Home > Panasonic > Air Conditioner > Panasonic Cs Xc12ckq Cs Xc9ckq Repair Manual

Panasonic Cs Xc12ckq Cs Xc9ckq Repair Manual

    Download as PDF Print this page Share this page

    Have a look at the manual Panasonic Cs Xc12ckq Cs Xc9ckq Repair Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 10737 Panasonic manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    							Applica ble piping kit
    CZ-3F5, 7AEN (XC9CK)
    CZ-4F5, 7, 10AN (XC12CK)
    SELEC T THE BEST LOCATION
    INDOOR UNIT
     
        • 
    • •  • 
    There should not be any heat source or steam near the
    unit.
     
        • 
    • •  • 
    There should not be any obstacles blocking the air
    circulation.
     
        • 
    • •  • 
    A place where air circulation in the room is good.
     
        • 
    • •  • 
    A place where drainage can be easily done.
     
        • 
    • •  • 
    A place where noise prevention is taken into
    consideration .
     
        • 
    • •  • 
    Do not install the unit near the door way.
     
        • 
    • •  • 
    Ensure the spaces indicated by arrows from the wall,
    ceiling, fence or other obstacles.
     
        • 
    • •  • 
    Recommended installa tion height for indoor unit shall be
    at least 2.3 m.
    OUTDOOR UNIT
     
        • 
    • •  • 
    If an awning is built over the unit to prevent direct
    sunlight or rain, be careful that heat radiation from the
    condenser is not obstructed.
     
        • 
    • •  • 
    There should not be any animal or plant which could be
    affecte d by hot air discharged.
     
        • 
    • •  • 
    Keep the spaces indicated by arrows from wall,ceiling,
    fence or other obstacles.
     
        • 
    • •  • 
    Do not place any obstacles which may cause a short
    circuit of the discharged air.
     
        • 
    • •  • 
    If piping length is over the common length, additio nal
    refrigerant should be added as shown in the table.
    Indoor/Outdoor Unit Installation Diagram
     
        • 
    • •  • 
    This illustration is for explan ation purposes only.
    The indoor unit will actually face a different way. Attached accessories
    41
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							10.2.1. SELECT THE BESTLOCATION
    (Refer to “Select the best location”
    section)
    10.2.2. HOW TO FIX INSTALLATION
    PLATE
    The mounting wall is strong and solid enough to prevent itfrom
    the vibration.
    The centre of installa tion plate should be at more than 450 mm
    at right and left of the wall.
    The distance from installa tion plate edge toceiling should more
    than 67 mm.
    From installa tion plate left edge to unit’s left side is 47 mm.
    From installa tion plate right edge to unit’s right is 73 mm.
    :
    :
    :For left side piping, piping connection for liquid should be
    about 14 mm from this line.
    For left side piping, piping connection for gas should be
    about 56 mm from this line.
    For left side piping, piping connecting cable should be
    about 785 mm from this line.
     1. Mount the installa tion plate on the wall with 5 screws or
    more.
    (If mounting the unit on the concrete wall, consider using
    anchor bolts.)
     
        • 
    • •  • 
    Alwaysmount the installa tion plate horizontally by
    aligning the marking-off line with the thread and using a
    level gauge.
     2. Drill the piping plate hole withø70 mm hole-core drill.
     
        • 
    • •  • 
    Line according to the arrows marked on the lower left
    and right side of the installa tion plate. The meeting point
    of the extended line is the centre of the hole. Another
    method is by putting measuring tape at position as
    shown in the diagram above. The hole centre is
    obtained by measuring the distance namely 150 mm
    and 125 mm for left and right hole respectively.
     
        • 
    • •  • 
    Drill the piping hole at either the right or the left and the
    hole should be slightly slanted to the outdoo r side.
    10.2.3. TO DRILL A HOLE IN THEWALL
    AND INSTALL A SLEEVE OF
    PIPING
     1. Insert the piping sleeve to the hole.
     2. Fix the bushin g to the sleeve.
     3. Cut the sleeve until it extrudes about 15 mm from the wall.
    CautionWhen the wall ishollow, please be sure to use the
    sleeve for tube ass’y to prevent dangers caused by
    mice biting the connecting cable.
     4. Finish by sealing the sleeve with putty or caulking
    compound at the final stage.
    10.2.4. INDOOR UNIT INSTALLATION
     1. For the right rear piping
     2. For the right and right bottom piping
    10.2. INDOOR UNIT
    42
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							 3. For the embedded piping
    (This can be used for left rear piping & left bottom piping also.)
    43
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							10.2.5. CONNECT THECABLE TO THE
    INDOOR UNIT
     1. The inside and outside connecting cable can be connected
    without removing the front grille.
     2. Conne cting cable between indoor unit and outdoo r unit
    shall be approved polychloropre ne sheathed 5 (XC9CK,
    XC12CK)×1.5 mm
    2flexible cord, type designation 245 IEC
    57 or heavier cord.
     
