    							Siemens Practices
    Installation Series:
    A30808-X5130-8120-1-89281
    Issue 1, May 1986
    ’1
    !Issued by Office Systems Group
    5500 Broken Sound Boulevard 
    N.W., Boca Raton, Florida 33431--___________-Siemcns Information Systems, Inc.(305) 994-8100 l Telex: 515052
    ----- - ..- -----
    Printed in U.S.A. 
    						
    							SATURN IIE EPABXA30808X5130-8120-1-8328Installation Test ProceduresIssue 1, May 1906SECTIONPAGE
    l.CO INTRDCUCTlON............;..............1-lPurpose..................................l-l
    scope....................................
    1-lSiemens SATURN IIE Practices.................l-l
    Siemens Customer Support Services............l-l
    2.00 
    PREP/%KGXIY ACTIVITY...................2-1Cener21..................................2-1Test Equipment Required....................2-lHandling Precautions for PC& with
    MOS Integrated Circuiis.....................2-lPC6 Removal and Replacement Guidelines.......2-1Initial Visual Inspection Procedures..............2-1
    3.CO GROUND TESTS..........................3-lGeneral...................................3-lSystem Ground Test.........................3-1Shelf Ground Continuity Test..................3-14.00 POWER-UP TESTS........................4-l
    Genera I..................................4-1Power-Up/Output Voltage Tests................4-l
    5.00 OPERATING PROGRAM LOAD!NG............5-1
    General...................................5-1Loading Operafing Dis!~......................5-lInputting CMU Data to Floppy Disk.............5-l
    &CO ON-FINE DlAGrGxTlC TESTS...............6-3
    General...................................6-lConnection of Maintenance Phone
    and Modem..............................
    6-lMDF Cross-Connecting Prccedures.............6-1System Diagnostic Tests;....................6-12
    7.CO INSTALLATION TEST PRCCEDURES CHEC#L!ST 7-lGeneral...................................7-l
    l=lGUREPAGE
    2.00 Signal 
    Cab!e Distribution for the SATURN IIESystem (Basic Cabinet).................
    2.01 Signal Cable Distribution for the SATURN 
    IIESystem (Expansion Cabinet).............
    2.02 Power/Ground Distribution for the SATURN 
    IIESystem (Basic Cabinet).................
    2.03 Power/Ground Distribution for the SATURN 
    IIESystem (Expansion Cabinet).............
    3.00 System Ground Test Connections
    ..........3.01 Shelf Ground Continuity Test Connections....
    4.00 Location of Input Voltage Connectors on
    Basic Backplane......................
    4.01 Location of Input Voltage Connectors on
    LTU Backplane.......................
    5.00 Floppy Disk and Storage Envelope.........
    5.01 Power System Unit (Front View)............
    5.02 Floppy Disk Loading Procedures...........
    5.03 
    CIOP Printed Circuit Board...............
    6.00 Maintenance Phone and Maintenance-Related
    Cress-Connections....................
    6.01 
    Modem Cross-Connections...............
    .2-4
    2-5
    2-6
    2-7
    3-2
    3-3
    . .4-5
    .4-6
    5-l
    5-4
    5-5
    5-6
    6-2
    6-z6.02 Single -Line Telephone Cross-Connections
    Using SLMA 
    PCB . . . 6-3
    6.03 Single -Line Telephone Cross-Connections
    Using SLAi6 PCB
    6.04 Siemens Digital Teiephone Cross-Connections
    Using SLMD PCB. .
    6.05 SATURN Attendant Console Cross-Connections
    6.06 CO and 
    CID Trunk Cross-Conneciions .
    6.07 Two-Wire (Type I) E&M Trunk Cross-Connec?ions6.08 Four-Wire (T;lce I) E&M Trunk Cross-Connections6-3
    63
    G-4
    E-5G-5
    G-S
    _.6.09 Two-Wire (Type II) E&M Trunk Cross-Connections . 6-6
    6.10 Four-Wire (?ype II) E&M Trunk Cross-Connections . 6-76.il Recorded Anncuncement (DID and Tie Trunk
    Vacant Number Intercept, and ACD
    Announcement 
    Service) Cross-Connections 6-7
    6.12 Code Ca!ling (With or Without Answerback)
    Cross-Connections . . 6-8
    6.13 Dial Ciciation 
    (DTMF) Cross-Conneciions. 6-8
    6.14 Music-en-Hold Cross-Connections Using
    TMBA4 PCB . . . . 6-9
    6.15 Music-on-Ho!d Cross-Connecticns Using
    SLMAISLA16 PCB . . . . . . 6-9
    6.16 Paging With Answerback Cross-Connections 6-10
    6.17 Paging Without Answerback Cross-Connections. . 6-10
    6.18 Universal Night Answer (UNA) Cross-Connections 
    E-116.49 Attendant Conscie Keypad and FcaturoButton Depiassion Ssquonce G-:3620 Siemens DYIiD Te!ephono Buttcn CcpressicnSequence . . . . . . . . . . . . . . 6-216.21 Siemens JR-DYAD Te!ephone EuitcnDepression Sequence . . 6-23
    1.00 Mnemonics Used in This Practice..............l-l
    2.CO PCB and Powar Supply Removal Guidelines.....2-22.01 Visual Inspeciion...........................2-33.00 System Ground Test.........................3-l3.01 Shelf Ground Continuity Test..................3-14.00 Power-Up/Output Voitnge Test.................4-l5.00 Loading Procedures fcr Operating Disk..........5-25.01 CIOP DIP Swiich Settings....................5-35.02 LED Display Values for Leading Errors..........5-4
    6.00 Tone Generator Test........................6-136.01 Tone Genera:or Test I\!umbers................G-i36.02 DTMF 
    Receiver Test........................G-146.03 Station Line Test...........................6-14
    6.04 DTMF Pad Test............................6-15
    6.05 Console Test...............................6-166.06 Attendant Console Displayable Characters.......6-196.07 Siemens Digital Telephone - DYAD Button Test 6-20
    6.08 Siemens Digital Telephone - JR-DYAD
    Button Test . . . . .
    6.09 Siemens 
    Digiial Telephone -DYAD Display Test6.10 Siemens Digital Telephone DisplayableCharacters . .
    6.11 Outgoing Trunk Test .
    6.12 Placing Circuit(s) In-Service
    6.13 Taking Circuit(s) Out-of-Service
    7.CO Insta!lation Test Procedures ChecklistG-22
    6-24
    6-25
    6-26
    6-27
    6-277-l 
    						
