Home > Nitsuko > Communications System > Nitsuko 24i/28i/124i/384i Hardware Manual

Nitsuko 24i/28i/124i/384i Hardware Manual

    Download as PDF Print this page Share this page

    Have a look at the manual Nitsuko 24i/28i/124i/384i Hardware Manual online for free. It’s possible to download the document as PDF or print. UserManuals.tech offer 57 Nitsuko manuals and user’s guides for free. Share the user manual or guide on Facebook, Twitter or Google+.

    							Hardware Manual
    28i/124i/384i 
    						
    							Hardware Manual
    1. Installing
    Cabinets
    2. PCB Installation
    and Startup
    3. Installing
    Extensions and Trunks
    4. Optional
    Equipment
    5. Data
    and SMDR
    6. Specifications
    and Parts
    28i/124i 
    						
    							92601INS08
    January 1999 
    						
    							1. Installing
    Cabinets1-1
    In this section
     . . . . . . . . . . . . . . . .
    Page
    Installing the Cabinets  . . . . . . . . . . . . . . . .1-3
    Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-3
    Before Installing . . . . . . . . . . . . . . . . . . . . . . . 1-3
    Site Requirements. . . . . . . . . . . . . . . . . . . . . . 1-3
    Removing the 28i Covers . . . . . . . . . . . . . . . . 1-4
    Mounting the 28i Cabinets . . . . . . . . . . . . . . . 1-4
    Removing the 124i Covers . . . . . . . . . . . . . . . 1-5
    Mounting the 124i Cabinets . . . . . . . . . . . . . . 1-5
    Connecting Expansion Cabinets . . . . . . . . .1-8
    Installing EXIFU PCBs . . . . . . . . . . . . . . . . . 1-8
    Grounding the Cabinets  . . . . . . . . . . . . . .1-10
    Connecting the Ground Wires - 28i System . 1-10
    Connecting the Ground Wires - 124i System. 1-11
    Section 1, INSTALLING THE MAIN AND EXPANSION CABINETS 
    						
    							1. Installing
    Cabinets1-3
    Unpacking
    Unpack the equipment and check it against your equipment lists.
    Inspect for physical damage. If you are not sure about a compo-
    nent’s function, review the Product Description Manual. Contact
    your Sales Representative if you have additional questions.
    Have the appropriate tools for the job on hand, including: a test
    set, a punch down tool and a digital voltmeter.
    Before Installing
    Make sure you have a building plan showing the location of
    the common equipment, extensions, the telco demarcation and
    earth ground. In addition, the installation site must meet the
    requirements outlined in the Standard Practices Manual.
    Site Requirements
    The common equipment is contained in three wall-mounted cab-
    inets: the Main Cabinet and two Expansion Cabinets. Choose a
    central location for the cabinets that allows enough space for the
    equipment — and provides enough room for you to comfortably
    work. The Installation Layout (Figure 1-4 and Figure 1-5 on
    pages 1-6 and 1-7) shows you abouthow much space your sys-
    tem requires.
    Each common equipment cabinet requires a three-prong dedi-
    cated 110 VAC 60 Hz circuit (NEMA 5-15 receptacle) located
    within 7 feet of the AC receptacle. You should install the exten-
    sion and trunk blocks to the right of the Main Cabinet. Telco
    should also install the RJ21X to the right of the Main Cabinet.
    INSTALLING THE CABINETS 
    						
    							1. Installing
    Cabinets
    1-4
    Removing the 28i Cover(Figure 1-1)
    To make installation easier, remove the cover on the KSU.
    1. Unscrew the two captive screws on the front of the cabinet
    cover.
    2. Lift up slightly on the front of the cover – then gently slide
    the cover back to remove it.
    Figure 1-1  REMOVING THE 28i COVER
    Mounting the 28i Cabinet(Figure 1-2)
    1. Using the screws provided, attach the metal bracket to the
    Main Distribution Frame (MDF) plywood backboard. Mount
    the bracket in a convenient location, about 12” higher than
    where you want the bottom of the cabinet to line up.
    2. Hang the KSU on the metal bracket.
    3. Install two mounting screws (provided) in the lower left and right
    hand corners of the KSU to secure it to the plywood backboard.
    The right side panel of the KSU can also be taken off by
    removing the screws at the top and bottom of the side panel.
    Figure 1-2  HANGING THE 28i CABINET
    80000 - 13
    80000 - 12
    INSTALLING THE 28i CABINET 
    						
