Page 131

CHAPTER 5: SETPOINTS
PQMII POWER QUALITY METER  – INSTRUCTION MANUAL5–45
process control. A minimum of 20 V applied must exist on all voltage inputs before this 
feature will operate.
•POWER FACTOR LEAD 1(2) PICKUP: When a leading power factor equals or exceeds 
the level set by this setpoint , a Power Factor Lead 1(2) condition will occur.
•POWER FACTOR LEAD 1(2) DROPOUT: When a leading power factor drops below this 
level, the Power Factor Lead 1(2) condition will drop out .
•POWER FACTOR LEAD 1(2)...

Page 132

5–46PQMII POWER QUALITY METER  – INSTRUCTION MANUAL
CHAPTER 5: SETPOINTS
5.5.6 Demand Alarms
PATH: SETPOINTS  S4 ALARMS/CONTROL  DEMAND
•PHASE A/B/C/NEUTRAL CURRENT DMD RELAY: Phase/neutral current demand 
detection can either be disabled or used as an alarm or process control. Set this 
setpoint to “Off ” if the feature is not required. Selecting “Alarm” activates the alarm 
relay and displays an alarm message whenever a phase/neutral current demand level 
 DEMAND [] PHASE A CURRENT DMD
RELAY:...

Page 133

CHAPTER 5: SETPOINTS
PQMII POWER QUALITY METER  – INSTRUCTION MANUAL5–47
is equalled or exceeded. Selecting “Aux1”, “Aux2”, or “Aux3” activates the respective 
auxiliary relay with no message displayed. This is intended for process control.
•PHASE A/B/C/NEUTRAL CURRENT DMD LEVEL: When the phase A/B/C/ or neutral 
current demand equals or exceeds this setpoint , a phase A/B/C or neutral demand 
alarm or process control indication occurs.
•3Φ POS/NEG REAL PWR DMD RELAY: Three-phase positive/negative real...

Page 134

5–48PQMII POWER QUALITY METER  – INSTRUCTION MANUAL
CHAPTER 5: SETPOINTS
5.5.7 Pulse Input
PATH: SETPOINTS  S4 ALARMS/CONTROL  PULSE INPUT
•PULSE INPUT 1(4) RELAY: Any of the PQMII switch inputs can be assigned to count 
pulse inputs as shown in 5.3.4 Switch Inputs. This setpoint can be used to give an 
indication (alarm or control) if the programmed level is equaled or exceeded. Set this 
setpoint to “Off ” if the feature is not required. Selecting “Alarm” activates the alarm 
relay and displays an...

Page 135

CHAPTER 5: SETPOINTS
PQMII POWER QUALITY METER  – INSTRUCTION MANUAL5–49
assigned, a PULSE INPUT 1(4) ALARM message will also be displayed. The units in this 
setpoint are determined by the 
S2 SYSTEM SETUP  PULSE INPUT  PULSE INPUT UNITS 
setpoint .
•PULSE INPUT 1(4) DELAY: This setpoint can be used to allow a time delay before the 
assigned relay will energize after the 
PULSE INPUT 1(4) LEVEL has been equaled or 
exceeded.
•TOTALIZED PULSES RELAY: A relay can be selected to operate based upon a...

Page 136

5–50PQMII POWER QUALITY METER  – INSTRUCTION MANUAL
CHAPTER 5: SETPOINTS
•PICKUP TIME: The relay assigned in the TIME RELAY setpoint energizes when the PQMII 
clock time equals or exceeds the time specif ied in this setpoint . Follow the example 
below to set the 
PICKUP TIME.
•DROPOUT TIME: The relay assigned in the 
TIME RELAY setpoint de-energizes when the 
PQMII clock time equals or exceeds the time specif ied in this setpoint . Follow the 
example above to set the 
DROPOUT TIME.
5.5.9 Miscellaneous...

Page 137

CHAPTER 5: SETPOINTS
PQMII POWER QUALITY METER  – INSTRUCTION MANUAL5–51
5.6 S5 Testing
5.6.1 Test Relays and LEDs
PATH: SETPOINTS  S5 TESTING  TEST RELAYS & LEDS
To verify correct operation of output relay wiring, each output relay and status indicator 
can be manually forced on or off via the keypad or serial port .
While the 
OPERATION TEST setpoint is displayed, use the VA L U E keys to scroll to the desired 
output relay and/or status indicator to be tested. As long as the test message remains...

Page 138

5–52PQMII POWER QUALITY METER  – INSTRUCTION MANUAL
CHAPTER 5: SETPOINTS
•SIMULATION ENABLED FOR: Select the desired length of time to enable simulation. 
When the programmed time has elapsed, current and voltage simulation will turn off. 
If “Unlimited” is selected, simulated currents and voltages will be used until simulation 
is turned off via the 
SIMULATION setpoint or via the serial port or until control power is 
removed from the PQMII.
•PHASE A/B/C/NEUTRAL CURRENT: Enter the desired phase and...

Page 139

CHAPTER 5: SETPOINTS
PQMII POWER QUALITY METER  – INSTRUCTION MANUAL5–53
NoteSimulated values for Analog outputs may only be entered while SIMULATION mode is set 
to “On”.
5.6.4 Analog Input
PATH: SETPOINTS  S5 TESTING  ANALOG INPUTS SIMULATION
•SIMULATION: Enter “On” to switch from an actual analog input to the programmed 
simulated value. Set this setpoint “Off ” after simulation is complete.
•SIMULATION ENABLED FOR: Select the desired length of time to run simulation. When 
the programmed time has...

Page 140

5–54PQMII POWER QUALITY METER  – INSTRUCTION MANUAL
CHAPTER 5: SETPOINTS
is turned off via the SIMULATION setpoint or via the serial port or until control power is 
removed from the PQMII.
•SWITCH INPUT A(D): Enter the switch input status (open or closed) to be simulated.
5.6.6 Factory Use Only
PATH: SETPOINTS  S5 TESTING  FACTORY USE ONLY
These messages are for access by GE Multilin personnel only for testing and service.
 FACTORY USE []
ONLYSERVICE PASSCODE:
0Range: N/A 
Start reading GE Pqm 2 Manual