Page 161

CHAPTER 6 NDA-24299
Page 146
Revision 1.0
POST INSTALLATION TEST
Repair Procedure When LED Indicates Abnormality
1.1 How to check LYR LED
1. Confirm the LYR LED lights green on the front edge of the FCH (PA-FCHA) circuit card. (See “LED
Indication (A)” in Figure 6-2.) When the LED lights green, the fusion link is established.
2. Make sure that any alarm LED is not ON (red/yellow). (See LED Indication (B) in Figure 6-2.)
When all alarm LEDs are OFF, the DTI (PA-24DTR) card is in normal operation.
If any...

Page 162

NDA-24299 CHAPTER 6
Page 147
Revision 1.0
POST INSTALLATION TEST
Repair Procedure When LED Indicates Abnormality
2.1 Front Cable
Make sure that front cable 10AL (10) FLT CA is securely inserted into the connectors.
FCH (PA-FCHA) switch setting
Make sure that the following keys are set properly:
Dch TS designation (0ch - 23ch: SW11, SW12, SW13)
Data Link Signal Logic (positive/negative: SW14-1)
Fusion Data Link Speed (48/56/64 kbps: SW14-2, 3)
LAPD Signal Link (user/network: SW14-4)
24DTI (PA-24DTR)...

Page 163

CHAPTER 6 NDA-24299
Page 148
Revision 1.0
POST INSTALLATION TEST
Repair Procedure When LED Indicates Abnormality
2.2.2 Loopback Point Designation
The DTI card can be set at one of the following loopback points:
1. Internal Loopback
All 24 B-channels sent from the TSW are looped back to the TSW at Interface on the card. At this
time, the adjacent node detects AIS signals. (See  
    in Figure 6-4.) 
2. Line Loopback
All 24 B-channels sent from the line are looped back to the line at Line Interface on the...

Page 164

NDA-24299 CHAPTER 6
Page 149
Revision 1.0
POST INSTALLATION TEST
Repair Procedure When LED Indicates Abnormality
Figure 6-5   How to Set the Fusion Link Test Mode
STEP 2: Select an appropriate loopback point by setting the switch (SW01/SW13B). Refer to Figure 6-6.
Figure 6-6   Loopback Point Designation
STEP 3: When the LYR LED flashes at 60-INT, the loopback in the block specified in Step 2 is OK. Refer to
Figure 6-7.
Note:Be sure to initialize the FCH (PA-FCHA) card after changing the setting of the...

Page 165

CHAPTER 6 NDA-24299
Page 150
Revision 1.0
POST INSTALLATION TEST
FCCS Network Connection Test
Figure 6-7   Fusion Link-Test Results
STEP 4: Return Mode to 8 (standard setting) when the test is complete.
STEP 5: Initialize the FCH (PA-FCHA) card using the MB switch.
Note:Be sure to initialize the FCH (PA-FCHA) card after changing the setting of the Mode Switch.
3. FCCS Network Connection Test
This section explains how to perform the following connection tests within the Fusion network:
Station-to-Station...

Page 166

NDA-24299 CHAPTER 6
Page 151
Revision 1.0
POST INSTALLATION TEST
FCCS Network Connection Test
STEP 3: Dial a telephone number (STN B) that belongs to another node.
STEP 4: The call terminates on STN B.
STEP 5: Confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 6: Replace the handset of STN A.
STEP 7: Repeat the above steps for all Fusion links.
3.1.2 FCCS Call Termination Test
STEP 1: Using the MBCT command, make busy all trunks in the origination route except the trunk...

Page 167

CHAPTER 6 NDA-24299
Page 152
Revision 1.0
POST INSTALLATION TEST
FCCS Network Connection Test
3.2.1 ATTCON Call Origination Test
STEP 1: Dial the operator access code (normally “0”), from STN A in Node A.
STEP 2: Confirm that the ATT lamp flashes and ringer sounds at each ATTCON in Node B.
STEP 3: Answer the call by pressing the ATND key.
STEP 4: Confirm the speech condition is sufficient (no noise, not one-party speech, etc.).
STEP 5: Release the call by pressing the CANCEL key.
STEP 6: Replace the...

Page 168

NDA-24299 CHAPTER 6
Page 153
Revision 1.0
POST INSTALLATION TEST
FCCS Network Connection Test
3.3.1 Line Origination Test: Confirmation of Physical/Telephone STN Number
STEP 1: Connect the line circuit card to be tested to a telephone set in Node A (self-Node).
STEP 2: Lift the handset of STN A and confirm dial tone.
STEP 3: Place a call to an ATTCON or D
term in Node B.
STEP 4: Answer the call and confirm the speech condition and Physical/Telephone (station) number of the
calling station.
STEP 5:...

Page 169

CHAPTER 6 NDA-24299
Page 154
Revision 1.0
POST INSTALLATION TEST
FCCS Network Connection Test
STEP 1: Using the MBTK Command, make busy all 3-party Conference Trunk (CFTs) except the trunk to be
tested.
STEP 2: Establish a station-to-station connection between STNs A and B in self-node (Node A). 
STEP 3: STN A goes to Switch Hook Flash (SHF), and after hearing special dial tone, dials the telephone
number of STN C in other node (Node B).
STEP 4: STN C answers the call.
STEP 5: STN A, after a brief talk...

Page 170

NDA-24299 CHAPTER 6
Page 155
Revision 1.0
POST INSTALLATION TEST
Fusion and Non-Fusion Connection Tests
STEP 2: Lift the handset of STN A in self-node (Node A).
STEP 3: Dial the telephone number of STN B that belongs to other node (STN B).
STEP 4: Confirm the speech condition is sufficient (no noise, not one-way speech, etc.).
STEP 5: Replace the handset of STN A.
STEP 6: Make idle all the trunks that were placed in make-busy state in STEP 1.
3.5.2 Alternate Route Trunk Test
STEP 1: Using the MBCT...