    							1. Installing
    Cabinets1-5
    Removing the 124i Covers(Figure 1-3)
    To make wall-mounting easier, remove the cover on each com-
    mon equipment cabinet. This allows you to use the cabinets as a
    mounting template.
    1. Unscrew the two captive screws on the right side of the cabi-
    net cover.
    2. Lift up the right side of the cover — then slide the cover to
    the left to remove it.
    Figure 1-3  REMOVING THE 124i COVER
    Mounting the 124i Cabinets(Figure 1-4 and Figure
    1-5)
    1. Using suitable fasteners, mount a Main Distribution Frame
    (MDF) plywood backboard in a centrally located spot.
    2. Hold the Main Cabinet against the MDF and mark all four
    mounting holes.
    3. Drill the marked holes using a 1/8” drill bit.
    4. Install two mounting screws (provided) in the top two holes,
    leaving about 3/8” shank exposed.
    5. Hang the Main Cabinet on the top two screws and fasten in
    place.
    6. Install the bottom two screws and tighten in place.
    7. Following the procedure above, install the expansion cabi-
    nets (if required). 
    92001 - 29
    INSTALLING THE 124i CABINETS 
    						
    							1. Installing
    Cabinets
    1-6
    Figure 1-4  28i INSTALLATION LAYOUT
    Continued on next page. . .
    80000 - 15
    Plywood backboard
    Dedicated
    AC Outlet
    Surge
    ProtectorTo earth
    ground To telco
    groundStation
    BlocksStation
    Blocks Trunk
    Blocks
    4
    4
    INSTALLING THE CABINETS 
    						
    							1. Installing
    Cabinets1-7
    INSTALLING THE CABINETS
    Figure 1-5  INSTALLATION LAYOUT
    To Verified
    Earth Ground
    Note: Each cabinet
    is shown in a typical
    8 x 24 configuration.
    Dedicated
    AC Outlet
    Dedicated
    AC Outlet
    Dedicated
    AC Outlet Surge
    Protector
    Surge
    Protector
    Surge
    ProtectorPlywood Backboard
    To
    Telco To
    Telco To
    Telco
    To
    Stations To
    Stations To
    Stations
    Trunk Blocks Trunk Blocks Trunk Blocks
    Station Blocks Station Blocks Station Blocks
    4’
    4’
    Expansion Cabinet #1
    Main Cabinet Expansion Cabinet #2 
    						
    							1. Installing
    Cabinets
    1-8
    Installing EXIFU PCBs on the 124i(Figure 1-6)
    Each 124i expansion cabinet requires an EXIFU Expansion
    Interface PCB.
    To connect Expansion Cabinet #1 to the Main
    Cabinet:
    1. In Expansion Cabinet #1, plug the EXIFU PCB into the first
    (CPRU) slot.
    2. Plug the EXIFU PCB ribbon cables into the two connectors
    at the top of the Main Cabinet backplane.
    3. Install the ferrite filters as shown.
    4. Install the metal strain reliefs in both the Main and
    Expansion #1 cabinets.To connect Expansion Cabinet #1 to Expansion
    Cabinet #2:
    1. In Expansion Cabinet #2, plug the EXIFU PCB into the first
    (CPRU) slot.
    2. Plug the EXIFU PCB ribbon cables into the two connectors
    at the top of Expansion Cabinet #1.
    3. Install the metal strain reliefs in both expansion cabinets.
    CONNECTING EXPANSION CABINETS 
    						
    All Nitsuko manuals Comments (0)