    							SATURN IIE EPABX
    installation Test ProceduresA30808-X5130-0120-l-0928Issue 1, May 1986.
    1.01Purpose. The equipment comprising the SATURN IiE(SATURN Ii-Expanded) System is compleYely tested at the fac-
    tory prior to shipment. The inspections and tests covered in
    this practice verify that the EPABX equipment has been
    properly installed; ensure that no damage 
    wasIncurred dur-
    ing transit; and confirm that the sysiem is completely opera-
    tional. Table 1.00 defines the mnemonics usedthroughout 
    ihispractice.
    CAUTION
    lnstalbtion test procedures on the SATL’RN I/E EPABXmust be performed only by Siemer;s cetiified personnel.
    1.02Sccpe. This practice is divided into the following sec-
    tions which are presented in the sequential order of per-for-mance after initial installation of a SATURN IIE System. When
    additional equipment is installed to an existing and active
    SATURN 
    IIE System, it is the responsibility of craft person-
    nel to determine the sequential order of the test procedures
    contained in 
    tihese sections.
    ACD
    Au;omaiic Cafl DisiributionALiVlAlarm
    ASCIIAmerican Standard Code for Information lntarchangeCIOPController/Input-Ouiput PrccessorCMUCustomer Memory Update
    coCentral Office
    CONFConference Module
    COTCentral Office Trunk
    DCIData Communication Interface
    DIDDirect Inward Dialing
    DIPDual lnline PackageDPDial PulseDTEDa?a Terminal EquipmentDTMFDual Tone MultifrequencyEIAElectronics Industries AssociationEPABXElectronic Private Automatic Branch Exchange
    FDDFloppy Disk Drive
    IRAMInput Random Access MemoryLTULine/Trunk UnitLTUPSLine/Trunk Unit Power Supply
    LEDLight-Emitting Diode
    MCAMemory Control and Attenuation
    MDFMain Distribution FrameMEM325Gkb MemoryMEM41Mb Memory
    MOSMetal Oxide Semiconductor
    MRAMaterial Return Authorization.
    MSMMemory Support ModuleMTCEMaintenance00sOut-of-ServiceORAMOutput Random Access MemoryPABXPrivate Automatic Branch Exchange
    PCBPrinted Circuit Board
    PENPort Equipment NumberPIMDPremium Instrument Module DigitalPSCParallel/Serial ConverterPSUPower Supply Unita. Section 
    l.CO - Introduction
    b. Section 2.00 
    - Preparatory Activiiyc. Section 3.00 
    - Ground Tests
    d. Section 4.00 
    - Power-Up Tests
    e. Section 5.00 
    - Operating Program Loading
    f. Section 
    6.80- On-Lina Diagnostic Tesis
    g. Section 7.00 - lnstallaticn Test ProceduresChecklist
    7.03Siemens SATURN IIE Prac:iccs. The practices, issue
    numbers and dates for the SATURN IIE EPABX are lists3 in thePractices Documentation Index A.30808~X5130-AlgO- * -E987 Al-ways refer to the !aiest issue of the application indcx to ob-
    tain the latest issue number of a practice.
    724 Siemens Cus;oma: Sqpsrt Services. Sicrnonsmaintains a nationwide network cf field service offices. Con-
    tact the Siemens regional oifice for any engineering es-sistance that may be requked.
    TaS!e 1.00 Mnemonics Used in This Practice
    DEFiN1TfONi-i 
    						