        • 
    • •  • 
    Ensure the color of wires of outdoor unit and the
    terminal Nos. are the same to the indoor’s respectively.
     
        • 
    • •  • 
    Earth lead wire shall be longer than the other lead wires
    as shown in the figure for the electrical safety in case of
    the slippin g out of the cordfrom the anchorage.
     
        • 
    • •  • 
    Secure the cable onto the control board with the holder
    (clamper).
    INSTALLATION OF AIR PURIFYING FILTER
     1. Open the front panel.
     2. Remove the air filters.
     3. Put air purifyin g filter into place as shown in illustration
    below.
    44
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							HOW TO TAKE OUT FRONT GRILLE
    Please follow the steps below to take out front grille if
    necessary such as when servicing.
     1. Set the vertical airflow direction louver to the horizon tal
    position.
     2. Slide down the two caps on the front grille as shown in the
    illustration below, and then remove the two mounting
    screws.
     3. Pull the lower section of the front grille towards you to
    remove the front grille.
    Whenreinstalling the front grille, first set the vertical
    airflow direction louver to the horizontal position and
    then carry out above steps 2 - 3 in the reverse order.
    AUTO SWITCH OPERATION
    The below operations will be performed by pressing the
    “AUTO”switch.
     1. AUTO OPERATION MODE
    The Auto operation will be activated immediately once the
    Auto Switch is pressed.
     2. TEST RUN OPERATION (FOR PUMPDOWN/SERV ICING
    PURPOSE)
    The Test Run operation will be activated if the Auto Switch
    is pressed continuously for more than 5 sec. to below 10
    sec.. A“pep”sound will occur at the fifth sec., in order to
    identify the starting of Test Run operation
     3. REMOTE CONTROLLER RECEIVING SOUND ON/OFF
    The ON/OFF of Remote Controller receiving sound can be
    change over by pressing the“AUTO”Switch continuously
    for 10 sec. and above. A“pep”,“pep”sound will occur at the
    tenth sec., in order to indicate the“ON/OFF”change over of
    remote control receiving sound.
    10.3. OUTDOOR UNIT
    10.3.1. SELECT THE BESTLOCATION
    (Refer to “Select the best location”
    section)
    10.3.2. INSTALL THE OUTDOOR UNIT
     
        • 
    • •  • 
    After selecting the best location, start installa tion according
    to Indoor/Outdo or Unit Installation Diagram.
     1. Fix the unit on concrete or rigid frame firmly and horizon tally
    by bolt nut. (ø10 mm).
     2. Wheninstalling at roof, please consider strong wind and
    earthquake. Please fasten the installa tion stand firmly with
    bolt or nails.
    10.3.3. CONNECTING THE PIPING
    Connecting The Piping To Indoor Unit
    Please make flare after inserting flare nut (locate at joint portion
    of tube assembly) onto the copper pipe. (In case of using long
    piping)
    Conne ct the piping
     
        • 
    • •  • 
    Align the center of piping and sufficie ntly tighten the flare
    nut with fingers.
     
        • 
    • •  • 
    Further tighten the flare nut with torque wrench in specified
    torque as stated in the table.
    MODELPiping size (Torque)
    GasLiquid
    XC9CK3/8”(42 N.m)1/4”(18 N.m)
    XC12CK1/2”(55 N.m)1/4”(18 N.m)
    Connecting The Piping To Outdoor Unit
    Decide piping length and then cut by using pipe cutter. Remove
    burrs from cut edge. Make flare after inserting the flare nut
    (located at valve) onto the copper pipe.
    Align center of piping to valves and then tighten with torque
    wrench to the specified torque as stated in the table.
    45
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							CUTTING ANDFLARING THE PIPING
     1. Please cut using pipe cutter and then remove the burrs.
     2. Remove the burrs by using reamer. If burrs is not
    removed, gas leakage may be caused.
    Turn the piping end down to avoid the metal powder
    entering the pipe.
     3. Please make flare after inserting the flare nut onto the
    copper pipes.
    (1)*
    *Connect the manifold gauge to the service port of 3-way
    valve.
    Measure the pressure.(2)*
    *Keep it for 5-10 minutes.
    Ensure that the pressure indicated on the gauge is the
    same as that of measured during the first time.
    10.3.4. AIR PURGING OF THE PIPING AND INDOOR UNIT
    The remaining air in the Refrigeration cycle which contains moisture may cause malfun ction on thecompressor.
     1. Remove the caps from the 2-way and 3-way valves.
     2. Remove the service-port cap from the3-way valves.
     3. To open the valve, turn the valve stem of 2-way valve counter-clockwise approx. 90°and hold it there for ten seconds, then
    close it.
     4. Check gas-leakage of the connecting portion of the pipings.
    For the left pipings, refer to item 4(A).
     5. To open 2-way valve again, turn the valvestem counter-clockwise until it stops.
    4(A). Checking gas leakage for the left piping.
    46
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							CHECK THE DRAINAGE
     
