Page 91
NDA-24306 CHAPTER 3 Page 63 Revision 1.0 1. MOUNTING OF UNITS AND MODULES Figure 005-1 Procedure for Mounting Units and Modules NAP-200-005 Sheet 1/16 Mounting of Units and Modules START Mounting of Modules, FANU, and TOPU. Mount modules, FAN BOX and TOPU for each cabinet referring to Figure 005-1. END (TOPU) Tighten these screws. Do the same at the rear side, too. (PIM3) Tighten these screws. Do the same at the rear side, too. (PIM2) Tighten these screws. Do the same at the rear side, too. (FAN BOX)...
Page 92
CHAPTER 3 NDA-24306 Pag e 6 4 Revision 1.0 2. INSTALLATION OF FANU Location of FANU (PZ-M369 and three electronic FANs) is shown in Figure 005-2. Depending on your system configuration, mount the FANU in the proper position. Figure 005-2 Locations of FANU NAP-200-005 Sheet 2/16 Mounting of Units and Modules NECNE AX 2400 IMSTO P U located here.FANU is FRONT VIEW NECNEAX 2400 IMSTOPU FA N B OX / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / /...
Page 93
NDA-24306 CHAPTER 3 Page 65 Revision 1.0 [Procedure for FANU on the TOPU] When any IMG is configured by two PIMs or less, the FANU is mounted as shown in Figure 005-3. Because the FANU is already mounted on the TOPU of the cabinet, perform Step 4 through Step 7 only, excepting a special case (Step 1 through Step 3 are not required in the normal cases). STEP 1 : Referring to Figure 005-3, mount the three FANs onto the FAN Mounting Plate. Then, fasten every four screws. STEP 2 : Accommodate the FAN...
Page 94
CHAPTER 3 NDA-24306 Pag e 6 6 Revision 1.0 STEP 4 : Fix a FAN fuse (5.0 A) onto the PZ-M369. Figure 005-4 Attachment of FAN Fuse (PZ-M369) STEP 5 : Connect the FAN cables as shown in Figures 005-5 and 005-6. STEP 6 : Lastly, attach the Top Cover onto the TOPU of the cabinet. Then, fasten the four screws (refer to Figure 005-7). Note:The procedures, Step 4 through Step 6, must be performed at each PBX cabinet adopting 1-PIM or 2-PIM configuration. NAP-200-005 Sheet 4/16 Mounting of Units and Modules...
Page 95
NDA-24306 CHAPTER 3 Page 67 Revision 1.0 Figure 005-5 Cable Connections for FANU on TOPU NAP-200-005 Sheet 5/16 Mounting of Units and Modules TH0 TH1 TH2 FAN FC0 FC1 FC2 TALM0 FAN Note 2 TA L M THM Note 1 PZ-M369 TO P U FA N U TOPU (To p View) Note 1:For details on the FAN connecor (PIM backplane), refer to Figure 005-6. Note 2:For details on the TALM connector (TOPU panel), refer to Figure 005-3. NEAX 24 00 IMSNE C . .. . .. PBX NE CN EA X 2 4 00 I M S ATTENTIONContents Static Sensitive Handling...
Page 96
CHAPTER 3 NDA-24306 Pag e 6 8 Revision 1.0 Figure 005-6 Connection of “FAN” Connector Cable (TOPU-PIM) NAP-200-005 Sheet 6/16 Mounting of Units and Modules TH2 TALM1 TALM0 TH1 TH0 FC0 FC1 FC2ON OFF AutoPWR SWNote PBXTO P U PIM (FAN) (FAN) B W B PZ-M369 ATTENTIONContents Static Sensitive Handling Precautions Required R EAR FA N
Page 97
NDA-24306 CHAPTER 3 Page 69 Revision 1.0 Figure 005-7 Attachment of the Top Cover NAP-200-005 Sheet 7/16 Mounting of Units and Modules NEAX 2 400 IMSNE C Top Cover TOPU PIM Mount the Top Cover onto the TOPU. Then, fasten the four screws using the Phillips screwdriver.
Page 98
CHAPTER 3 NDA-24306 Pag e 7 0 Revision 1.0 [Procedure for FANU in the FAN BOX] When any IMG is configured by three or four PIMs, the FANU must be accommodated within the FAN BOX in the center of the cabinet. Because the FANU is originally mounted on the TOPU as shown in Figure 005-3, relocate the FANU into the dedicated FAN BOX per the Steps below: STEP 7 : Referring to Figure 005-3, remove the FANU from the TOPU. - Remove the two screws fastening the PZ-M369. Then, lift away the PZ-M369. - Remove the...
Page 99
NDA-24306 CHAPTER 3 Page 71 Revision 1.0 Figure 005-8 Relocation of FANU and Insertion into FAN BOX NAP-200-005 Sheet 9/16 Mounting of Units and Modules Note Screws for FAN Mounting Plate Screws for PZ-M369FAN BOX connection bar FAN BOX connection bar Note:Before inserting the FANU into the FAN BOX, connect the FAN cables for “FC0”, “FC1” and “FC2” connectors on the PZ-M369. Refer to Figure 005-9 on the next page. ATTENTIONContents Static Sensitive Handling Precautions Required FR ON T
Page 100
CHAPTER 3 NDA-24306 Pag e 7 2 Revision 1.0 Figure 005-9 FAN Cable Connections for FC0/FC1/FC2 Connectors NAP-200-005 Sheet 10/16 Mounting of Units and Modules FC0 FC1FC2 FA N 0 FA N 1 FA N 2 PZ-M369 Before installing the FANU into the FAN BOX, connect FAN cables as shown below. ATTENTIONContents Static Sensitive Handling Precautions Required