. LeadTerminal Black (Phase A).................. L1 Red (Phase B).................... L2 Yellow (Phase C)................ L3 4. Turn power on by...
Page 125
125RTAA-IOM-3 Start-Up Procedures General If the pre-start checkout, as discussed above, has been completed, the unit is ready to start. UCM controls are shown in Figure 51 and UCM Sequence of Operation is shown in Figures 56 and 57. Complete each step, in sequence, as follows: [ ] Move the Chiller Switch on the UCM to the STOP/RESET position. [ ] As necessary, adjust the setpoint values in the UCM menus, as described in “Menu Function Descriptions and Selections”. [ ] Close the fused-disconnect...
Page 126
126 RTAA-IOM-3 Figure 56 Unit Sequence of Operation – RTAA 240 to 400 Tons (Continued on Next Page)
Page 129
129RTAA-IOM-3 Unit Shutdown Procedures Temporary Shutdown and Restart To shut the unit down for a short time, use the following procedure: 1. Move the Chiller Switch to STOP/ RESET. The compressors will continue to operate and, after unloading for 20 seconds, will stop when the compressor contactors de- energize. The condenser fans will be de-energized at this time. 2. The unit disconnect switch and unit mounted disconnect (if installed) should remain closed to keep the compressor sump heaters...
Page 130
130RTAA-IOM-3 System Restart After Extended Shutdown. Follow the procedures below to restart the unit after extended shutdown: 1. Verify that the liquid line service valves, oil line, compressor discharge service valves and suction service valves (if installed) are open (backseated). Caution: To prevent damage to the compressor, be sure that all refrigerant valves are open before starting the unit. 2. Close the main disconnect and unit mounted disconnect (if installed) to energize the compressor sump...