        • 
    • •  • 
    Open front panel and remove air filters.
    (Drainage checking can be carried out without removing the
    front grille.)
     
        • 
    • •  • 
    Pour a glass of water into the drain traystyrofoam.
     
        • 
    • •  • 
    Ensure that water flows out from drain hose of the indoor
    unit.
    EVALU ATION OF THE PERFORMANCE
     
        • 
    • •  • 
    Operate the unit at cooling operation mode for fifteen
    minutes or more.
     
        • 
    • •  • 
    Measure the temperature of the intake and discharge air.
     
        • 
    • •  • 
    Ensure the difference between the intake temperature and
    the discharge is more than 8°C.
    CHECK ITEMS
    Is there any gas leakage at flare nut connection?
    Has the heat insulation been carried out at flare nut
    connection?
    Is the connecting cable being fixed to terminal board firmly?
    Is the connecting cable being clamped firmly?
    Is the drainage OK?
    (Refer to“Check the drainage”section)
    Is the earth wire connection properly done?
    Is the indoor unit properly hooked to the installation plate?
    Is the power supply voltage complied with rated value?
    Is there any abnormal sound?
    Is the cooling operation normal?
    Is the thermostat operation normal?
    Is the remote control’s LCD operation normal?
    Is the air purifying filter installed?
    10.3.5. CONNECT THECABLE TO THEOUTDOOR UNIT
     1. Remove the control board cover from the unit by loosen ing the screw.
     2. Conne cting cable between indoor unit and outdoo r unit shall be approved polychloropre ne sheathed 5 (XC9CK, XC12CK)×1.5
    mm
    2flexible cord, type designation 245 IEC 57 or heavier cord.
     3. Secure the cable onto the control board with the holder (clamper).
     4. Attach the control board cover back to the original position with the screw.
    10.3.6. PIPEINSULATION
     1. Please carry out insulation at pipe connection portion as mentioned in Indoor/Outdo or Unit Installation Diagram. Please wrap
    the insulated piping end to prevent water from going inside the piping.
     2. If drain hose or connecting piping is in the room (where dew may form), please increase the insulation by using POLY-E FOAM
    with thickness 6 mm or above.
    47
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							10.3.7. OXYGEN TUBE CONNECTION
    Precautions during oxygen tube connection
     1. Tube allowable length and height difference is the same as
    pipes.
     2. Tube should be pulled without folding it along the path of
    refrigerant pipe, providing sufficie nt allowance and cut to
    length.
     
        • 
    • •  • 
    If there is no allowance, tube length will contract when
    temperature changes and it may cause trouble.
     
        • 
    • •  • 
    On the other hand, tube length used without cutting and
    in the form of loop too should be avoided.
     3. When thetube is passed throught the pipe hole, it should
    not form the innerwall of the pipe bends.
    The tube may be pressed to the corner of the hold and
    crushed.
     4. Cutting of tube should be done with cutter or knife, cutting
    suface should be straight and even.
    Finishing should be done and leave no scratches behind .
     5. Tube end’s last 15 mm (the section to be inserted to the
    joint during connection) should be free from any damages.
     6. Take note that the inside of tube should be free from
    stones, dirt, dust, and other impurities.
    Oxygen tube connection
     
        • 
    • •  • 
    Insert oxygen tube into the joint section of indoor unit till it
    fully reaches its limit (about 15mm).
     
        • 
    • •  • 
    Insert into the joint of outdoor unit in the same manne r.
     
