NEC Neax 2400 Ipx Fusion Network System Manual
Here you can view all the pages of manual NEC Neax 2400 Ipx Fusion Network System Manual. The NEC manuals for Communications System are available online for free. You can easily download all the documents as PDF.
Page 161
CHAPTER 6 NDA-24299 Page 146 Revision 1.0 POST INSTALLATION TEST Repair Procedure When LED Indicates Abnormality 1.1 How to check LYR LED 1. Confirm the LYR LED lights green on the front edge of the FCH (PA-FCHA) circuit card. (See “LED Indication (A)” in Figure 6-2.) When the LED lights green, the fusion link is established. 2. Make sure that any alarm LED is not ON (red/yellow). (See LED Indication (B) in Figure 6-2.) When all alarm LEDs are OFF, the DTI (PA-24DTR) card is in normal operation. If any...
Page 162
NDA-24299 CHAPTER 6 Page 147 Revision 1.0 POST INSTALLATION TEST Repair Procedure When LED Indicates Abnormality 2.1 Front Cable Make sure that front cable 10AL (10) FLT CA is securely inserted into the connectors. FCH (PA-FCHA) switch setting Make sure that the following keys are set properly: Dch TS designation (0ch - 23ch: SW11, SW12, SW13) Data Link Signal Logic (positive/negative: SW14-1) Fusion Data Link Speed (48/56/64 kbps: SW14-2, 3) LAPD Signal Link (user/network: SW14-4) 24DTI (PA-24DTR)...
Page 163
CHAPTER 6 NDA-24299 Page 148 Revision 1.0 POST INSTALLATION TEST Repair Procedure When LED Indicates Abnormality 2.2.2 Loopback Point Designation The DTI card can be set at one of the following loopback points: 1. Internal Loopback All 24 B-channels sent from the TSW are looped back to the TSW at Interface on the card. At this time, the adjacent node detects AIS signals. (See in Figure 6-4.) 2. Line Loopback All 24 B-channels sent from the line are looped back to the line at Line Interface on the...
Page 164
NDA-24299 CHAPTER 6 Page 149 Revision 1.0 POST INSTALLATION TEST Repair Procedure When LED Indicates Abnormality Figure 6-5 How to Set the Fusion Link Test Mode STEP 2: Select an appropriate loopback point by setting the switch (SW01/SW13B). Refer to Figure 6-6. Figure 6-6 Loopback Point Designation STEP 3: When the LYR LED flashes at 60-INT, the loopback in the block specified in Step 2 is OK. Refer to Figure 6-7. Note:Be sure to initialize the FCH (PA-FCHA) card after changing the setting of the...
Page 165
CHAPTER 6 NDA-24299 Page 150 Revision 1.0 POST INSTALLATION TEST FCCS Network Connection Test Figure 6-7 Fusion Link-Test Results STEP 4: Return Mode to 8 (standard setting) when the test is complete. STEP 5: Initialize the FCH (PA-FCHA) card using the MB switch. Note:Be sure to initialize the FCH (PA-FCHA) card after changing the setting of the Mode Switch. 3. FCCS Network Connection Test This section explains how to perform the following connection tests within the Fusion network: Station-to-Station...
Page 166
NDA-24299 CHAPTER 6 Page 151 Revision 1.0 POST INSTALLATION TEST FCCS Network Connection Test STEP 3: Dial a telephone number (STN B) that belongs to another node. STEP 4: The call terminates on STN B. STEP 5: Confirm the speech condition is sufficient (no noise, not one-way speech, etc.). STEP 6: Replace the handset of STN A. STEP 7: Repeat the above steps for all Fusion links. 3.1.2 FCCS Call Termination Test STEP 1: Using the MBCT command, make busy all trunks in the origination route except the trunk...
Page 167
CHAPTER 6 NDA-24299 Page 152 Revision 1.0 POST INSTALLATION TEST FCCS Network Connection Test 3.2.1 ATTCON Call Origination Test STEP 1: Dial the operator access code (normally “0”), from STN A in Node A. STEP 2: Confirm that the ATT lamp flashes and ringer sounds at each ATTCON in Node B. STEP 3: Answer the call by pressing the ATND key. STEP 4: Confirm the speech condition is sufficient (no noise, not one-party speech, etc.). STEP 5: Release the call by pressing the CANCEL key. STEP 6: Replace the...
Page 168
NDA-24299 CHAPTER 6 Page 153 Revision 1.0 POST INSTALLATION TEST FCCS Network Connection Test 3.3.1 Line Origination Test: Confirmation of Physical/Telephone STN Number STEP 1: Connect the line circuit card to be tested to a telephone set in Node A (self-Node). STEP 2: Lift the handset of STN A and confirm dial tone. STEP 3: Place a call to an ATTCON or D term in Node B. STEP 4: Answer the call and confirm the speech condition and Physical/Telephone (station) number of the calling station. STEP 5:...
Page 169
CHAPTER 6 NDA-24299 Page 154 Revision 1.0 POST INSTALLATION TEST FCCS Network Connection Test STEP 1: Using the MBTK Command, make busy all 3-party Conference Trunk (CFTs) except the trunk to be tested. STEP 2: Establish a station-to-station connection between STNs A and B in self-node (Node A). STEP 3: STN A goes to Switch Hook Flash (SHF), and after hearing special dial tone, dials the telephone number of STN C in other node (Node B). STEP 4: STN C answers the call. STEP 5: STN A, after a brief talk...
Page 170
NDA-24299 CHAPTER 6 Page 155 Revision 1.0 POST INSTALLATION TEST Fusion and Non-Fusion Connection Tests STEP 2: Lift the handset of STN A in self-node (Node A). STEP 3: Dial the telephone number of STN B that belongs to other node (STN B). STEP 4: Confirm the speech condition is sufficient (no noise, not one-way speech, etc.). STEP 5: Replace the handset of STN A. STEP 6: Make idle all the trunks that were placed in make-busy state in STEP 1. 3.5.2 Alternate Route Trunk Test STEP 1: Using the MBCT...