Page 41
1. The inside and outside connecting cable can be connected without removing the front grille. 2. Connecting cable between indoor unit and outdoor unit shall be approved polychloroprene sheathed 4 × 1.5 mm 2 flexible cord, typedesignation 245 IEC 57 or heavier cord. • Ensure the color of wires of outdoor unit and the terminal Nos. are the same to the indoor’s respectively. • Earth lead wire shall be longer than the other lead wires as shown in the figure forthe electrical safetyin case of the...
Page 42
HOW TO TAKE OUT FRONT GRILLE Please follow the steps below to take out front grille if necessary such as when servicing. 1. Open the intake grille and remove the screw at the front of the front grille. 2. Set the vertical airflow direction louver to the horizontal position. 3. Slide down the 2 caps on the front grille as shown in the illustration below, and then remove the 2 mounting screws. 4. Pull the lower section of the front grille towards you to remove the front grille. When reinstalling the...
Page 43
10.6. Outdoor unit 10.6.2. INSTALL THE OUTDOOR UNIT • After selecting the best location, start installation according to Indoor/Outdoor Unit Installation Diagram. 1. Fix the unit on concreteor rigid frame firmly and horizontally by bolt nut. (ø10 mm). 2. When installing at roof, please consider strong wind and earthquake. Please fasten theinstallation standfirmly with bolt or nails. 10.6.3. CONNECTING THE PIPING Connecting The Piping To Indoor Unit Please make flare after inserting flare nut (locate...
Page 44
CUTTING AND FLARING THE PIPING 1. Please cut using pipe cutter and then remove the burrs. 2. Remove the burrs by using reamer. If burrs is not removed, gas leakage may be caused. Turn the piping end down to avoid the metal powder entering the pipe. 3. Please make flare after inserting the flare nut onto the copper pipes. 10.6.4. AIR PURGING OF THE PIPING AND INDOOR UNIT 1) Checking gas leakage 1. Remove the service-portcap from both3-wayvalves. 2. Connect the manifold gauge set tothe service port...
Page 45
The air which contains remaining moisture in the refrigeration cycle may cause a malfunction on the compressor. 1. To purge the air, push the pin on the gas side 3-way valve for three seconds using with a hexagonal wrench and set it free for one minute. • Repeat this three times. 2. To balance the refrigerant, close the low pressure side valve on the manifold gauge and release a refrigerant from the piping through service port until the gauge indicates 0.49 ~ 0.294 MPa. 3. Set theboth 3-wayvalves to...
Page 46
10.6.6. PIPE INSULATION CHECK THEDRAINAGE • Open front panel and remove air filters. (Drainage checking can be carriedout without removing the front grille.) • Pour a glass of water into the drain tray-styrofoam. • Ensure that water flows out from drain hose of the indoor unit. EVALUATION OF THEPERFORMANCE • Operate the unit at cooling operation mode for fifteen minutes or more. • Measure the temperature of the intake and discharge air. • Ensure the difference between the intake temperature and the...
Page 47
11 3-way Valve 3-way Valve (Liquid Side)3-way Valve (Gas Side) WorksShaft PositionService PortShaft PositionService Port ShippingClosedClosedClosedClosed (With valve cap)(With cap)(With valve cap)(With cap) Air purgingClosedOpenClosedOpen (Installation and(Clockwise)(Connected manifo ld(Clockwise)(Push-pin) Re-installation)gauge w/charging cylinder) OperationOpenClosedOpenClosed (With valve cap)(With cap)(With valve cap)(With cap) Pumping downClosedClosedOpenOpen (Transferring)(Clockwise)(With...
Page 48
11.1. Air purging Required tools: Hexagonal wrench, adjustable wrench, torque wrenches, wrench to hold the joints, gas leak detector, and charging set. 1. Recheck the piping connections. 2. Open thevalve of the lowpressure side of Manifold gauge counter-clockwise for 10 seconds, and then close it. 3. Check for gas leakage. • Check the flare connections for gas leakage. 4. Purge the air from the system. • Open the Low pressure side valve of the manifold gauge. • Press the valve core pin with the...
Page 49
11.2. Pumping down 1. Confirm that both the 3-wayvalves are setto the open position. • Remove the valve stem caps and confirm that the valve stems are in the raised position. • Be sure to use a hexagonal wrench to operate the valve stems. 2. Operate the unit for 10 to 15 minutes. 3. Stop operation and wait for 3 minutes, then connect the charge set to the serviceport of the3-wayvalves. • Connect the charge hose with the push pin to the gas side service port. 4. Air purging of the charge hose. •...
Page 50
(Re-installation) 1. Remove the capnut from3-wayvalves. • Remove the cap nutfrom 3-wayvalves after carefully checked whether the piping connection was properly and certainly done. 2. Confirm that thevalve inboth3-wayvalves are set to the CLOSED position. 3. Connect the gas cylinder to the liquid-side (high- pressure) 3-wayvalve andthe charge set to the gas side (low-pressure) 3-wayvalve. • Remove the flare nut from the service port to connect the charge set and gas cylinder. • Close the valves on...