        • 
    • •  • 
    If the insert does not fully reach the limit, oxygen may leak
    out from the joint causing abnormal noise. 
        • 
    • •  • 
    In both indoor and outdoor unit, the tube inserted will be
    locked inside the joint by the stopper, and the job is
    complete. To make sure that it’s done properly, pull out
    lightly to check if can be removed.
    Connection check
     
        • 
    • •  • 
    Do connection check after normal running of
    cooling/heatin g/ has been confirmed during trial operation.
    (You cannot do proper oxygen tube connection check
    before normal running has been confirmed during trial
    operation).
     
        • 
    • •  • 
    Operate according to the sequence listed below, and check
    tube connection.
     1. Check if the cap at the air filter (right) inner area of
    oxygen supply section releases air after it has been
    lifted up.
    ( If there is no air release, the cause may be tube
    collape , or the insert at join section not proper. Check
    again and make correction if found not properly done.)
     2. After checking, make sure that you push down the cap
    and return to its original position.
    (If it is not returned to its position, it may cause
    abnormal noise.)
    Finishing
     
        • 
    • •  • 
    Finishin g should be carried out for pipe and drain hose.
     
        • 
    • •  • 
    Refer to 10.3.6 Pipe insulation of outdoo r unit.
    48
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							11 2-way, 3-way Valve
    2-way Valve (Liquid Side)3-way Valve (Gas Side)
    WorksShaft PositionShaft PositionService Port
    ShippingCloseCloseClose
    (With valve cap)(With valve cap)(With cap)
    EvacuationCloseCloseOpen
    (Installation and(Counter-Clockwise)(Clockwise)(Push-pin)
    Re-installation)
    OperationOpenOpenClose
    (With valve cap)(With valve cap)(With cap)
    Pumping downCloseOpenOpen
    (Transferring)(Clockwise)(Counter-Clockwise)(Connected manifold
    gauge)
    EvacuationOpenOpenOpen
    (Servicing)With vacuum pump
    Gas chargingOpenOpenOpen
    (Servicing)(With charging cylinder)
    Pressure checkOpen
    (Servicing)OpenOpen(Connected manifold
    gauge)
    Gas releasingOpen
    (Servicing)OpenOpen(Connected manifold
    gauge)
    49
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    							Required tools: hexago nal wrench, adjustable wrench, torque
    wrenches, wrench to hold the joints and gas leak detector.
    The additio nal gas for air purging has been charged in the
    outdoor unit.
    However, if the flare connections have not been done correctly
    and there gas leaks, a gas cylinde r and the charge set will be
    needed.
     1. Recheck the piping connections.
     2. Open the valvestem of the 2-wayvalvecounter-
    clockwise approximately 90°,wait 10seconds, and
    then set it to closed position.
     
        • 
    • •  • 
    Be sure to use a hexago nal wrench to operate the valve
    stem.
     3. Check for gas leakage.
     
        • 
    • •  • 
    Check the flare connection for gas leakage.
     4. Purge the air from the system
     
        • 
    • •  • 
    Set the 2-way valve to the open position and remove the
    cap from the3-way valve’s service port.
     
        • 
    • •  • 
    Using the hexago nal wrench to press the valve core pin,
    discharge for three seconds and then wait for one
    minute.
    Repea t this three times.
     5. Use torque wrench to tighten theservice port cap to a
    torque of 1.8 kg.m. (18 N.m).The air in the indoor unit and in the piping must be purged. If air
    remains in the refrigeration pipings, it will affect the
    compressor, reduce the cooling capacity, and could lead to a
    malfun ction.
     6. Set the 3-way valve to theopened position.
     7. Mount thevalvestem nuts to the 2-way and 3-way
    valves .
     8. Check for gas leakage.
     
        • 
    • •  • 
    At this time, especiallycheck for gas leakage from the 2-
    way and 3-way’s stem nuts, and from the service port
    cap.
    CautionIf gas leakage is discovered in step (3) above, take
    the following measures:
    If the leaks stop when the piping connections are
    tightened further, continue working from step (4).
    If the gas leaks do not stop when the connections are
    retightened, repair the location of the leak, discharge
    all of the gas through the service port, and then
    recharge with the specified amount of gas from a gas
    cylinder.
    11.1. Air Purging of the Piping and Indoor Unit
    11.1.1. Air purging (Installation)
    Service port cap
    Be sure, using a torque wrench to tighten the service port cap (after using the service port), so that it prevents the gas
    leakage from the refrigerationcycle.
    Procedure:
    50
    CS-XC9C KQ CU-XC 9CKQ / CS-XC12CK Q CU-XC12 CKQ 
    						
    All Panasonic manuals Comments (0)

    Related Manuals for Panasonic Cs Xc12ckq Cs Xc9ckq Repair Manual