    							SATURN IIE EPABX
    Installation Test Procedures
    .Table 1.00 Mnemonics Used in This Practice (Continued)
    [\fiNEMDNIC *DEFINITION
    RAUPRemote Access Unit/Ports
    RGENRing Generator
    S-416Subscriber Line Module Analog - 16 lines
    SLMASubscriber Line Module Analog
    SLMA-SSubscriber Line Module Analog 
    - Station
    SLMDSubscriber Line Module Digital
    SMXTGSignal Multiplexer/Tone GeneratorSPCStored-Program-ControlledSPGSingle Point Ground
    TMBA-2Two-Wire E&M Trunk
    TMBA-4Four-Wire E&M Trunk
    TMBMCentral Office Trunk
    TMIEDirect Inward Dialing Trunk
    TMSTransmission Measuring Set
    TSTAPPTest - ApparatusTSTDIAGTest - Maintenance DiagnosticTTYTeletypewriter
    UNAUniversal Night Answer
    ZUNAZoned Universal Night Answer
    -48PS
    -48Vdc Power Supply
    l-2 (2 pages) 
    						
    							SATURN IIE EPABXA30808-X5130-B120-l-8928Installation Test ProceduresIssue 1, May 1986
    2.01General. This section describes the test equipment re-
    quired to perform the installation test procedures, handling
    precautions for Printed Circuit Boards 
    (PCBs) with Metal Ox-
    ide Semiconductor (MOS) integrated circuits, guidelines for
    removal and replacement of 
    PCBs and powei supplies, and
    initial visual inspection procedures.
    2.02Test Equipment Required. The following test equip-
    ment is required to perform the procedures contained in this
    practice:
    a. Digital Multimeter. A digital multimeter of 
    gocd com-
    mercial quality with an accuracy of + 1.0% or better.
    The digital multimeter is used to perform the ground
    tests and output voltage tests.
    b.Maintenance Test Phone. For both Dial Pulse (DP) and
    Dual Tone Multifrequency (DTMF) systems, a lineman’s
    test set or a single line te!ephone. A modular jack
    (MTCE PHONE) is provided on the front panal of the
    PSU for conneciing the maintenance test phone when
    equipped with a modular plug. When the maintenance
    test phone is not equipped with a modular plug, a sta-
    tion appearance can be used via the Main Distribu-
    tion Frame 
    (MDF). The mainienance test phone is used
    to perform the on-line diagnostic tests.
    c. Data Service Terminal. A Keyboard-Send-Receive
    (KSR) daia terminal equipped with a standard ASCII
    keyboard and an EIA RS-232C interface (Silent 700
    Series 
    - Model 743 KSR - Texas Instruments, or
    equivalent). The data service terminal is used to input
    installation dependent data (i.e., system data base) into
    system memory when the standard data base format
    is supplied with the SATURN 
    IIE System.d. -Transmission Measuring Set. A transmission measur-
    ing set (TMS) used to measure the transmission qual-
    ity of a trunk or station (Hewlett Packard HP-355iA or
    equivalent). Refer to the manual On-Line 
    DiagnostiCTests, Outgoing Trunk Test and Station Line Tosl.2.03handling Precautions for 
    PCBs wifh MCS Integmt-ed Circuiklt is important that craft personnel handling FCBswith MOS integrated circuits free themselves from electrostatic
    charge by touching a grounded cabinet frame before handling
    such 
