Page 231
NDA-24234 CHAPTER 3 Page 201 Revision 3.0 INSTALLATION PROCEDURE 1. CROSS CONNECTION OF STATIONS Note 1: Provide the necessary cross connections at the MDF by using copper wires of 0.5 mm diameter (24 AWG). 2-core twisted wire is used for speech path, and single-core wire is used for control wire. It is recommended that wires of different colors be used for trunks, station lines, PFT, etc., so that they can easily be distin- guished. Note 2:For cross connections between stations and C.O. lines for PFT,...
Page 232
CHAPTER 3 NDA-24234 Pag e 20 2 Revision 3.0 INSTALLATION PROCEDURE 2. CROSS CONNECTION OF TRUNKS (C.O. LINES AND TIE LINES) Note 1: Provide the necessary cross connections at the MDF by using copper wires of 0.5 mm diameter (24 AWG). 2-core twisted wire is used for speech path, and single-core wire is used for control wire. It is recommended that wires of different colors be used for trunks, station lines, PFT, etc., so that they can easily be distin- guished. Note 2:For cross connections between...
Page 233
NDA-24234 CHAPTER 3 Page 203 Revision 3.0 INSTALLATION PROCEDURE Figure 015-2 Cross Connection of Trunks (C.O. Lines and Tie Lines) NAP-200-015 Sheet 4/30 Cable Termination and Cross Connections from MDF to Peripheral Equipment, C. O. Lines, and Tie Lines AX BX 16COT CARDC.O. LINE Module Group Side AX BX 8TLT CARDTIE LINE TA X RAX 8TLT CARD TIE LINE EX MX TBX RBX (1) 16COT card (3) 8TLT card (for E&M Trunk) (2) 8TLT card (for DID Trunk) Note 1 Note 1:For 2W/4W E&M systems, these leads are not...
Page 234
CHAPTER 3 NDA-24234 Pag e 20 4 Revision 3.0 INSTALLATION PROCEDURE 3. CROSS CONNECTIONS FOR PFT Note 1: The COT must be accommodated in a universal slot of the same Unit (U) in which the cross-connected PFT is mounted. See the figure below. Note 2:Provide the necessary cross connections at the MDF by using copper wires of 0.5 mm diameter (24 AWG). 2-core twisted wire is used for speech path, and single-core wire is used for control wire. It is recommended that wires of different colors be used for...
Page 235
NDA-24234 CHAPTER 3 Page 205 Revision 3.0 INSTALLATION PROCEDURE NAP-200-015 Sheet 6/30 Cable Termination and Cross Connections from MDF to Peripheral Equipment, C. O. Lines, and Tie Lines START Check the terminal locations on the Module Group side of the MDFReferring to Section 1., “CROSS CONNECTION OF STATIONS” and Section 2., “CROSS CONNECTION OF TRUNKS (C.O. LINES AND TIE LINES)” in this NAP, identify the lead names of the stations and trunks to be connected to the PFT (NCU) card and the...
Page 236
CHAPTER 3 NDA-24234 Pag e 20 6 Revision 3.0 INSTALLATION PROCEDURE Figure 015-4 Cross Connection for PFT NAP-200-015 Sheet 7/30 Cable Termination and Cross Connections from MDF to Peripheral Equipment, C. O. Lines, and Tie Lines PBX COT PFT(PA-M53) CardLT AXX BXX LT AXX BXX MDF MDF NCU ROXX TOXX RIXX TIXX NCU AOXX BOXX AIXX BIXX Analog TelephoneInstallation Cable : When PIM Power is OFF : When PIM Power is ON LC Central Office
Page 237
NDA-24234 CHAPTER 3 Page 207 Revision 3.0 INSTALLATION PROCEDURE 4. CROSS CONNECTION OF ALARM INDICATING PANEL AND MUSIC ON HOLD Note: Provide the necessary cross connections at the MDF by using copper wires of 0.5 mm diameter (24 AWG). 2-core twisted wire is used for speech path, and single-core wire is used for control wire. It is recommended that wires of different colors be used for trunks, station lines, PFT, etc., so that they can easily be distin- guished. Alarm Indicating Panel Music On Hold...
Page 238
CHAPTER 3 NDA-24234 Pag e 20 8 Revision 3.0 INSTALLATION PROCEDURE Figure 015-5 Connection of Alarm Indicating Panel and Music on Hold (Single IMG Configuration) NAP-200-015 Sheet 9/30 Cable Termination and Cross Connections from MDF to Peripheral Equipment, C. O. Lines, and Tie Lines Locations of Terminal and Connector General Cable Connection for Alarm Indicating Panel FRONT VIEW REAR VIEW LPR BASEU BZ-C21 RPT Terminal (PZ-M377) TPWR FA L M -48VGND (RPT0) (RPT1)EXALM LPR BASEU FRONT VIEW REAR...
Page 239
NDA-24234 CHAPTER 3 Page 209 Revision 3.0 INSTALLATION PROCEDURE Figure 015-5 Connection of Alarm Indicating Panel and Music on Hold (Single IMG Configuration) (2/2) NAP-200-015 Sheet 10/30 Cable Termination and Cross Connections from MDF to Peripheral Equipment, C. O. Lines, and Tie Lines 16 PH EXALM CA cable Pin Assignment16 PH EXALM CA and Installation Cable (25P) MDF MUSIC SOURCE Audible and Visual Alarm Indicating Panel MN BELL MJ FM0 E MJA MNA BELL MJB MNB RPT1 (G) RPT0 (48v) PIN No. 26 27 28...
Page 240
CHAPTER 3 NDA-24234 Pag e 21 0 Revision 3.0 INSTALLATION PROCEDURE Figure 015-6 Connection of Alarm Indicating Panel (Multiple IMG Configuration) (1/2) NAP-200-015 Sheet 11/30 Cable Termination and Cross Connections from MDF to Peripheral Equipment, C. O. Lines, and Tie Lines Locations of Terminal and Connector General Cable Connection for Alarm Indicating Panel FRONT VIEW RPT Terminal (PZ-M377) TPWR FA L M -48VGND (RPT0) (RPT1) LPR BASEU FRONT VIEW REAR VIEW 01234 12 34 512 34 5 LPR LPR BSCF -48V...