    PCEs, or by wearing grounded wrist straps. Failur:, to
    observe this practice may result in damage to MO3 PCBsdue to electrostatic discharge.
    WARNING
    lirazardous voltages exist r&h.% the eqo&ment cabins?.
    Be extremely careful when perr”orming fcsa-incjtroubleshooting procedures with the oquipmcr;tpanel(s) removed.
    2.04PCB Removal and P,ep!acemenZ Guide%% In many
    instances during testing, the corrective action for a procedure
    in which the proper verification was not obtained requires that
    a PCB or a power supply be removed and replaced with a
    spare. 
    Tablo 2.00 provides the guidelines that shou!d be o!)-served when removing and rep!acing PCBs and powor SI:;X-plies in an active sysicm.2.05 
    lnifial Visual kspactizn Procedurx. The visu’al in-
    spection procedures contained in Tab!e 2.01 must be psrfcrmcdto ensure that the equipment comprising the SATURN ItE Sys-
    tem has been properly installed and configured to meet the
    installation requirements. Before proceeding 
    wiih the visual in-
    spections, the front, rear and side panels of the cabinei shouldbe removed to allcw thorough inspection of the equipment.
    2-1 
    						
    							-
    Table 2.00 PC3 and Power Supply Remcval Guidelines
    I’AODIJLE ORSERVEC”SPECIAL
    UNITSTATEINSTRUCTKWIS
    CIOPNA
    CONF. NA
    DTMF00s
    FDDO, 
    FDDlNALTUCfNA
    LTUPSlNA
    MCA
    MEM3
    kzMEM4NAMSMl
    NA
    MSM Baitery lNAPIMD00sPSCNAPSUNA
    RAUP
    NA
    SLAl600sSLMA-000s
    SLMA-S
    003SLMD00s
    SMXTGESTMBA-2
    TMBA-4
    00s
    TMBM
    00s
    TMIE00s-48PS.lNA-48PStfNA
    * Optional depending upon customer/system requirements.
    NA = Not Applicable; 00s = Out-of-ServiceNotes 1 and 2
    Notes 1 and 2
    Note 3
    None
    Note 4
    Note 5
    Notes 1 and 2
    Notes 1 and 2
    Notes 
    1 and 2
    Note 1
    Note 6
    Note 3
    Notes 1 and 2
    Note 7
    Notes 1 and 2
    Note 3
    Note 3
    Note 3
    Note 3
    Notes 1 and 2
    Note 3
    Note 3
    No?e 3
    Note 3
    Note 8Noie 3
    Notes:
    1.System outage (halts call processing). Set BASIC PS circuit breaker on PSU to off.2.Open FDD and remove floppy disk before removing PCB. After new PCB is inserted, reinsert floppy disk, close
    FDD, set BASK PS circuit breaker on PSU to on, and press reset switch on CIOP3.VVait for in-process ca!ls i0 complete.4.Removal places one-half of ports in shelf out-of-service.5.Before removal, set related LTUPS circuit breaker on PSU to off. Removal places all ports in shelf out-of-service.6.Battery may be replaced with power applied to system.7.System outage (halts call processing). Before removal, set all circuit breakers to off, open FDDs and remove flop-
    py disks. After replacement, reinsert floppy disks, close FDDs, set circuit breakers to on, and press reset switch
    on CIOR8.Set related circuit breaker on PSU to off. May halt call processing depending upon system configuration and
    traffic. If there are two -48Vdc power supplies (where system includes an Expansion Cabinei), the remaining sup-
    ply may have sufficient capacity to support system operation.
    A30808-X5130-8120-l-8928Issue 1, May 1986
    2-2 
    						
    							I.-
    A30808-X5130-B120-l-8928Issue 1, May 1986 SATURN IIE EPABX
    Installation Test Procedures
    Table 2.01 Visual Inspection
    STEPVISUAL INSPECTIONREFERENCE
    1Check that the cabinet ac power cord is not connected to an
    electrical outlet.
    2Check that the -48Vdc power supply is strapped forSATURN IIE EPABX Installation11OVac or 22OVac.Procedures Practice (Section 4.00)
    3Check that all circuit breakers on the Power System UnitSATURN IIE EPABX Installation
    (PSU) are in the OFF position and fuses inserted.Procedures Practice (Section 4.00)
    4If the MSM is installed, check that the Battery Packk is notSATURN IIE EPABX Installation
    connected but inserted into corresponding position. AlsoProcedures Practice (Section 4.00)
    check that the PSU is strapped for MSM operation.
    5Check that each PCB in the system is withdrawn from its
    backplane connector.
    6Check that the DIP switch settings for the CIOP board are setSATURN IIE EPABX Installation
    to meet the operating characteristics of the particular dataProcedures Practice (Section 4.00)
    service terminal to be used to input the installation-dependent
    data(i.e.,data base) into system memory when the standard
    data base format is supplied with the SATURN IIE System.
    7Check that each trunk-type PCB (i.e., TMEM, TMIE, TMBA-2SATURN IIE EPABX Installation
    and/or TMBA-4) is properly strapped according to theProcedures Practice (Section 4.00)
    operating characteristics of the trunk facility of the Central
    Office (CO) or distant PABX.
    8Chec!c that the intercabinet signal and power/ground cablingFigures 2.00 through 2.03
    arrangements are complete and all connectors are firmly seat-
    ed according to the referenced illustrations (Figures 2.00
    through 2.03).
    9Check that Berg Clips are on pins 27 and 28 of unusedSATURN IIE EPABX Installation
    signal cable connectors on basic shelf.Procedures Practice (Section 4.00)
    2-3 
    						
    							w3w13-I  
    ISATURN 
    IIE EPABX,xtallation Test ProceduresA30808-X5130-B120-l-5928Issue 1, May 1986
    Figure 
    2.00Signal Cable Distribution for the SATURN IIE System (Basic Cabinet) 
    						
    							SATURN IIE EPABX
    Installation Test ProceduresA30808-X5130-B120-l-8928issue 1, May 1986
    W23EXPANSION CABINET
    \
    I--- ---
    : ]1FDD 
    :, 
    i;wi!
    i-L--i-- - _-__--
    LiTJ-. - -
    -r----- *
    W22BASIC CA&NET
    A5040-2.313186Figure 2.01Signal Cable Distribution for the SATURN IIE System (Expansion Cabinet)
    2-5 
    						
    							SATURN IIE EPABXtnstallation Test ProceduresA30808-X5130-8120-1-8928Issue 1, May 1986
    LTUSOLINE TRUNK UNIT SHELFJ42
    J43
    r JPL
    JlBASS
    BASIC SHELFEl a----
    J46J47
    E2
    05039.1..wmGFigure 2.02Power/Ground Distribution for the SATURN IIE System (Basic Cabinet)
    2-6 
    						